Introduction
The California Air Resources Board's (CARB) Low Carbon Fuel Standard (LCFS)
regulation, which appears at sections 95480 to 95503 of title 17, California Code of
Regulations, is designed to reduce greenhouse gas emissions associated with the life
cycle of transportation fuels used in California. CARB staff has prepared this guidance
document to describe the regulatory requirements in a user-friendly format. Unlike the
regulation itself, this document does not have the force of law. It is not intended to
and cannot establish new mandatory requirements beyond those that are already in
the LCFS regulation, nor can it supplant, replace, or amend any of the legal
requirements of the regulation. Conversely, any omission or truncation of regulatory
requirements does not relieve entities of their legal obligation to fully comply with all
requirements of the regulation.
Purpose
This guidance document is designed to summarize and describe requirements for
spending proceeds from the sale of credits issued by the CARB Executive Officer for
using electricity pathways (referred to as "electricity credits"). Electricity credits are
issued to Load Serving Entities (LSE), including Electrical Distribution Utilities (EDU),
and non-LSEs. Entities must report their spending in an Annual Report submitted to
CARB via the LCFS Reporting Tool (LRT) by April 30th of the following year. A template
is available for entities to record and submit the required information for their
electricity credit proceeds spending in their Annual Report on the guidance document
webpage.' The template is further discussed in the penultimate section of this
document.
1 https:llww2.arb.ca.govlour-work/programs/low-carbon-fuel-standardlicfs-guidance-documents-user-
guides-and-faqs
1
This guidance document addresses regulations in sections 95491(d)(3)(A) and
95483(c)(1)(A)6. of the LCFS regulation.2
Background
The LCFS regulation requires entities generating credits using electricity pathways
("electricity credits") to use the resulting credit proceeds to benefit Electric Vehicle
(EV) drivers and their customers, and generally invest in projects that promote
transportation electrification in California. Electrical Distribution Utilities have
additional spending requirements, including minimum contributions to the Clean Fuel
Reward Program and toward equity projects.
EDUs are issued base credits for residential EV charging by the CARB Executive
Officer, who has calculated quarterly the number of credits using a procedure
described in section 95486.1(c)(1). Entities using electricity for non-residential EV
charging, residential incremental credits 4 electric forklifts, electric transport
refrigeration units, electric cargo handling equipment, and shore power for ocean-
going vessels at berth must provide electricity data to the designated entity for LCFS
reporting pursuant to sections 95483.2(b)(8), 95491, and 95491.1. Transit agencies
using electricity for fixed guideway systems are the fuel reporting and entities and
credit generators for electricity used to propel the system, unless the agency decides
to not opt-in to LCFS, where upon the EDU supplying electricity for the system
becomes the credit generator. Entities using other electric transportation applications
must apply to the Executive Officer to be the fuel reporting entity and credit
generator for electricity supplied if it meets the requirements of section 95488.7(a)(3)
and 95491.
Entities are required to report their spending in their Annual Report to LCFS, and are
encouraged to use the provided template, as described in the "Itemized Reporting of
Electricity Credit Proceeds" section of this document. These spending requirements
do not apply to credits resulting from ZEV Fueling Infrastructure pathways.
2 All citations to the LCFS regulation are found in Title 17, California Code of Regulation (CCR), sections
95480-95503.
3 "Base Credit" refers to the credit generated by an LSE for non-metered electric vehicle charging using
carbon intensity values provided in the Lookup Table pathway for California Average Grid Electricity.
4 "Incremental Credit" refers to any credit generated in addition to the base credit for supplying low-CI
electricity to or smart charging for residential EV charging and is calculated using the difference
between the carbon intensity for California Average Grid Electricity and the low-CI electricity source.
2
Spending Requirements for non-Load Serving Entities
Paragraph 7 in section 95491(d)(3)(A) of the LCFS regulation provides specific
requirements for non-LSE use of electricity credit proceeds. These requirements apply
to all credits generated using electricity pathways including incremental credits.'
Non-LSEs are encouraged to use the electricity credit proceeds resulting from a
specific category or sector of electric transportation to invest in transportation
electrification projects in the same category or sector. For example, an entity
generating electricity credits for public EV charging can use the proceeds to
incentivize public EV charging or deploy additional EV charging infrastructure. If it is
not feasible to execute projects in the specific category or sector to promote electric
transportation, entities may propose projects in another category or sector. Ideally,
electricity credit proceeds shall be used for new transportation electrification efforts.
However, proceeds may be used to cover eligible expenses starting the calendar year
in which the entity had opted-in to the LCFS. Examples that would meet the electricity
credit proceeds spending requirements for a non-LSE are:
1. Providing incentive support for purchasing/leasing of EVs or other electric
transportation equipment (for example, electric forklifts, electric cargo handling
equipment, electric transportation refrigeration units, electric buses, electric
trucks, etc.).
2. Providing incentive or direct investment for installing EV charging infrastructure.
3. Providing rebates or other incentive for using electricity as a transportation fuel
(for example, providing discounted or no-cost electricity for transportation
applications, providing discounted or no-cost rides on electric public transit,
etc.).
4. Marketing, education, outreach programs to provide information and material
to inform the public on the benefits of electric transportation. This could include
information regarding the environmental, health and economic benefits of
electric transportation, including a comparison of the total cost of electric
transportation mode versus other alternatives (including the cost of refueling,
servicing and maintenance, etc.).
The above list of examples is not exhaustive. Entities may use electricity credit
proceeds to support other transportation electrification projects which are not
included in the list but would meet the LCFS requirements. Entities may choose to
spend all electricity credit proceeds in a single program or project.
Non-LSEs can refer to the "Itemized Reporting of Electricity Credit Proceeds" section
in this document for guidance in reporting their electricity credit proceeds spending.
5 Entities generating credits for providing low-CI electricity may use credit proceeds from incremental
credits to offset the incremental cost of procuring low-CI electricity or renewable electricity certificates
(RECs) if that incremental cost is not already being paid by other sources.
3
Spending Requirements for Load Serving Entities
LSE refers to a Load-Serving Entity as defined in the LCFS regulation and includes
Electrical Distribution Utilities (EDU) and Community Choice Aggregators (CCA).
Paragraphs 2. through 4. in section 95491(d)(3)(A) of the LCFS regulation provide
specific requirements for an LSE to use electricity credit proceeds.'
Load-serving entities that are Electrical Distribution Utilities that opt-in for base
crediting must contribute a minimum portion of their base credits to the Clean Fuel
Reward program, and a minimum portion of the proceeds from the remaining base
credits, known as "holdback credits," toward equity projects which are discussed in
subsequent sections of this guidance. Remaining electricity credit proceeds must be
spent as described in this section of the guidance.
LSEs are encouraged to use the electricity credit proceeds resulting from a specific
category or sector of electric transportation to invest in transportation electrification
projects in the same category or sector. For example, entities receiving incremental
credits for providing low-CI electricity for residential EV charging can use the proceeds
to provide incentive for additional metered residential charging using low-CI
electricity, including additional metering in residences for EV charging or to lower the
cost of EV charging for residences with metering. If it is not feasible to execute
projects in the specific category or sector to promote electric transportation, entities
may propose projects in another category or sector. Ideally, electricity credit proceeds
shall be used for new transportation electrification efforts. However, proceeds may be
used to cover eligible expenses starting the calendar year in which the entity had
opted into the LCFS.6 Examples that would meet the electricity credit proceeds
spending requirements for an LSE are:
1. Providing incentive support for purchasing/leasing EVs or other electric
transportation equipment (for example, electric forklifts, electric buses, electric
trucks, etc.).
2. Providing incentive or direct investment for installing residential or non-
residential EV charging infrastructure.
3. Providing rate options or incentives to encourage EV charging during off-peak
hours to provide grid benefits.
4. Providing on-bill credit or other incentives to promote use of electric
transportation.
5. Marketing, education, outreach programs to provide information and material
to inform the public on the benefits of EV transportation. This could include
information regarding the environmental, health and economic benefits of EV
6 For example, if an entity registered or a designator was designated for LCFS reporting in Q4 2019,
that entity could use credit proceeds for any eligible transportation electrification related expenses
starting in calendar year 2019. In this case, "entity" means either the default first fuel reporting entity
opting in to the LCFS or designating another entity to participate in the LCFS on their behalf.
4
ownership, including a comparison of the total cost of an EV versus an internal
combustion engine alternative (including the cost of refueling, servicing and
maintenance, etc.)
The above list of examples is not exhaustive. Entities may use electricity credit
proceeds to support other transportation electrification projects which are not
included in the list but would meet the LCFS requirements. Entities may choose to
spend all electricity credit proceeds in a single program or project.
LSEs can refer to the "Itemized Reporting of Electricity Credit Proceeds" section in
this document for guidance in reporting their electricity credit proceeds spending.
Itemized Reporting of Electricity Credit Proceeds
Pursuant to paragraphs 5. and 7. in section 95491(d)(3)(A) of the LCFS regulation, all
entities (LSE and non-LSE) generating electricity credits are required to submit an
itemized summary of efforts and costs associated with meeting electricity credit
proceeds requirements. This itemized summary must be submitted along with Annual
Compliance Report due by April 30 of each year. For this reporting the entity is
encouraged to use the electricity credit proceeds reporting template provided by
CARB. The most updated electricity credit proceeds reporting template can be
downloaded from the LCFS Reporting Tool (LRT) home page? or from the Guidance
webpage.' An Investor-Owned Utility (IOU) must also submit an unredacted copy of
the annual implementation report required under Order 4 of California Public Utilities
Commission of California (CPUC) Decision 14-12-083, or any successor CPUC
Decisions.
ACCOUNTING OF LCFS PROCEEDS FOR ITEMIZED REPORTING
All entities shall include in an itemized summary the following for a complete and
accurate accounting of electricity credit proceeds during the prior calendar year to
demonstrate they have met the electricity credit proceeds requirements.' For
example, the itemized summary submitted by April 30, 2020, would cover the period
during January 1, 2019 to December 31, 2019.
1. Total number of credits carried over from the prior calendar year.
2. Total number of credits generated during the calendar year.
3. Total number of credits sold during the calendar year.
4. Total number of credits carried over to next calendar year.
5. Total proceeds ($) resulting from credits sold during the calendar year.
6. Total number of electricity credits carried over from the prior calendar year.
7. Total number of electricity credits generated during the calendar year.
'A suggested reporting template for the itemized summary is available on the LRT home page and is
also available on the LCFS Guidance Documents, User Guides, and FAQs webpage.
5
8. Total number of electricity credits sold during the calendar year.
9. Total number of electricity credits carried over to next calendar year.
10.Total proceeds ($) resulting from electricity credits sold during the calendar
year.
11.Any electricity credit proceeds ($) carried over from prior calendar year.
12.Total electricity credit proceeds ($) spent during the calendar year.
13.Any electricity credit proceeds ($) earmarked for future use. Provide a brief
description of expected use and timeline, if available.
14.A brief description and breakdown of electricity credit proceeds ($) used during
the calendar year to implement individual projects or programs to benefit EV
drivers and customers, and to promote transportation electrification in
California.
Spending Requirements for Electrical Distribution Utilities:
Clean Fuel Reward Program
Pursuant to section 95483(c)(1)(A), upon California Public Utilities Commission (CPUC)
approval of Pacific Gas and Electric's, Southern California Edison's, and San Diego Gas
and Electric's filing(s) to initiate a Clean Fuel Reward (CFR) program, all opt-in EDUs
must contribute a minimum percent of base credits for residential EV charging (or net
base credit proceeds) to provide a Clean Fuel Reward funded exclusively by LCFS
credit proceeds, as per the contribution tabulated below:
Table 1 : Minimum percentage of base credit and base credit proceeds opt-in EDUs
must contribute to the Clean Fuel Reward Program.
EDU category CFR % Contribution CFR % Contribution
(2019-2022) (2023 and onwards)
Large Investor-owned Utilities 67% 67%
Large Publicly-owned Utilities 35% 45%
Medium Publicly-owned Utilities 20% 25%
Small Publicly-owned Utilities 0% 2%
EDUs must account for all the base credits issued during the reporting period. For
example, the following base credit issuances which occurred in 2021 must be
accounted for 2021 annual reporting:
1. January 2021 issuance
2. April 2021 issuance
3. July 2021 issuance
4. October 2021 issuance
6
To demonstrate that credit proceeds contributed to the CFR program met the
minimum contribution requirement:
• EDUs must use an average credit price based on all their credit sales that were
completed in the reporting year (for example, year 2020).
• If the total credits sold by an EDU are less than the total base credits issued
during the reporting period, for the unsold credit portion, they may use the
annual average credit price for the reporting year as published by CARB in the
Monthly LCFS Credit Transfer Activity Reports.$
Spending Requirements for Electrical Distribution Utilities:
Holdback Credit Equity Projects
The remainder of the base credits issued to an opt-in EDU that are not contributed to
the CFR Program are called "holdback credits." Starting January 1, 2022, all opt-in
EDUs must use a minimum portion of the holdback credit proceeds to support
transportation electrification for the primary benefit of or primarily serving at least one
of the following:
1. Disadvantaged communities
2. Low-income communities
3. Low-income individuals
4. Rural areas
ELIGIBLE PROJECTS
All transportation electrification projects funded through holdback credit equity
proceeds must be for the primary benefit of or primarily serve disadvantaged
communities, low-income communities, low-income individuals, or rural areas.
• A disadvantaged community is a census tract defined by California Health and
Safety Code section 39711(a) and is based on geographic, socioeconomic,
public health, and environmental hazard criteria.
• A low-income community is a census tract with median household income at or
below 80 percent of the statewide median income or with median household
income at or below the threshold designated as low income by the Department
of Housing and Community Development's list of state income limits adopted
pursuant to Health and Safety Code section 50093.
• A low-income individual is an individual who either:
o is eligible under California Alternative Rates for Energy (CARE) or Family
Electric Rate Assistance Program (FERA); or
8 https://ww3.arb.ca.govlfuels/Icfs/creditlirtmonthlycreditreports.htm
7
o is defined by California Health and Safety Code section 50079.5 with a
median household income at or below 80% of the statewide income or at
or below the threshold designated by the California Department of
Housing and Community Development's list of State income limits,9 or
o meets the definition of low-income established by a publicly-owned
electric utility (POU), if that individual lives with the service area of that
POU; or
o is any combination of the above.
• A rural area is a census tract with at least 75% of its population identified as
rural by the latest US Census data. Rural populations live outside urban area
census blocks and urban cluster census blocks, as defined by the US Census.
Projects eligible by being located in disadvantaged and low-income community and
rural areas, and not eligible by benefiting low-income individuals, must be targeted at
publicly available community aspects (e.g., public chargers, public transportation, and
drayage truck electrification).
LCFS staff strongly recommend that EDUs implement projects that avoid substantial
burdens to residents, such as physical or economic displacement of community
residents or businesses.
For projects that include both eligible and not eligible components, the not eligible
components cannot be credited to holdback equity proceeds. Shared costs between
eligible and not eligible components must be pro-rated before being credited to
holdback credit equity proceeds.
Transportation electrification projects identified in the LCFS Regulation can be shown
in the following ways to primarily benefit or primarily serve disadvantaged
communities and/or low-income communities and/or rural areas or low-income
individuals:
i. Electrification and battery swap programs for school or transit buses
The school must be located in, or the buses must make the majority of their
stops in disadvantaged communities, low-income communities, and/or rural
areas; or the majority of bus ridership must be from disadvantaged
communities, low-income communities, and/or rural areas, or low-income
households.
ii. Electrification of drayage trucks
The trucks must operate in or necessarily through a disadvantaged community,
low-income community, and/or rural area, or be owner-operated by a low-
income individual.
9 Available at https://www.hcd.ca.gov/grants-funding/income-limits/state-and-federal-income-
limits.shtml
8
iii. Investment in public EV charging infrastructure and EV charging infrastructure in
multifamily residences
The location of public electric vehicle charging infrastructure must be in a
disadvantaged community, low-income community, or rural area, and no
obstructions of obstacles exist to preclude vehicle operators from entering the
charging premises, no access cards or personal identification codes are
required for the charger to dispense electricity, and no formal or registered
equipment training shall be required for individuals to use the charger.
The location of electric vehicle charging infrastructure in multifamily residences
must be in a disadvantaged community, low-income community, or rural area,
or, for multifamily residences not located in one of these communities,
specifically benefit low-income individuals.
Where applicable, electric vehicle charging spaces must meet the requirements
of the 2019 California Green Building Standards Code.
iv. Investment in electric mobility solutions, such as EV sharing and ride hailing
programs
Rebates and incentives must directly benefit low-income individual drivers or
riders, or the majority of ride endpoints must occur in disadvantaged
communities, low-income communities, or rural areas.
V. Multilingual marketing, education, and outreach
Marketing, education, and outreach must be multi-lingual, accessible, and
primarily directed toward low-income individuals and members of
disadvantaged communities, low-income communities, and/or rural areas.
vi. Additional rebates and incentives for low-income individuals for purchasing or
leasing new or previously owned EVs; installing EV charging infrastructure in
residences; promoting the use of public transit and other clean mobilityr
solutions; and offsetting costs for residential or nonresidential EV charging
The rebates and incentives must be offered to low-income individuals to qualify
as equity spending under this subsection. Where applicable, electric vehicle
charging spaces must meet the requirements of the 2019 California Green
Building Standards Code.
vii. Other transportation electrification projects in disadvantaged communities
and/or low-income communities and/or rural areas or for low-income individuals
can be eligible for funding with holdback credit equity proceeds.
These projects must be approved by the CARB Executive Officer before
implementation. The application process is described in the next section.
9
EXECUTIVE OFFICER APPROVAL PROCESS FOR OTHER
TRANSPORTATION ELECTRIFICATION EQUITY PROJECTS
An EDU may be interested in supporting a transportation electrification project that is
not on this list but could benefit disadvantaged and/or low-income communities
and/or rural areas or for low-income individuals. To qualify as a holdback credit equity
project, such a project must be approved by the CARB Executive Officer based on:
• a description of the project;
• a demonstration that the project promotes transportation electrification for
disadvantaged communities, low-income communities, low-income individuals,
and/or rural areas; and
• evidence the project was developed with and has the expressed support of
local environmental justice advocates, local community-based organizations,
and local municipalities.
o Letters from environmental justice advocates, local community-based
organizations, and local municipalities affirming their participation in the
development of the project and their support of the project.
o Advocates, organizations, and municipalities that represent and work
within communities within a project's boundaries are local. Advocates,
organizations, and municipalities with physical addresses outside of the
State of California and with activities only at a State or Federal level are
not local.
Applicants shall use the LCFS Reporting Tool (LRT)7 Correspondence to submit the
relevant documents.
INELIGIBLE PROJECTS
Holdback credit proceeds must not be used for the following activities, pursuant to
section 95483(c)(1)(A)6.d.:
• to meet compliance obligations;
• to pay for the costs of the Assembly Bill 32 Cost of Implementation Fee
Regulation (COI), Regulation for the Mandatory Reporting of Greenhouse Gas
Emissions (MRR), or the purchase of allowances;
• to pay for lobbying costs, employee bonuses, shareholder dividends, or costs,
penalties, or activities mandated by any legal settlement, administrative
enforcement action, or court order.
ADMINISTRATIVE COSTS
Of the required proceeds encumbered for eligible projects, at least ninety percent
must be spent on costs immediately associated with the implementation of the
projects. No more than ten percent of total annual spending on holdback credit equity
projects may be spent on administrative costs. Administrative costs may include, but
are not limited to:
10
• salaries, wages and benefits of employees who perform administrative
functions, including EDU management, payroll, personnel, accounting, and
budgeting;
• facility and occupancy costs directly associated with administrative functions;
• computer support services;
• training, travel, and licenses directly associated with administrative functions;
• taxes, interest, and general insurance; and
• general expenses.
For projects that have non-equity components, the administrative costs for the equity
components will be pro-rated on a cost basis.
If the EDU contracts with a community-based organization on a project and anticipates
administrative costs consequently will exceed ten percent, the EDU may submit a
request for CARB approval of the exceedance by September 30 of the prior year.
HOLDBACK CREDIT ALLOCATION ACCOUNTING
Proceeds from holdback credits sold after January 1, 2022 must be used, at least in
part, to support equity transportation electrification projects.
Table 1 shows the minimum portion of holdback credit proceeds that must be spent
on eligible equity projects by each opt-in EDU.10 The percentage of holdback credit
proceeds required to be allocated for equity projects will be calculated based on the
year the credits are sold. In year one, 30% of the proceeds must be spent on equity
projects, with increasing percentage requirements in subsequent years. Thus, the
percent of proceeds that must be spent on equity projects from holdback credits
issued in 2022 but not sold until 2024 would be 50%.
Table 2: Minimum percentage of holdback credit proceeds opt-in EDUs must
spend on eligible equity projects.
Minimum percent of
Year
holdback credit proceeds
Year One (typically 2022) 30%
Year Two (typically 2023) 40%
Subsequent Years 50%
If an opt-in EDU contributes all base credits issued in a quarter to the CFR program,
the EDU will have no holdback credits that quarter.
Opt-in EDUs may spend credit proceeds on eligible holdback equity projects before
selling holdback credits, and allocate those expenditures to holdback credit proceeds,
10 Pursuant to section 95483(c)(1)(A)6.a. of the LCFS regulation.
11
so long as the expenditure occurred on or after January 1, 2022. Opt-in EDUs may
contribute their holdback credits or credit proceeds to another EDU's equity project.
Opt-in EDUs may aggregate holdback credit equity proceeds with funding from other
sources, including from other funds held by other entities, but must track their
holdback credit proceeds separately. The Annual Report must demonstrate the
expenditures related to holdback credit proceeds, as discussed in the following
section.
ACCOUNTING OF LCFS PROCEEDS FOR HOLDBACK CREDIT EQUITY
PROJECTS
In order to count the proceeds toward the minimum for a given calendar year, the
proceeds must be encumbered in that calendar year. Encumbrance of the holdback
credit proceeds for designated eligible equity projects must be included in the Annual
Compliance Report pursuant to section 95491. Reports on each project, which can be
included in the reporting template, must include descriptions of how the project:
1. is an eligible project by supporting transportation electrification for the primary
benefit of or primarily serving disadvantaged communities and/or low-income
communities and/or rural areas or low-income individuals;
2. supports increased access to clean transportation and mobility options;
3. relates to existing incentive projects to diversify and maximize State, local and
EDU investments;
4. demonstrates partnership and support from local community-based
organizations; and
5. meets community-identified clean transportation needs.
These five descriptions are consistent with the findings and recommendations of the
SB 350 Low-Income Barriers Study, Part B."
In addition to the descriptions of the projects, a complete report for Holdback
Proceeds Equity Projects shall include an annual accounting of the following
information for the reporting year:
1. The total number of base credits issued to the EDU
2. The total number of holdback credits the EDU possesses from previous years
3. The total number of base and holdback credits sold
4. The proceeds from the sale of the base and holdback credits
5. The number of base credits contributed to the Clean Fuel Rewards Program
6. The amount of base credit proceeds contributed to the Clean Fuel Rewards
Program
7. The holdback credit proceeds spent on equity projects
8. The amount of holdback proceeds spent on administration costs
11 Low-Income Barriers Study, Part B: Overcoming Barriers to Clean Transportation Access for Low-
Income Residents, Final Guidance Document. CARB, 2018. Pursuant to 95483(c)(1)(A)6.b.
https://ww3.arb.ca.govlmsprogltransoptionslsb350_final_guidance_document 022118.pdf
12
EDUs can find a holdback equity proceeds reporting template as a worksheet in the
electricity credit proceeds reporting template, which can be downloaded from the
LCFS Reporting Tool (LRT) home page' or from the Guidance webpage.'
Contact
If you have questions regarding the above information, or would like to contact LCFS
staff for consultation if it seems unclear whether a potential use case would meet the
electricity credit proceeds requirement, please visit the LCFS Contacts webpage:
https://www.arb.ca.gov/fuelsllcfs/contact.htm.
13