Loading...
HomeMy WebLinkAbout8 Donner Lake Feeder Project Agenda Item # 8 Public Utility District i ACTION To: Board of Directors From: Sanna Schlosser Date: July 15, 2009 Subject: Approve a Letter of Intent to Purchase Materials from NV Energy for the Donner Lake Circuit No. 3 Feeder Project 1. WHY THIS MATTER IS BEFORE THE BOARD Board authorization is required for expenditures in excess of $15,000. 2. HISTORY The new Donner Lake Circuit 3 feeder is a new 12.47kV distribution feeder that will originate at the District's Donner Lake Substation and connect to the Tahoe Donner area. This new circuit is needed to increase capacity, improve system performance and reliability. It will be approximately 2 miles long and will be built under existing 60kV transmission lines owned by the District and NV Energy. Major milestones in the history of this project to date include: January, 2007 - Initial Discussions with NV Energy August 15, 2007 - Board Approval of a Task Order to prepare the CEQA Initial Study December 5, 2007 - Board Approval of CEQA Initial Study December 19, 2007 - Public Hearing on CEQA Initial Study January 16, 2008 - Adoption of Final CEQA Document October 15, 2008 - Board Approval of Design and Pole Contact Agreements with NV Energy 3. NEW INFORMATION NV Energy has completed the design for the portion of the transmission line they own, and will construct this portion of the project. In order to complete the project in 2009, certain materials must be procured immediately due to extended lead times. These materials include several steel poles necessary for the project. NV Energy has requested a Letter of Intent from the District regarding the purchase of these materials. The Letter of Intent must state that the District will pay for these materials when invoiced by NV Energy. The estimated cost of these materials is $257,908. The anticipated project schedule is shown below: July 15, 2009 - Consideration of Approval of a Letter of Intent with NV Energy (this action) August 2009 - Consideration of a Contract Approval with NV Energy to construct the Donner Lake Circuit 3 Feeder and associated improvements on NV Energy's transmission line September 1, 2009 - Start of Construction November 1, 2009 - Completion of Construction November, 2009 - Consideration of Approval of a Tax Liability Payment to NV Energy 4. FISCAL IMPACT The source of funding for the new Donner Lake Circuit No. 3 feeder is Facilities Fees as this project provides increased electrical capacity and improves reliability. Sufficient funds exist in the Electric Facilities Fees account to cover the monies due NV Energy for these materials. Authorization to construct this new distribution feeder will be brought to the Board for action in August of 2009. Authorization to make payment to NV Energy for the tax liability issue will be brought to the Board for action in November 2009, or when actual construction costs are known. 5. RECOMMENDATION Authorize the Board President to sign a Letter of Intent with NV Energy to purchase materials in advance of construction for the Donner Lake Circuit 3 feeder. Stephen Hollabaugh Michael D. Holley Assistant General Manager General Manager Truckee Donner Public Utility District Directors Joseph R, Aguera Jeff Bender J. Ron Hemig John Hillstrom Patricia S. Sutton July 10, 2009 General Manager Michael D. Holley Shauna K.Adams Manager Major Projects NV Energy PO Box 10100 Reno,NV 89520-0024 Dear Ms.Adams, SUBJECT: 607 UNDERBUILD PROJECT The Truckee Donner Public Utility District Electric Department has received your request for a formal letter of intent from the Truckee Donner Public Utility District(the District). The District anticipates beginning construction in September and completing the project this year. The District understands that some of the materials needed for construction of this project have lead times of up to 10 weeks. Therefore, in order to meet our proposed schedule, it is necessary to order materials as soon as possible. Per NV Energy's letter to the District,materials which need to be ordered include light duty steel poles (10 week lead time)and non-stock wood poles. The quoted prices for these materials are$91,379 and$166,529, respectively. The District requests NV Energy to order these materials on behalf of the District and agrees to pay for these materials when invoiced. Sincerely, J.Ron Hemig President,Truckee Donner PUD Board of Directors P.O.Box 309—Truckee,CA 96160—Phone 530-587-3896—www.tdpud.ors 'k Nk FVV E n e Qo,y July 9,2009 Stephen I-Iollabaugh Electric Utility Manager Truckee Donner Public Utility District P.O. Box 309 Truckee, CA 96160 Dear Steve: Subject: 607 Underbuild Project Please find the following estimate and request for a letter of intent pursuant to the Pole Contact Agreement between Sierra Pacific Power Company, dba NVEnergy, (Sierra)and Truckee Donner Public Utility District(TDPUD). This Agreement grants TDPUD a license to own and operate a 12,47kV distribution feeder along Sierra's #607 60kV transmission line as specified in the referenced contract Agreement. The #607 transmission line is part of the defined Path 24, the"Sierra Summit Path", which ties our system to the California Independent System Operator(ISO) Corporation. It has been determined to be an operationally significant connection between Sierra and PG&E by Western Electricity Coordinating Council (WECC). Sierra will commence rebuilding this line to accommodate TDPUD's distribution circuit this fall with the understanding that a May 1, 2010 date is requested for project completion. Sierra must order long lead materials now to meet the required construction window beginning in September,2009. A letter of intent to construct and acknowledgement that payment will be required upon delivery of materials is requested as assurances for ordering the non-stock materials. This includes light duty steel poles that have a ten week lead time for $91,379 and non-stock wood poles that have a 4 week lead time for$166,529, Once construction begins, TDPUD will be invoiced for the remaining materials and progress payments for the labor. The estimate for construction of the#607 60kV line is from $1,045,455 to $1,444,013. Construction time ranges from six to ten weeks. This estimate includes the cost component to cover Sierra's estimated liability for Federal Income Tax in accordance with California Public Utilities Decision No. 87-09-026 issued in Investigation No. 86-11-019, Costs have been estimated for this project by the least expensive method which is also in accordance with Sierra's engineering and construction practices. The estimate also assumes: o Worst case scenario for a ten week construction period o A small amount of road construction for construction access o A moderate amount of blasting will be required o Traffic control on 1-80 P.O.BOX 98910, LAS VEGAS,NEVADA 89151-0001 6226 WEST SAHARA AVENUE,LAS VEGAS,NEVADA 89146 P.O,BOX 10100,RENO,NEVADA 89520-0024 6100 NEIL ROAD,RENO,NEVADA 89511 NVEnergy.com o TDPUD will obtain and meet all mitigation measures outlined in the Federal, State and Local permits. This includes obtaining required biological surveys prior to construction and securing a contractor who will implement storm water pollution prevention measures as required by your permits. d An on-site fire crew o Other items as detailed in the Agreement Sierra welcomes the opportunity to accommodate TDPUD's request to utilize our facilities for this project. Please contact me if you have any questions or concerns. Sincerely, Shauna K. Adams Manager Major Projects Cc: Samna Schlosser,TDPUD Joe Ilorvath,"I"DPUD Mike Braithwaite, NVE Greg Lambert,NVE Gary Porter,NVE Colin Harlow,NVE Kelly Toulouse,NVE Ellen Costanza,NVE copy�. RE C0E P 2 3 (2` 0 Sierra Pacific POWER W E R C O M P A N V www.sieffapacific.com Gregory P.Lambert Major Accounts FxeaiNve 6100 Neil Road,P.O.�Box 10100-Mail Code S2A41 Reno,Nevada 89520-0024•Phone:775.834.5247•Fax:775.834.5778•E-Mail:&mbcn aQ swc.com September 22, 2008 Mr. Joe Horvath Electric System Engineer Truckee Donner PUD P.O. Box 309 Truckee, CA 96160 Re: Truckee Donner PUD 607 Line 60kV Rebuild Project Dear Steve: Sierra Pacific is prepared to begin work on the project to (1) construct approximately two miles of Sierra owned 60kV transmission line connecting TDPUD's Donner Lake and Tahoe Donner Substations and (2) install the District's 3 phase 12.47kV distribution feeder as an underbuild circuit along Sierra's line. This work is being requested by TDPUD to accommodate its plans to upgrade the District's electric system in the area. Based on the information provided by TDPUD regarding the project's requirements and scheduling needs, Sierra is prepared to begin the planning, design and engineering phase of the project after it has received your authorization to proceed and your advance payment in the amount of$31,939 to cover the costs associated with these activities. An overview of the proposed project is provided in the sections that follow. Scope of Project The project involves the planning, design and construction of approximately two miles of Sierra's 60kV transmission line that connects TDPUD's Donner Lake and Tahoe Donner Substations and the installation of TDPUD's 3 phase 12.47kV distribution feeder as an underbuild circuit along Sierra's line. The starting point for the underbuild on the 607 line is to be the tap pole for the District's Donner Lake Substation tap line (just south of I-80 next to Donner Lake Rd) and the end point is where the 607 line crosses Ski Slope Way in the Tahoe Donner Subdivision, a distance of approximately 10,000 feet. The exact extent of the work to be performed, as well as the cost and project schedule, will be known with a greater degree of certainty and will be reviewed with you, after the planning, design and engineering phases of the project have been completed. x, Estimated Project Costs As of the date of this letter, the total cost of the project is estimated to be approximately $480,525. This estimate, which assumes all the work is performed by Sierra, is summarized below and is described in greater detail in the accompanying Project Estimate worksheet. It includes a 10% contingency to account for any unanticipated costs but does not make any provisions for tax liabilities that may incurred as a result of the project or for any unforeseen permitting or environmental costs. Truckee Donner PUD 607 Line 60kV Rebuild Proiect Total Stores and Materials $382,815 Total Misc.Vouchers $ 569 Total Company Labor $46,457 Total Transportation S 7,000 Subtotal $436,841 Contingency 43,684 Total Estimate (excluding tax) $480,525 Estimated cost per mile $254,246 Portion attributable to Planning, Design, Engineering, Surveying and Lands $ 31,939 Tax Liability calculated based on year in which project is completed. 2008 = 17%<69kV 15%> 69kV 2009 28%<69kV 24%> 69kV (Note: See accompanying Project Estimate for more information) The estimated costs will be monitored as the project progresses. If significant changes in costs begin to arise as a result of currently unanticipated factors, this information will be communicated to TDPUD. Such factors might include unforeseen increases in material, labor or equipment costs, changes in project design or project scope, and/or delays in construction caused by inclement weather, fires or other natural phenomena. After the project has been completed, estimated costs will be adjusted to reflect actual costs incurred and an invoice will be submitted to TDPUD for payment within 30 days after the date of the invoice. This invoice will take into account all advance payments made by TDPUD and will constitute the "net" amount due. The net amount due will calculated based on all available cost information and invoices at the time the project is completed and will be subject to a final adjustment after Sierra has finished its normal internal audit and review of the project's cost components. 2 Taxability The act of constructing, upgrading and/or improving Sierra-owned facilities for the purpose of accommodating their joint use by TDPUD has been determined to result in a non-cash contribution to Sierra, the value of which triggers an income tax liability to Sierra under the 1986 Federal Tax Reform Act and is thus subject to a tax gross up in accordance with California Public Utilities Decision No. 87-09-026 issued in Investigation No. 86-11-019. This tax gross up shall be included in TDPUD's total cost and shall be collected by Sierra. The current tax gross up rates for California depreciable property are .15 (15%) for Transmission (greater than 69 kV) and .17 (17%) for Distribution (less than 69 kV). These rates will change effective January 1, 2009, to .24 (24%) for Transmission(greater than 69 kV)and to .28 (28%) for Distribution(less than 69 W). The tax gross- up rate applied will be the one in effect at the time the project is completed. Invoicing and Payment Procedures Regarding the process of paying for costs incurred by Sierra as a result of its activities on this project, TDPUD will be asked to submit to Sierra an advance payment in the amount of$31,939 to be applied against expenses incurred by Sierra during the planning, design, and engineering phases of the project. These expenses are listed on page 2 of 2 of the accompanying Project Estimate and are identified as shown below. Drafting $ 2,904 Civil Engineering $ 22,399 Surveying $ 3,318 Lands S-318 TOTAL $ 31,939 Should any portion of this advance not be spent, the amount remaining will either be refunded to TDPUD, or will be applied against other expenses incurred by Sierra during the construction phase. If TDPUD chooses to have Sierra construct the new line, prior to the purchasing of materials and the actual start of construction, a second payment will be requested to pay for"total stores" and/or other "voucher" or material costs that will be incurred by Sierra. Should TDPUD choose to construct the new line, Sierra will require that one of its inspectors be on- site to view the construction activities and ensure the line is built to Sierra's standards. The cost associated with this function, which is to be borne by TDPUD, is estimated to be$14,518 and will be billed to TDPUD after the project is completed. As discussed earlier, after the project has been completed, estimated costs will be adjusted to reflect actual costs incurred and an invoice will be submitted to TDPUD for payment within 30 days after the date of the invoice. The net amount due will be calculated based on all available cost information and invoices at the time the project is completed and will be subject to a final adjustment after Sierra has finished its normal internal audit and review of the project's cost components, a process that takes approximately ninety(90) days to complete. Once this process has been concluded and approval has been given to the project and all of its costs, the final result will be compared against the total amount paid by TDPUD. If necessary, an adjustment will be made in the form of either a refund to TDPUD or a request for payment of the additional charge due. 3 Scheduling and Related Information With regard to the schedule for this project,TDPUD has not yet determined a target date for when the new line and underbuild should be placed in-service. In addition, TDPUD has indicated they would like to assume responsibility for constructing the line. Given that these decisions regarding scheduling and construction can be made at a later date, Sierra is prepared to move forward with the planning, design and engineering phase of the project. If the process described above meets with your approval, please indicate your acknowledgement and acceptance by signing in the space provided below. To authorize Sierra to proceed with planning, design and engineering, please return this signed letter, along your advance payment in the amount of $31,939,to me at Sierra's main offices at 6100 Neil Rd.,P.O. Box 6100,Reno,NV, 89520-0024. Should you require assistance or additional information,please contact me at(775)834-5247. Sincerely, Accepted on o r t-n h P r 1 5 ,?n o s 2008 Signature. ti. o ; T�s Gregory P. Lambert Major Account Executive Name: Tim F. T a y-1 or Major Accounts Department Sierra Pacific Power Company Title: P r P-,; r3 P n t- o f t riQ R oa rsd — Truckee Donner PUD Encl: Project Estimate CC: Steve Hollabaugh,Assistant General Manager, Truckee Donner PUD Shaun Adams, Major Projects Manager,Major Projects, SPPCo. Michael Braithwaite, Sr. Engineer, Transmission Design/Civil Engineering, SPPCo. Bob Pohl,Team Leader,Tax,Taxation Department, Sierra Pacific Resources Ellen Costanza, Sr. Contracting Agent,Project Controls&Analysis, SPPCo. 4 PROJECT ESTIMATE PAGE 1 OF 2 04 4/08 PROJECT TITLE: Truckee Donner PUO 607 Lire 6OkV Rebuild DESCRIPTION: Construct approx. 2 rrtiles of new 60kV line,,Oth list. 1nder.bUild. JOB LENGTH: 1.89 miles ESTIMATOR: Mike Braithwaite SPPCO STOCK MATERIAL QUANTITY REO'D UNIT PRICE TOTAL COST 397.5 AA Carina Conductor 30,900 ft. $0.92 $28,514 6OkV Tanget Structure 25 ea. $9,000 $225,000 6OkV Dead End Structure 9 ea. $10,500 $94,500 Material contingency 10% $34,801 TOTAL STORES COST: , 4iR' ;,` '�, o- .g, i,'"; l* .. x 3 ,, e s <a - s s / +C a`'✓ '"y.=T ,,.,. VOUCHERS.- MATERIALS QUANTITY REQ'D UNIT PRICE TOTAL COST None 0 ea. $0 $0 TOTAL MATERIAL VOUCHERS: CONTR LABOR & MISC QUANTITY REO'D UNIT PRICE TOTAL COST Crew Expenses 1 Ls, $0 $0 Equipment rental 1 s. $0 $0 Misc vouchers 1 Ls. $0 $569 TOTAL MISCELLANEOUS VOUCHERS: 69 TOTAL VOUCHERS 569 WORK ORDER ESTIMATE SUMMARY(cunt.) PAGE 2 OF 2 LABOR: SPPCO MAN-HOURS HOURS RATE-$JHR TOTAL COST TRANSMISSION OPERATIONS S'raigM Tame 4460 $65 $14,518 Overtime 466 $58 $0 GENERA!CONSTRUCTION 323 DRAFTING $62 $0 60 $62 $2,904 CIVIL ENGINEERING 30,E $66 $22,399 SURVEYING 260 $62 $3,318 LANDS 40 $62 $3,318 MISC - OTHER 40 $60 $0 TOTAL COMPANY LABOR: 6,45 TRANSPORTATION: HOURS RATE-$1HR TOTAL COST TRANSPORTATION $7,000 TOTAL TRANSPORTATION: ,0 00 SUBTOTAL WORK ORDER; 36,841 CONTINGENCY : 10% $43,68 TOTAL WORK ORDER; P0,525 Cost per mile: $254,246 GRAND TOTAL: L $480,525