HomeMy WebLinkAbout10 Transformer bid Agenda Item # 10 DONNER Public Utility District ACTION To: Board of Directors From: Sanna Schlosser Date: April 02, 2008 Subject: Consideration of the Award of a Transformer Bid. 1. WHY THIS MATTER IS BEFORE THE BOARD The amount of this award is in excess of $15,000 therefore Board approval is necessary. 2. HISTORY The District's annual purchase of transformers is required to meet our new construction obligations and the purchase also includes units for routine replacements. Vendors bid on transformers with options for two different types of dielectric fluid: petroleum-based mineral oil and seed-based biodegradable oil. The Board previously reviewed the differences between these types of dielectric fluids. The Board approved the purchase of biodegradable oil in all transformers for the 2007 contract. In order to enter into year-long contracts, vendors request the use of a quarterly materials escalation clause which the District has included in transformer contracts since 2006. The following factors are used to determine the successful bidder: price, adherence to our contract and specifications, and delivery time. The lowest bid price is determined by the Total Owning Cost (TOC) formula calculation. The TOC is the sum of the Unit Price (initial purchase price) plus the cost of losses over the expected life of the unit. The TOC calculation allows the District to determine the transformers with lowest overall ownership costs, which may not correspond to the lowest initial purchase or contract prices. The low bidder for a category type is determined by the summation of the TOCs for all transformers within that category, based on a quantity of one (1) for each transformer. 3. NEW INFORMATION Bids have been opened and analyzed for the District's purchase of transformers. The Total Owning Cost (TOC) calculation was used to determine the low bidders as depicted in Table 1. Attached are summaries of the bid information received. The bid results show the description and quantity of transformers required, vendor name, dielectric fluid type, quoted price, and delivery time. District contracts specify that bids must be awarded by entire category. These categories are Single Phase Pole Mounted Transformers (Schedule A), Single Phase Pad Mounted Transformers (Schedule B) and Three Phase Pad Mounted Transformers (Schedules C and D). The apparent low bidder for Schedules C and D is HD Supply/Cooper, however the transformers bid do not comply with District Specifications. The bid from HD Supply/Cooper is therefore non-compliant with District specifications. The next lowest bidder for these Schedules is Howard Industries, however Howard Industries did not submit our Non-Collusion Affidavit. Therefore, Howard is non-responsive to the District's Contract. General Pacific is compliant and responsive with District Standards and Contracts. 4. FISCAL IMPACT Sufficient funds exist for the purchase of new transformers within the approved FY 2008 capital budget. This award will be limited to the approved FY 2008 capital budget. 5. RECOMMENDATION The recommendations are based on TOC evaluations and are as follows: 1. Find HD Supply/Cooper Power Systems non-compliant with District Standards for Schedules C &D. 2. Find Howard Industries non-responsive to District Contract. 3. Award Schedule A, Pole Mounted Single Phase Transformers with Biodegradable Dielectric Fluid to HD Supply/Cooper with the contract prices as listed on the 2008 Transformer Bid Award Recommendation Table, to be effective until 6/30/08. 4. Award Schedule B, Pad Mounted Single Phase Transformers, and Schedules C and D, Three Phase Pad Mounted Transformers, with Biodegradable Dielectric Fluid to General Pacific with the contract prices as listed on the 2008 Transformer Bid Award Recommendation Table, to be effective until 6/30/08. Steve Hollabaugh, A sistant General Michael D. Holley, General Manager Manager TABLE 1 - TRANSFORMER BID RESULTS Evaluated Price Comparison - Total Owning Cost (TOC) (TOC=Initial Purchase Price + Cost of losses over transformer life) Schedule A- Single Phase Pole Mount Trans. 120/240V Mineral Oil HD Supply/ Sched Cooper GE Gen Pac Howard Moloney WESCO Al $2,019.20 $1,969.27 $1,986.23 $2,231.90 $2,259.76 A2 $2,598.57 $2,576.40 $2,537.08 Non- $2,932.79 $2,851.47 A3 $2,610.44 $2,521.24 $2,485.18 Responsive $2,985.17 $2,759.84 A4 $3,367.42 $3,078.57 $3,108.18 to $3,454.50 $3,514.90 A5 $2,152.23 $2,099.07 $2,145.33 District $2,220.70 $2,464.51 A6 $2,862.19 $2,741.83 $2,688.05 Contract $2,982.01 $2,981.87 A7 1 $3,218.47 $3,195.99 $3,352.45 $3,500.31 $3,582.13 $18,828.52 $18,182.36 $18,302.49 $0.00 $20,307.38 $20,414.47 Schedule B - Single Phase Padmount Trans. 120/240V Mineral Oil HD Supply/ Sched Cooper GE Gen Pac Howard Moloney WESCO 131 $2,917.21 $0.00 $2,369.07 $0.00 $2,882.46 62 $4,103.54 $0.00 $3,378.96 Non- $0.00 $3,846.94 B3 $5,105.58 $0.00 $4,532.23 Responsive $0.00 $4,740.67 B4 $6,036.81 $0.00 $5,655.73 to $0.00 $5,644.74 65 $3,281.85 $0.00 $2,684.14 District $0.00 $3,282.44 136 $4,371.17 $0.00 $3,726.02 Contract $0.00 $4,151.28 $25,816.16 $0.00 $22,346.15 $0.00 $0.00 $24,548.52 Schedule C -Three Phase Padmount Trans. 120/208V Mineral Oil HD Supply/ Sched Cooper GE Gen Pac Howard Moloney WESCO C1 $0.00 $7,966.82 $0.00 $8,332.62 C2 $0.00 $9,326.97 $0.00 $9,417.52 C3 Non- $0.00 $11,110.01 Non- $0.00 $11,113.36 C4 Compliant $0.00 $12,858.27 Responsive $0.00 $12,591.06 C5 with $0.00 $15,798.28 to $0.00 $15,874.78 C6 District $0.00 $18,707.91 District $0.00 $18,766.52 C7 Standards $0.00 $25,901.78 Contract $0.00 $23,344.42 C8 $0.00 $35,091.92 $0.00 $36,556.06 $0.00 $0.00 $136,761.96 $0.00 $135,996.34 Schedule D -Three Phase Padmount Trans. 277/480V Mineral Oil HD Supply/ Sched Cooper GE Gen Pac Howard Moloney Pauwels D1 $0.00 $7,911.92 $0.00 $8,056.16 D2 $0.00 $9,144.76 $0.00 $9,444.38 D3 Non- $0.00 $11,211.82 Non- $0.00 $10,965.28 D4 Compliant $0.00 $12,494.98 Responsive $0.00 $12,342.71 D5 with $0.00 $15,272.05 to $0.00 $15,701.54 D6 District $0.00 $17,956.75 District $0.00 $18,390.30 D7 Standards $0.00 $24,197.45 Contract $0.00 $22,472.65 D8 $0.00 $33,206.43 $0.00 $35,211.90 D9 $0.00 $40,774.67 $0.00 $42,834.11 $0.00 $0.00 $172,170.82 $0.00 $0.00 $175,419.02 3/21/2008 Page 1 of 2 Indicates recommended bidder Schedule A- Single Phase Pole Mount Trans. 120/240V Biodegradable Fluid HD Supply/ Sched Cooper GE Gen Pac Howard Moloney WESCO Al $2,095.20 $0.00 $2,246.27 $2,371.90 $2,665.82 A2 $2,653.20 $0.00 $2,795.08 Non- $3,162.79 $3,417.66 A3 $2,701.44 $0.00 $2,719.18 Responsive $3,235.17 $3,321.26 A4 $3,277.96 $0.00 $3,416.18 to $3,719.50 $4,119.33 A5 $2,095.70 $0.00 $2,554.67 District $3,235.17 $2,872.08 A6 $2,700.96 $0.00 $2,962.05 Contract $3,719.50 $3,828.40 A7 $3,279.79 $0.00 $3,686.00 $2,365.70 $4,329.01 $18,804.24 $0.00 $20,379.42 $0.00 $21,809.74 $24,553.57 Schedule B - Single Phase Padmount Trans. 120/240V Biodegradable Fluid HD Supply/ Sched Cooper GE Gen Pac Howard Moloney WESCO B1 $3,116.93 $0.00 $2,662.07 $0.00 $0.00 B2 $4,287.23 $0.00 $3,707.96 Non- $0.00 $0.00 B3 $5,332.50 $0.00 $5,034.23 Responsive $0.00 $0.00 B4 $6,343.24 $0.00 $6,345.73 to $0.00 $0.00 B5 $3,443.85 $0.00 $3,227.14 District $0.00 $0.00 B6 $4,588.17 $0.00 $4,359.02 Contract $0.00 $0.00 $27,111.91 $0.00 $25,336.15 $0.00 $0.00 $0.00 Schedule C -Three Phase Padmount Trans. 120/208V Biodegradable Fluid HD Supply/ Sched Cooper GE Gen Pac Howard Moloney WESCO C1 $11,827.46 $9,686.82 $0.00 $0.00 C2 $13,134.26 $10,907.04 $0.00 $0.00 C3 Non- $15,219.51 $12,937.27 Non- $0.00 $0.00 C4 Compliant $18,375.48 $14,760.71 Responsive $0.00 $0.00 C5 with $21,879.15 $17,957.28 to $0.00 $0.00 C6 District $24,087.23 $21,413.01 District $0.00 $0.00 C7 Standards $34,654.57 $28,622.23 Contract $0.00 $0.00 C8 $48,215.98 $39,062.92 $0.00 $0.00 $0.00 $187,393.63 $155,347.28 $0.00 $0.00 $0.00 Schedule D-Three Phase Padmount Trans. 277/480V Biodegradable Fluid HD Supply/ Sched Cooper GE Gen Pac Howard Moloney WESCO D1 $12,063.75 $9,427.99 $0.00 $0.00 D2 $12,458.69 $10,699.52 $0.00 $0.00 D3 Non- $14,144.10 $12,962.27 Non- $0.00 $0.00 D4 Compliant $17,767.93 $14,242.87 Responsive $0.00 $0.00 D5 with $21,573.82 $17,201.05 to $0.00 $0.00 D6 District $23,930.14 $20,360.10 District $0.00 $0.00 D7 Standards $33,256.35 $26,692.44 Contract $0.00 $0.00 D8 $43,982.79 $38,390.43 $0.00 $0.00 D9 $53,876.28 $45,566.67 $0.00 $0.00 $0.00 $233,053.85 $195,543.33 $0.00 $0.00 $0.00 3/21/2008 Page 2 of 2 2008 TRANSFORMER BID AWARD RECOMMENDATION Contract Period 3/12108 to 3112/09 BIODEGRADABLE OIL Order Contract Extended Type Schedule Qty Price Price Polemount-1 Ph. HD Supply/Cooper Power 25 kva Al $1,112.00 $0.00 37.5 kva A2 11 $1,428.00 $15,708.00 37.5 kva A3 $1,345.00 $0.00 50 kva A4 $1,687.00 $0.00 25 kva A5 $1,134.00 $0.00 37.5 kva A6 $1,469.00 $0.00 50 kva A7 $1,841.00 $0.00 $15,708.00 Padmount, 1 Ph. General Pacific 25 kva 131 $1,799.00 $0.00 50 kva B2 $2,238.00 $0.00 75 kva B3 $3,114.00 $0.00 100 kva B4 $4,058.00 $0.00 25 kva B5 $2,359.00 $0.00 50 kva B6 $2,850.00 $0.00 $0.00 Padmount, 3 Ph. 120/208v General Pacific 45 kva C1 $7,886.00 $0.00 75 kva C2 $8,297.00 $0.00 112.5 kva C3 $9,345.00 $0.00 150 kva C4 1 $10,395.00 $10,395.00 225 kva C5 3 $12,303.00 $36,909.00 300 kva C6 2 $14,249.00 $28,498.00 500 kva C7 $17,531.00 $0.00 750 kva C8 1 $22,252.00 $229252.00 $98,054.00 277/480v General Pacific 45 kva D1 $7,635.00 $0.00 75 kva D2 $8,233.00 $0.00 112.5 kva D3 $9,624.80 $0.00 150 kva D4 $9,998.00 $0.00 225 kva D5 $11,572.00 $0.00 300 kva D6 $13,456.00 $0.00 500 kva D7 $16,394.00 $0.00 750 kva D8 $23,172.00 $0.00 1000 kva D9 $27,673.00 $0.00 $0.00 Notes: 1. Prices are effective until 6/30/08.Thereafter, prices are subject to quarterly escalation until end of contract. 2. Extended Price indicates amount to be purchased upon award of Contract. 3/24/2008