Loading...
HomeMy WebLinkAbout14 Tank Rehab 2023 Bid Rejection TRUCKEE - AGENDA ITEM #14 Public Utility District MEETING DATE: April 5, 2023 TO: Board of Directors FROM: Neil Kaufman, Water System Engineer Chad Reed, Water Utility Director SUBJECT: Consideration of Rejection of All Bids for the Ski Run Water Storage Tank Rehabilitation Project APPROVED BY - Bn`an C. Wright,.'General Manager RECOMMENDATION: Reject all bids received for the Ski Run Water Storage Tank Rehabilitation Project. BACKGROUND: The District currently operates 34 water storage tanks located throughout the water distribution system: • 30 ground level welded steel tanks • Two ground level bolted steel tanks • One partially buried pre-stressed concrete tank • One elevated welded steel tank The tanks range in volume from 100,000 gallons to 1.5 million gallons with the oldest tank constructed in 1963 and the newest tank constructed in 2021. Many of these tanks are still utilizing their original interior coating systems, which are approaching 50 years old. The design standards and seismic engineering requirements have also changed significantly and while the tanks are not out of compliance, many of the tanks do not meet current standards. During preparation of the 2020 Water System Capital Improvement Plan update, staff identified the need for significant increases in funding for annual water storage tank maintenance projects. In order to efficiently plan for and manage the additional projects, the need for an outside engineering consultant was identified. In June 2021, the Water Page 1 of 4 Department issued a Request for Proposals (RFP) to select a consultant to perform the engineering work associated with the District's water storage tank rehabilitation plan. After review of the proposals, a contract was awarded to Carollo Engineers in August 2021. Staff and Carollo Engineers identified the District's Roundhill Tank as the first water storage facility to be addressed within the larger storage tank rehabilitation plan. During the development of the project specifications and bid documents, staff consulted with Carollo Engineers regarding a cost benefit analysis between rehabilitation and replacement. It was recognized at the time that the recent shift in labor costs and materials had narrowed the gap between the two options from a cost perspective but consensus was that rehabilitation was still the most favorable option. Bid documents for the rehabilitation of Roundhill Tank were completed by Carollo in March 2022, with a Bid Opening held in April, 2022. On May 4, 2022, a contract was awarded to Resource Development Company (RDC) of Sparks, Nevada. During the rehabilitation project, it was determined that the metal tank shell and weld materials were found to be at a much more advanced state of degradation than originally anticipated. To address this advanced stage of degradation, a change order was approved to address the discovered issues. Recognizing that there was already substantial progress in the completion of the Roundhill Tank Rehabilitation Project prior to discovery of the additional necessary work, staff determined the change order issuance was appropriate. However, it was also acknowledged that with the additional change order work, the overall cost of rehabilitation was quickly approaching engineer's estimates for complete replacement. ANALYSIS: In September 2022, the Board of Directors approved a contract with Carollo to conduct engineering evaluations and prepare bid documents for the rehabilitation of the Ski Run and Prosser Lakeview Tanks. The cost proposal for this work was $182,975. The Board also approved a ten percent change order allowance for a total authorization not to exceed $201,300. Based upon the field inspections, it is believed that the Ski Run tank is in better condition than the Roundhill Tank. However, it should be noted that the configuration of the water system prevents the tank from being removed from service and completely drained to perform a thorough interior inspection. It should also be noted that the Ski Run Tank was built by the same contractor in the same general time frame as the Roundhill tank and a similar level of repairs are expected. As noted above, an overall review of water system operations and water storage capacities was conducted. This review determined that the Ski Run Tank has a critical function in moving water to the highest portion of the Tahoe Donner subdivision. Simply removing the tank from service is not feasible. In an effort to reduce the project cost, the scope of work was slightly reduced with items such as replacement of the roof vents and ladders and installation of a sample port removed from the contract. Page 2 of 4 A set of bid documents for rehabilitation of the Ski Run tank was prepared and bidding began in early February 2023. The bid opening was held on March 2, 2023. Five bids were received: Bidder Location Amount Responsive Euro Style Management Sacramento, CA $395,000 Yes Resource Development Company Sparks, NV $505,100 Yes Paso Robles Tank Hemet, CA $649,116 Yes Crosno Construction Arroyo Grande, CA $670,884 Yes Unified Field Services Corporation Bakersfield, CA $54,548,737 Yes It should be noted that there was a mathematical error in the bid from Unified Field Services Corporation. Correction of this error using the procedure indicated in the bid documents results in the final bid price given above. All bids received were over the engineers estimate, of$361,000. The apparent responsive low bidder was Euro Style Management for $395,000 or nearly ten percent over the engineer's budget. In addition to the overage, staff knows additional costs would be incurred for the construction-phase engineering, construction inspection and administration. There are sufficient funds available to proceed with the bid from Euro Style Management. However, it is position of the Water Department that spending $450k - $500k to rehabilitate the existing tank is not advisable for the following reasons: 1) The existing tank is functional, but is undersized. At 100,000 gallons, it is the smallest tank in the system (the Armstrong Tank is also 100,000 gallons in size). 2) The rehabilitated tank would not be upgraded to current seismic codes and the diameter to height ratio of the smaller tanks makes them more susceptible to damage in an earthquake event. 3) The rehabilitated tank would not be upgraded to current industry standards. As noted above, certain items were deleted from the scope as a cost savings measure. The existing pump station at the Ski Run tank is original construction (50 years old). The building is in fair condition with chalet-style wood stick framing and a metal roof. The electrical switchgear has not been replaced and the structure is too small to allow for proper maintenance of the pumps and equipment. The overall plan for this site involves replacement of the pump station with a new CMU block building and electrical switchgear. The site piping was replaced in 2008 and provisions for a new pump station structure were included in that work. The generator at the site was installed in 2008 and will remain. After the new pump station is constructed and the old pump station is demolished, there will be sufficient space for construction of a larger tank (200,000 to 250,000 gallons) at the site. Page 3 of 4 Goals and Objectives: This item is in support of the following goals and objectives: District Code1.05.020 Objectives: 1. Responsibly serve the public. 3. Provide reliable and high quality water supply and distribution system to meet current and future needs. 5. Manage the District in an environmentally sound manner. 6. Manage the District in an effective, efficient and fiscally responsible manner. Strategic Goals: 1. Manage for Financial Stability and Resiliency. FISCAL IMPACT: There is no direct fiscal impact associated with rejecting the bids for the Ski Run Water Storage Tank Rehabilitation. The Water Department will proceed with redevelopment of the Ski Run Tank site. Contracts for design and construction associated with this work will be presented to the Board at future date. It is likely that an outside contract will also be necessary for demolition and removal of the existing Prosser Lakeview Tank. ATTACHMENTS: None. Page 4 of 4