DistrictPublic Utility
CONSENT
To: Board of Directors
From: Sanna Schlosser
Date: December 03, 2008
Subject: Award Control Enclosure Bid for Tahoe Donner Substation.
1. WHY THIS MATTER IS BEFORE THE BOARD
Only the Board can approve bid awards over $15,000.
2. HISTORY
This material purchase is required for the Tahoe Donner Substation Rebuild Project.
The Control Enclosure is an integral part of these substation improvements. The
Board of Directors awarded the engineering contract for this project in November
2007. The bid period began on October 20, and ended on November 20, 2008.
3. NEW INFORMATION
The District received 3 bids by the deadline. A summary of the bid information is
attached. Electrical Power Products (EP2) submitted the lowest responsive bid. Our
consultants have confirmed that the materials specified comply with District
requirements.
4. FISCAL IMPACT
The FY08 Capital Budget includes $193,081 for this project, funded by rates.
5. RECOMMENDATION
Award the bid for one Control Enclosure assmbly to Electrical Power Products in the
amount of $162,254, not including taxes.
b.
Stephen Hollabaugh Michael D. Holley
Assistant General Manager General Manager
Control Enclosure Bid Opening 20-Nov 1400
Manufacturer Bid Bond Non-Collusion Price Delivery Date Exceptions
Electrical Power Products yes yes $162,254.00 22-24 weeks
Keystone Electrical yes yes $179,536.34 July 15, 2009
AZZ/Carter and Crawley es no $180,510.88 July 15, 2009 a
10%
Exceptions:
a. No non-collusion affidavit Bid is non-responsive