HomeMy WebLinkAbout12, SCADA 3 Change OrderAction Item # 12 Consideration of an Increase in the Change Order Authorization for SCADA Reliability Improvement Project - Phase 3 December 18, 2013 Background / History • SCADA Phase 2 — Awarded on June 6, 2012 to Terry Hansen Electric (THE) — Notice of Default issued May 1, 2013 — Contract Addendum and Remediation plan negotiated and issued on June 7, 2013 • SCADA Phase 3 — Awarded on August 7, 2013 to Curtis and Sons, Inc (CSC) 2 New Information • THE has indicated they will do no further work on Phase 2 — Remaining deficiencies need to be addressed — The District is negotiating a deductive change order and project closeout with THE • Construction underway for Phase 3 — Executed change orders amount to about $14,000 — Propose transferring remaining Phase 2 work to the Phase 3 project — Work includes retesting around 150 fibers and performing miscellaneous repairs 3 Fiscal Impact • CSC submitted an estimate of $44,526 for this work • Staff proposes increasing the change order allowance by $507000 • Sufficient funds exist in the Electric Capital budget 0 Recommendation • Authorize an increase in the change order allowance to Curtis and Sons Construction for the SCADA Reliability Improvement Project — Phase 3 from $32,804 to $82,804, for a new project total not to exceed $410,845 5