HomeMy WebLinkAbout8 Brockway Pipeline Change order Agenda Item # R Public Utility District Memorandum To: Board of Directors From: Jessica Wilson Date: September 6, 2006 Subject: Change Order No. 1 for the Brockway Transmission Pipeline Project 1. Why this matter is before the board: Approval from the Board of Directors is necessary to issue a Change Order to a construction contract. 2. History: On April 5, 2006, the Board awarded the Brockway Transmission Pipeline project to Vulcan Construction & Maintenance, Inc., in the amount of$2,976,939.00. 3. New information: The pipeline construction from the intersection of Bridge St. and Jibboom St. to the intersection of Martis Dr. and Ranch Way has been completed. As of September 6, approximately 950 feet remains to be constructed along Bridge St. I am requesting a Change Order to the Contract for issues covered under four general items that cover the issues encountered thus far during the pipeline construction. Item 1: As mentioned in the staff reports to the Board, the casing installation under the railroad tracks entailed rock excavation. The contractor interpreted the specifications differently from our intent, which resulted in a meeting with the boring subcontractor on June 7. At the meeting, it was agreed that additional compensation would be negotiated upon completion of the casing. The casing installation was completed on July 18, 2006, almost two months behind schedule. There was over 250 hours of rock excavation logged to install the 175 feet of casing. Based on Vulcan's bid for rock excavation, the claim would have been over $250,000, but after a few discussions the contractor and subcontractor agreed to the amount of$135,042.16. As a result of this rock excavation issue, I will be revising the specifications and bid items related to bore and jack operations for projects that are constructed in the future. Page 1 Item 2: Also mentioned in the staff reports to the Board, the existing pavement along the pipeline alignment was found to be thicker than the 4 inches allowed for in the Bid Documents. The pavement was up to 9-inches thick Downtown and up to 18-inches thick along Brockway. Per the Encroachment permit from the Town, we are required to replace up to 9 inches of the removed pavement. This resulted in Advanced Asphalt placing 47 more tons of asphalt Downtown and 54.5 more tons of asphalt along Brockway. Moreover, Vulcan had to hire Penhall Company to sawcut the pavement along Brockway because Vulcan did not have a large enough blade on their asphalt grinder and the additional time required to sawcut ahead of the trenching operations. Based on the additional costs from Advanced Asphalt for the extra thickness of pavement and from Penhall Company for the asphalt grinding, Vulcan is owed $32,205.59 for this work. Item 3: This item includes the crossing of utilities that were crossed in the field but not shown on the Contract Drawings. Last year, the proposed Brockway Transmission Pipeline alignment was surveyed, picking up all the utilities that were marked in the field. However, it is common practice for utilities to only mark their active lines when an Underground Service Alert (U.S.A.) is called in. There are many abandoned utilities that are not marked, especially in the Downtown area. We attempted to include abandoned lines in the Contract Drawings by going off of the historical drawings and maps we collected from the local utilities, but unknown utilities were still encountered during pipeline construction. When an unknown utility was encountered at an elevation that conflicted with the new pipeline, it was first determined if the utility was active or abandoned. If abandoned, the utility was removed; if active, the new pipeline was routed around the utility. Both options cost Vulcan time and lost productivity. Following is a sampling of the types of unknown utilities encountered in the field: • At Bridge Street and Church, three unknown, steel pipelines were found at an elevation conflicting with the new pipeline. They were determined to be abandoned water pipes and cut out of the way. • North of the bridge on Brockway Road, the gas company marked their 2-inch and 8-inch gas lines, which Vulcan found by hand digging. Thinking they were safely past the gas, they continued to excavate, only to hit another 2-inch gas line, not identified by the gas company. It resulted in a gas leak and the shut-down of the area for most of the morning. Later, the gas company explained that one of the 2- inch gas lines was a vent, which they typically do not mark in the field. • In the Regional Park, an unknown, direct buried electrical line was snapped through by the excavator. Excavation and work stopped until it was determined that the electrical line was not live and abandoned. Vulcan has associated costs for every hour that their crew, rented vehicles, rented equipment, and subcontractors can not work due to unforeseen circumstances. We agreed to the hours and costs incurred by Vulcan for the lost time and productivity. Vulcan is owed $15,414.41 for this item. Item 4: This item covers the field conditions that differed from what was shown on the Contract Drawings. Usually, there is a conflict in elevations at utility crossings. We attempt to make our Contract Drawings as accurate as possible by referring to historical maps collected from the local utilities and measuring depths of manholes, Page 2 storm drain inlets and valve nuts, but there is still a certain amount of uncertainty without potholing every single utility crossing. The following disparities were encountered in the field: • At the Regional Park entrance off of Estates Drive, the existing sewer and water mains were at different elevations than shown in the Contract Drawings, conflicting with the new pipeline's profile. Vulcan was forced to use additional 45 degree bends to get under the existing utilities. • South of the bridge on Brockway Road, an existing 6-inch water main was found to be in a 24-inch case pipe with concrete backfill, conflicting with the new pipeline's profile. Vulcan spent the rest of the day rerouting the new pipeline with 45 degree bends to get over the case pipe. • In Estates Drive, Vulcan could not find the gas as shown on the Drawings and where marked in the field by the gas company, so they called the gas company for help. After a day and a half of searching, Vulcan and the gas company found the line 15 feet away from the original marking. Production came to a standstill until the gas main was found for fear of hitting the line. The associated costs and time that Vulcan's crew, rented vehicles, rented equipment, and subcontractors were working on these changes to the Contract Drawings were agreed upon. Vulcan is owed $36,872.76 for this item. 4. Recommendation: I recommend that the Board authorize Contract Change Order No. 1, in the amount of a $219,534.92 payment to Vulcan Construction & Maintenance, Inc., from the District. At this time, there are two more change order items that I expect to bring to the Board in a Closeout Change Order. The first issue involves rock blasting along Estates Drive and Martis Drive. On three separate occasions, large rocks were encountered along the alignment falling under the Rock Work clause in our specifications. It was determined that blasting the rock would be more economical and quicker than hammering on the rock with a breaker. Although it was a time saver, the blasting of over 120 feet along Estates removed much of the road's asphalt as well. Vulcan Construction will be due additional compensation for the Rock Work and additional asphalt. The second issue involves the Actual vs. Bid Quantities associated with closing out a project. The actual quantities constructed will be measured at the end of the project and compared to the bid quantities, resulting in a credit or debit to the District. Attachments: Change Order Form Page 3 AUG-31-2006 15:09 5592654715 5592654715 P.02i02 TRUCKEE • Change Order Contract Name: Brockway Transmission Pipeline Contract Change Order No: 1 Orig. Contract Amt. $ 2,976,939.00 Days NA Date: September 6, 2005 Prev. Apprd Changes$ 0.00 Days NA Contractor: Vulcan Construction& Maint., Inc. This Change$ 219,534.92 Days NA Revised Contract Amt.$ 3,196,473.92 Days NA This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct, fumish equipment and materials, and perform all work as necessary or required to complete the Change Order Items for a lump sum price agreed upon between the Contractor and District. Increase in (Decrease) Contract Time Description of Changes Contract in Contract Extension Amount $ Amount $ da 1 —Rock Excavation for the Bore&Jack Operation $135,042.16 NA 2—Additional Asphalt $32,205.59 NA 3— Interference with Utilities not shown on the Contract $15,414.41 NA Drawings 4—Field Conditions differ from Contract Drawings $36,872.76 NA Totals $219,534.92 Net change in contract amount(increase or decrease) $219,534.92 The amount of the Contract will be increased by the sum of $219,534.92 and the Contract Time shall not be extended. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete the Change order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Cha Order shall be effective when approved by the District. Accepted: /Contractor Date: 3lOco (Signature) Approved: /District Date: (Signature) Pagel �3. TRUCKEE ER Change Order DistrictPublic Utility Contract Name: Brockway Transmission Pipeline Contract Change Order No: 1 Orig. Contract Amt. $ 2,976,939.00 Days NA Date: September 6, 2005 Prev. Apprd Changes$ 0.00 Days NA Contractor: Vulcan Construction & Maint., Inc. This Change$ 219,534.92 Days NA Revised Contract Amt. $ 3,196,473.92 Days NA This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items for a lump sum price agreed upon between the Contractor and District. Increase in (Decrease) Contract Time Contract in Contract Extension Description of Changes Amount $ Amount $ (days) 1 — Rock Excavation for the Bore&Jack Operation $135,042.16 NA 2—Additional Asphalt $32,205.59 NA 3—Interference with Utilities not shown on the Contract $15,414.41 NA Drawings 4— Field Conditions differ from Contract Drawings $36,872.76 NA Totals $219,534.92 Net change in contract amount(increase or decrease) $219,534.92 The amount of the Contract will be increased by the sum of $219,534.92 and the Contract Time shall not be extended. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete the Change order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the District. Accepted: /Contractor Date: (Signature) Approved: /District Date: (Signature) Page 1