HomeMy WebLinkAbout11, Board Presentation Electric & Water OperationsBudget Item #11
FY14 & FY15 Budget
a)
Operating/Capital
Budget:
Electric Operations
b)
Operating/Capital
Budget:
Water Operations
October 2, 2013
Budget Process Schedule
September 4
• Mission, goals and objectives
• Budget assumptions
• Organization chart
• Labor
• Existing debt
September 18
• Purchased Power Plan
• RPS definition change by CEC
• Overview of Prop 18 process
2
Budget Process Schedule
October 2 (tonight)
• Electric and Water operational and capital budgets
October 16
• Support services operational and capital budgets
• Revenue, rates, fees and charges
• Financial Master Plan
• Electric and Water reserves
• Set public hearing date for budget
3
Budget Process Schedule
November 6
• Draft FY14 & FY15 Budget
• Financial Master Plan
• Water Rate Study
• Public Hearing — Draft budget
• Set public hearing date for water rates
November 20
• Consider adopting budget
N
Budget Process Schedule
January 15
• Public Hearing — Water rates
• Consider adopting water rate ordinance
February 15
• Water rates can become effective
5
Background / History
• District Code requires the District to prepare a two-year budget
• On September 4, Staff presented the following assumptions:
-Annual inflation is expected to be 3%
- New development activity will increase
- No new debt
- No planned electric rate increase in FY14 & FY15
- Estimated water rate annual increase of 3% in FY14 & FY15
- $5 monthly water meter surcharge (7.5%) ends December 31St
- Estimated labor rate increase of 2% in FY14
- Estimated labor rate increase of 3% in FY15
- One IT employee added in FY14
6- One Work Order employee restored in FY15
District Average Annual Spending
Infrastrucl
$6
Establishing
Reserves - $1.8N
5%
Public Information
& Conservation
Programs - $1.51"rll,
4%
Supplies, (Material
& Other - $3.UIM,
8%u
$6.7M, 18%
A Power -
A, 27'%
final Labor -
M, 21
Electric Department
New Information
• Electric Utility revenue
— No rate increase
— Budgeted demand flat in FY14; 1% increase in FY15
• Reorganization of Power Supply/GIS departmental expenses
— Department name changed to IT/GIS department
— All District IT costs and responsibilities consolidated into one
department
— Provides for better management of IT resources
— The 2013 budget and actuals normalized to account for these
changes
New Information
• Electric Operations
— System maintenance
— Tree trimming
— High level of RPS
• Electric Capital Projects
— Master Plan
— SCADA Reliability Improvement
— Donner Lake Substation
— New construction anticipated to increase
compared to recent years
Electric Department
Comparison of FY13, FY14 and FY15 Budgets
(in thousands of dollars)
Budgets
Wariance
FY114
FY15
VS.
vs.
FY13
FY14
FY15
FY13
FY14
Operating Exlpenses
$ 31134
$3126
3,40
4%
4%
Maintenance Expenses
468
459
483
-°%
5%
Total O&M Expenses
$ 3,602
$3,7'28
$ 3,892
%
4%
Capital Expenditures
2,675
2,565
2,636
4%
01%
3%
4%
Total Department Expenditures $ 6,277 $ 6,2913 $ 6,528
11
Electric Department Capital Projects & Equipment
(in thousands of dollars)
FY14 FY15
Rate Funded
Electric (Master Plan Projects $ 484 $ 563
Upgrade Donner Lake Substation 348 809
CAIDA Security 202 -
Routine Replacements
Poles, Reclosures, Regulators, Transformers, Meters 240 250
Distribution Replacements & Improvements 396 418
Line & Extension Upgrades 264 278
Various District Projects 152 160
Total Rate Funded Projects 21086 23568
Replacement Vehicles funded by Vehicle Reserve 479 68
Total Electric Projects $ 21565 $ 21636
12
Water Department
13
New Information
• Water Utility revenue requirements
— Estimated water rate annual increase of 3% in FY14 & FY15
— Budgeted demand 1% annual increase in FY14 & FY15
14
New Information
• Water Operations
— No new employees
— Reduced energy costs for pumping due to increased
efficiencies and pipeline replacement
— Some operational labor shifted to capital projects
• Water Capital Projects
— Pipeline replacement
— Donner view replacement
— Pump station replacement
— Water meter installations
15
Water Department
Comparison of FY13, FY14 and FY15 Budgets
(in thousands of dollars)
Budgets
%Variance
FY114
FY15
Vs.
Vs.,
FY13
FY14
FY15
FY113
FY14
Operating Expenses
$27261
$2,320
$21383
3%
3%
Energy Casts
1,474
1, 36�6
1,367
-111 %
0%
Maintenance Expenses
11410
174'O�5
11446
O�%
2%
Total O&M Expenses
$51145
$5,6�31
$51130
-2%
2%
Capital Expenditures
11575
1187'3
11267
19�%
3%
-48%
-8%
Total Department Expenditures $67726 $6)9�O4 $61397
IV
Water Department Capital Projects & Equipment
(in thousands of dollars)
IW&E!
I W&
Pipeline Replacement
$
11209
$
421
Donner View Replacement
15
_
Misc Facility Renovation
55
-
Pump Station Replacement
-
300
Total Rate Funded Projects
19430
721
'water Meters Funded l by Water Meter surcharge
395
450
Replacement Vehicles funded by Vehicle Reserve
48
Total rater Projects
19873
19267
17
Fiscal Impact
• This budget workshop is part of the overall budget process
that will affect the District's spending for the next two fiscal
years
Recommendation
Review this report and provide comments