Loading...
HomeMy WebLinkAbout12 Pioneer Trail Pipeline Award• Tahoe Donner Subdivision • 5,600 single-family residences • 400 multi -family residences • Other development — Clubhouses, golf course, downhill ski area, etc. • 44% of water system customer base • Additional 500 residential units expected at buildout • Served by a single 14-inch diameter pipeline • Two pump stations • Two storage tanks that serve as forebays for the pump stations • Constructed in about 1970 • Approaching end of their useful life • A second pipeline into the Tahoe Donner area is needed • Project identified in the Water System Master Plan • 16-inch pipeline • West end connects to existing 16-inch pipeline in Northwoods Blvd. • East end connects to 24-inch pipeline near Comstock Drive • Downsized from 20-inch pipe identified in the Water System Master Plan • Joint trench including 6-inch electrical & 2-inch communication conduit • 3,000 gpm pump station • Located on District -owned property • Near TNT concrete batch plant • Three contracts previously awarded to outside consultants • Water Works Engineers - Design assistance for Trout Creek crossing and hydraulic transient analysis • Sauers Engineering - Pump station design • Helix Environmental Consulting - CEQA review • CEQA Initial Study/Mitigated Negative Declaration • Made public on March 12 • Public comment period closed on April 12 • Board approval for CEQA purposes on May 4 • Overall project broken into two construction contracts • Scope of pipeline contract • Approximately 8,150 feet of 16-inch water pipe • Approximately 7,800 feet of 6-inch and 2-inch conduit • Five fire hydrants • Valves and pipe fittings • Eleven primary power vaults and one switch pad • Construction of a utility crossing of Trout Creek on the existing bridge • Advertising for bids • Began on April 18 • Bid opening on May 19 at 2:00 pm • Two bids were received Bidder Location Bid Price Responsive C&D Contractors Burdick Excavating Grass Valley, CA Carson City, NV $4,497,043 $5,296,845 Yes Yes • Long lead time for 16-inch pipe • 4 to 5 months for delivery • Project schedule • Award of pipeline construction contract - June 1, 2022 • Installation of Trout Creek crossing - Sept -Oct 2022 • Installation of valve at east end of pipeline - Sept -Oct 2022 • Completion of pipeline project - September 2023 • District staff is reviewing 95% submittal for the pump station • Advertising for bid in early June • Bid opening in early July • Bid price from C&D Contractors is $4,497,043 • Ten percent change order allowance is recommended • Total of authorization of $4,950,000 • Joint project between Water and Electric Departments. Cost allocation is: Amount Percentage Water Department $ 3,613,391 80.4% Electric Department $ 883,652 19.6% Change Order Allowance $452,957 10% Total $4,950,000 110% • FY 2022 Water Department budget includes $2,555,000 for the Pioneer Trail Pipeline • Based on the C&D bid price, the Water Department's portion of cost including potential change orders is $3,980,000 • $1,425,000 over budget • Absorbed overtime within the 10-year CIP • Electric Department's portion of cost including potential change orders is $970,000 • Project not specifically identified in FY 2022 of 2023 budgets • Sufficient funds are available in Electric Department Capital Reserve Fund Balance of $11.3 million as of 12/31/2021 • Award of the pipeline construction the constructing the pump station • Budget of $2,865,000 • $350,000 in FY 2022 • $2,515,000 in FY 2023 contract commits the District to project • Both projects are budgeted and recommended to be funded by the water new debt issuance • Authorize the General Manager to execute a contract with C&D Contractors in an amount of $4,497,043, plus a ten percent change order allowance for a total authorization not to exceed $4,950,000 for the Pioneer Trail Pipeline Project