To: Board of Directors
From: Stephen Hollabaugh, Assistant General Manager
Date: January 12, 2001
Monthly Activity Report
Power Supply Issues:
I am sure that the Board has heard of the power shortages in California that have been in the news.
The District is not affected by these reliability problems. I have been investigating many future power
sources to stabilize the future power supply of the District. I met in Boise with Idaho Power and
UAMPS concerning future power sales to both the District and UAMPS. I am working also with
NCPA and ENRON just to name a few to try to get a good long term power strategy worked out for
the District. Obviously most of my time has been spent trying to make since of the “California Energy
Crisis” as I am sure each of you have seen almost nightly on the news. You might have heard on the
news that Lassen Municipal Utility District (LMUD) in Susanville was caught short during this price
spike and is approximately sixteen million dollars in debt. LMUD plans on raising retail electric rates
125%. When I have something ready for the Board to discuss, I will bring it to the board quickly, as
power supply deals come and go promptly.
I have spoken to several customers concerning the removal of our 11% wholesale energy
credit. Nearly all the comments have been positive with many customers complimenting the
District about our rates and reliability.
I am scheduled to be at a meeting in Salt Lake City Utah the day of the Board meeting, so I will not
be in attendance. If you have any questions, please do not hesitate to call me.
Power Supply Expenses for 2000:
I have calculated our Power Supply Expenses for 2000 to be approximately 4.69 million dollars,
which is about $75,000 under budget. Our cost could have been 21.77 million dollars if we were
subject to the wholesale prices during the year. That’s a 17 million dollar difference.
Labor Management Steering Committee: I am meeting each month with the Labor
Management Steering Committee. Peter Holzmeister, Mary Chapman, and I represent
management. Mike Connell, Rosana Matlock, Patrick Waite and George Caballero. We
have been discussing job descriptions, training and promotion procedures and future
job trends at the District.
GIS Strategic Plan Issue: (Graphical Information System): I have attached a schedule and
update prepared by Ian Fitzgerald.
Geographic Information Systems – Update by Ian Fitzgerald
Currently I have developed a schedule as follows:
Sept 2000 Create GIS Team
Oct 2000 Buy GIS Software; Create Nevada County GIS Data Consortium
Nov 2000
Dec 2000 Final Parcel Data model developed
Jan 2001 AutoCAD Land base complete (contingent on Cranmer Engineering)
Feb 2001
Mar 2001 GIS Land base fully operational
Apr 2001 Water/Electric Data model customization complete
May 2001 Data Conversion
Jun 2001 Data Conversion
July 2001 Data Conversion
Aug 2001 Data Conversion
Sept 2001 Full Facility Data Conversion completed; Customer Data linked to GIS
Oct 2001 Begin Full training of staff in GIS
Begin looking at Outage Management Options
Nov 2001 Tie in SCADA to GIS system software
Dec 2001 Finish staff training in GIS
2002 Implement Outage Management; Incorporate 3-D Land Surface;
Develop GPS Base Stations; Introduce GIS into Field; Development of
Telco Data model and conversion of Telco facilities
As of January 12/2001 the following has been completed:
Parcel Data Model completed in November, 2000
Electric Data Model completed January 11, 2001
Water Data Model to start Mid-February.
Land base completed for Tahoe-Donner, Donner Lake, Airport/Sierra Meadows, and
Devonshire. This is still on target for completion in at end of January and GIS
Implementation of March 2001.
Purchase of GIS software is completed; network implementation will be completed in
early February.
Nevada County GIS Data Consortium has been initialized; next meeting should be in
February.
As a note, it seems all things are going smoothly in the GIS implementation. The above
schedule was developed when I first arrived and seems to be holding very strongly. I do not
foresee and difficulties with maintaining this schedule throughout 2001.