Loading...
HomeMy WebLinkAbout7-Consideration of Final Completion of the District Pipeline Replacement – 2013 ProjectAgenda Item # 7 CONSENT To: Board of Directors From: Neil Kaufman Date: October 16, 2013 Subject: Consideration of Final Completion of the District Pipeline Replacement — 2013 Project 1. WHY THIS MATTER IS BEFORE THE BOARD The District Pipeline Replacement - 2013 project is complete. A resolution accepting the project as complete requires Board approval. 2. HISTORY In April 2013, the Board awarded the construction contract for the District Pipeline Replacement - 2013 project to A&K Earthmovers Sparks, Nevada. The project involved replacement of about 2,300 feet of pipeline at five locations in the Tahoe Donner area. A&K began work in late May and completed the construction at the end of August. The original bid price was $489,714.22. At the time of award, the Board also established a 10 percent change order allowance for a total for a total authorization not to exceed $538,700.00. In August 2013, a progress report was presented to the Board. It was also identified that the original change order allowance would likely be exceeded due to issues associated with subsurface water on two of the pipeline segments. In response, the change order allowance was increased from $48,985.78 to $75,000. 3. NEW INFORMATION During the course of the project, 21 change order requests were reviewed by staff and then approved by the General Manager. These change orders totaled $51,769.34 and did not exceed the $75,000 change order allowance established by the Board of Directors. The items generally fell under the following categories: • Additional Work Not Included in the Original Contract: During the course of the project, it was necessary to perform some additional work that was not covered by the original bid items such as removal of a tree and installation of some fire hydrant extensions. These items totaled $8,824.92. Repair of Water Leaks: The old pipelines required repair at three locations to control water such that the new pipeline construction could be performed. The additional time and materials associated with repairing these water leaks is $8,708.26. Field Conditions Differing from the Contract Drawings: The pipeline design along Northwoods Boulevard at Viking Way assumed that the existing sewer laterals were deep enough to allow the new water pipe to be routed above the laterals. However, it was determined that there was insufficient clearance between the existing water and sewer laterals and it was necessary to route the new pipe under the sewer laterals. This results in a deeper trench requiring more excavation and backfill. The costs associated with this work total $10,820.53. • Subsurface Water: Significant volumes of subsurface water were encountered on two of the pipeline segments (Northwoods Boulevard at Norse Avenue & Northwoods Boulevard at above Chamonix Road). This amount of water required changes in backfill materials, equipment and construction methods. The costs total $23,415.63. In addition, there are two items that result in a credit to the District: Reconciliation of Bid Quantities vs. Actual Constructed Quantities: The contract is based on a unit price bid. Attachment 1 shows the differences between bid totals and the amounts actually constructed. This analysis results in a $19,945.00 credit to the District. • TSD repair of broken sewer lateral: A sewer lateral on Davos Drive near Heidi Way has broken during the pipeline construction. This break caused a backup in the lateral that overflowed out the property line cleanout. Upon discovery of the problem, TSD was notified and TSD crews responded to the site. Cleanup of the overflow and repair of the broken lateral was performed by TSD with assistance from A&K Earthmovers. TSD send the District and invoice for $2,852.02 for this work. The District paid TSD directly and the District is due reimbursement from A&K for this cost. In early September, District staff performed a final walkthrough on the project. The work performed is considered complete and should be accepted by the District. Attached is a draft resolution (Attachment 2) accepting the project and directing that a Notice of Completion be filed. 4. FISCAL IMPACT The original bid price was $489,714.22. Once adjustments are made for the items described above, the final contract price is $518,686.54. 5. RECOMMENDATION Adopt a resolution accepting the District Pipeline Replacement - 2013 project as complete and authorize the filing of the Notice of Completion. Michael D. Holley General Manager / Water Utility Manager