HomeMy WebLinkAbout7 District Pipeline Replacement Change order Agenda Item # 7 TRUCKEE R JPF Public Utility District `0_ ACTION To: Board of Directors From: Neil Kaufman Date: September 10, 2009 Subject: Consideration of the Approval of Change Order No. 3 to the District Pipeline Replacement— 2009 — Contract C 1. WHY THIS MATTER IS BEFORE THE BOARD Change orders in excess of the change order allowance require Board authorization. 2. HISTORY In 2005 and 2006, the Water Department made Board presentations regarding the condition of existing water pipelines and the need to pursue a pipeline replacement program. The District subsequently issued a COP in 2006 and dedicated a portion of those funds for the pipeline replacement program. Pipeline construction projects have been undertaken during 2006, 2007 and 2008 as part of this program. The construction for 2009 entails about 18,000 feet of pipeline and has been broken into three separate construction contracts. • Contract A - Hillside Drive, Solvang Way, Staghorn Road & St. Croix Way • Contract B - Oslo Drive, Sierra Glen Way, Skiview Loop, Snowpeak Way & Tyrol Road • Contract C - Chamonix Road, Donner View Tank site, Innsbruck Tank site, Rhineland Avenue, Skislope Way, & West Reed Avenue The Bid opening for Contract C was held on February 24, 2009. Nineteen bids were received. The apparent low bidder for the project was Wunschel & Sons. The Board found Wunschel & Sons bid to be non-responsive due to omissions on the bid bond. The Board subsequently awarded the contract to Cruz Excavating on March 4, 2009 in an amount not to exceed $656,993.00 plus a 10% change order allowance of $65,000. 3. NEW INFORMATION Contract C includes construction at six separate locations: • Chamonix Road • Donner View Tank Site • Innsbruck Tank Site • Rhineland Avenue • Skislope Way • West Reed Avenue The construction work at the Innsbruck Tank site and Rhineland Avenue has been completed. The construction work at the Donner View Tank Site is complete with the exception of pavement restoration, which is partially finished. The worts on Skislope Way and West Reed Avenue has not been started. Cruz Excavating has been completely paid for the work performed at the Donner View Tank site, Innsbruck Tank site and Rhineland Avenue. No payments have been made for on Skislope Way and West Reed Avenue. Overall, Cruz has performed $309,913.97 of the original contract work and an additional $23,275.75 in change order work. The District is holding 10% retention in the amount of$33,318.97 and has made payments to Cruz for $299,870.75. The work on Chamonix Road is partially complete. The main line pipe has been installed and Cruz is working on installation of the service laterals and meter boxes. The pipe has not been pressure tested and pavement restoration has not been performed. The total bid price for the work on Chamonix Road was $245,357. To date Cruz has earned $107,075 for work on Chamonix Road. Cruz has earned about 44% of the bid price for the work on Chamonix Road and the worts can be considered about 50% complete. Cruz has been experiencing significant cash flow issues and has been unable to purchase the materials necessary to complete the work on Chamonix Road. The District has held a number of discussions with Cruz regarding this issue. At this point, it has been determined that the best course of action would be to have Cruz complete the work on Chamonix Road and delete the work on Skislope Way and West Reed Avenue from the contract. This amount of worts totals $203,280 ($124,130 for Skislope Way and $79,150 for West Reed Avenue). In addition, in order to complete the work on Chamonix Road, it will be necessary for the District to directly purchase the needed materials from the supplier. The estimated cost of this material is $23,000, including sales tax. There will be a corresponding reduction in the amount of money paid to Cruz. The Change Order No. 3 is included as Attachment 1. 4. FISCAL IMPACT The original contract award for Contract C was $656,993.00. It is recommended that a deductive change order be issued, deleting Skislope Way, West Reed Avenue and District-furnished materials from the contract. This results in a revised contract price of$453,988.75. Original Contract Price $656,993.00 Change Orders to Date $23,275.75 Skislope Way - $124,130.00 West Reed Avenue - $79,150.00 District-Furnished Materials - $23 000.00 Revised Contract Price $453,988.75 5. RECOMMENDATION Authorize Change Order No. 3 to the District Pipeline Replacement- 2009- Contract C in a deductive amount of $226,280 subject to the terms and conditions of the Change Order. 01 y f Ed Taylor Michael D. Holley Water Utility Manager General Manager Attachment 1 Change Order Public Contract Name: District Pipeline Replacement—2009—Contract C Contract Change Order No: 3 Orig. Contract Amt. $ 656,993.00 Days NA Date: September 10, 2009 Prev. Apprd Changes $ 23,275.75 Days NA Contractor: Cruz Excavating, Inc. This Change $ -226,280.00 Days NA Revised Contract Amt. $ 453,988.75 Days NA This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items for a lump sum price agreed upon between the Contractor and District. Increase in (Decrease) Contract Time Contract in Contract Extension Description of Changes Amount $ Amount $ (days) 1 —Deletion of Work on Skislope Way $124,130.00 2—Deletion of Work on West Reed Avenue $79,150.00 3—Deletion for District Supplied Materials for Chamonix Rd. $23,000.00 Totals $226,280.00 Net change in contract amount(increase or decrease) $226,280.00 The amount of the Contract will be decreased by the sum of $226,280.00 and the Contract Times shall not be extended. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete the Change order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the District. Accepted: /Contractor Date: (Signature) Approved: /District Date: (Signature) Pagel