MEETING DATE: December 7, 2022
TO: Board of Directors
FROM: Neil Kaufman, Water System Engineer
Chad Reed, Water Utility Director
SUBJECT: Final Closeout of the District Pipeline Replacement— 2022
Construction Contract
APPROVED BY
Brian C. Wright, General Manage
RECOMMENDATION:
Adopt Resolution 2022-22 accepting the District Pipeline Replacement— 2022 project as
complete and authorize the filing of the Notice of Completion.
BACKGROUND:
In February 2022, the Board awarded the construction contract for the District Pipeline
Replacement — 2022 project to C&D Contractors of Nevada City, California. The project
involved replacement of about 7,000 feet of pipeline at three locations:
• Bull Pine Trail & Donner Trail Road
• Copenhagen Drive
• Swiss Lane
The bid price was $2,681,035. The Board also established a ten percent change order
allowance of $268,965, for a total authorization not to exceed $2,950,000.
During the course of the project, four change order requests were submitted and reviewed
by staff. After review and discussion, the District and C&D agreed on a total of$66,452.86
for these issues. The items were:
• Dewatering, gravel backfill, trench, cut-off walls and additional construction efforts
associated with significant groundwater levels encountered on Donner Trail Road
Page 1 of 3
• Delays associated with an unmarked natural gas lateral on Swiss Lane
• Additional fittings for the pipeline alignment on Copenhagen Drive
• Repairs to the old leaking water line on Copenhagen Drive
In addition to the four change order requests noted above, there are two items that result
in credits to the District.
• The contract is based on a unit price bid. Attachment 1 shows the differences
between bid totals and the amounts actually constructed. This analysis results in
a $62,802 credit to the District.
• The contract documents indicated that the District would furnish meter box
assemblies for two of the pipeline segments (Bull Pine/Donner Trail and Swiss
Lane) and that C&D was responsible for furnishing meter box assemblies for the
third pipeline segment (Copenhagen Drive) since the District did not have enough
meter box assemblies on hand for all of the properties along Copenhagen Drive.
However, due to supply chain issues, C&D was unable to obtain the specified
meter box assembly. In order to facilitate completion of the project during the
summer of 2022, the District agreed to provide some additional meter box
assemblies, with C&D utilizing an acceptable alternate design for the remaining
properties. The District is due a credit of $42,700 for providing this additional
material.
In November, District staff performed a final walkthrough on the project. The work
performed is complete and should be accepted by the District. Attached is a draft
resolution (Attachment 2) accepting the project and directing that a Notice of Completion
be filed.
OBJECTIVES & GOALS:
This item is in support of the following goals and objectives:
District Code1.05.020 Objectives:
3. Provide reliable and high quality water supply and distribution system to meet current
and future needs.
Strategic Goals:
1 . Manage for Financial Stability and Resiliency (1.7. Water meter Testing and
Replacement program)
Page 2 of 3
FISCAL IMPACT:
The original bid price was $2,681,035. Once adjustments are made for the items
described above, the final contract price is $2,641,985.86.
Item Amount
Original bid price $2,681,035.00
Approved change order requests $66,452.86
Reconciliation of bid vs. actual quantities ($62,802.00)
Credit for District-furnished materials $42,700.00
Total $2,641,985.86
The funding source for this project is the Water Department General Fund. In addition to
the amount paid to C&D Contractors, the District has incurred additional outside expenses
for pre-construction environmental surveys, construction inspection, and geotechnical
testing.
ATTACHMENTS:
Bid Quantity vs. Actual Quantity Analysis
Resolution 2022-22
Page 3 of 3