HomeMy WebLinkAbout8 Donner Lake Feeder Project Agenda Item # 8
DONNER
�il Public Utility District
ACTION
To: Board of Directors
From: Joe Horvath
Date: August 05, 2009
Subject: Authorize Payments to NV Energy for the Construction of the
Donner Lake Circuit No. 3 Feeder Project
1. WHY THIS MATTER IS BEFORE THE BOARD
Board authorization is required for expenditures in excess of$15,000.
2. HISTORY
The new Donner Lake Circuit 3 feeder is a new 12.47kV distribution feeder that will
originate at the District's Donner Lake Substation and connect to the Tahoe Donner
area. This new circuit is needed to increase capacity, improve system performance
and reliability. It will be approximately 2 miles long and will be built under existing
60kV transmission lines owned by the District and NV Energy. Major milestones in the
history of this project to date include:
• January, 2007 - Initial Discussions with NV Energy
• August 15, 2007 - Board Approval of a Task Order to prepare the CEQA Initial
Study
• December 5, 2007 - Board Approval of CEQA Initial Study
• December 19, 2007 - Public Hearing on CEQA Initial Study
• January 16, 2008 - Adoption of Final CEQA Document
• October 15, 2008 - Board Approval of Design and Pole Contact Agreements with
NV Energy
• July 15, 2009 - Board Approval of Letter of Intent to Purchase Materials from NV
Energy
3. NEW INFORMATION
NV Energy has completed the design for the portion of the transmission line they own,
and they have informed us that they will construct this portion of the project for the
District (see attached letter dated July 9, 2009). NV Energy has estimated
construction costs to be: $1,200,000 for the rebuild of the existing 60kV transmission
line to accommodate the District's new feeder; $350,000 for the construction of the
District's new feeder; and $200,000 for the tax liability payment to cover NV Energy's
federal tax increase due to the upgrading of their transmission facilities. The total not-
to-exceed construction cost for NV Energy's portion of the new underbuild circuit is
$1,550,000. The exact amount of the tax liability payment will be known only after
construction is complete and actual costs are identified.
In addition, the approved CEQA and Storm Water Pollution Prevention Plan (SWPPP)
documents require certain environmental mitigations to be performed during
construction. We have received a Task Order proposal from Inland Ecosystems in the
amount of $13,810 to perform the required mitigation work.
The anticipated project schedule is shown below:
• August 5, 2009 - Consideration of Payment Authorization to NV Energy for the
construction of the Donner Lake Circuit 3 Feeder and associated improvements on
NV Energy's transmission line (this action)
• August 5, 2009 - Consideration of Approval of a Task Order from Inland
Ecosystems to perform environmental mitigations during construction of the
Donner Lake Circuit 3 Feeder(this action)
• August 17, 2009 - Start of NV Energy Construction
• November 1, 2009 - Completion of NV Energy Construction
• November, 2009 - Consideration of Approval of a Tax Liability Payment to NV
Energy
4. FISCAL IMPACT
The source of funding for the new Donner Lake Circuit No. 3 feeder is Facilities Fees
as this project provides increased electrical capacity and improves reliability. Sufficient
funds exist in the Electric Facilities Fees account to cover the monies due NV Energy
for construction of the new underbuild circuit.
Authorization to make payment to NV Energy for the tax liability issue will be brought
to the Board for action in November 2009, or when actual construction costs are
known.
5. RECOMMENDATION
Authorize the General Manager to approve payments to NV Energy for an amount not
to exceed $1,550,000 for the construction of the Donner Lake Circuit 3, to be funded
from Facility Fees.
Approve a Task Order in the amount of $13,810 for Inland Ecosystems to perform the
environmental mitigations during construction as required by the approved CEQA and
SWPPP documents, to be funded from Facility Fees.
Stephen Hollabaugh Michael D. Holley
Assistant General Manager General Manager
A
NVE n e Ir o
by-
July 9,2009
Stephen I follabaugh
Electric Utility Manager
Truckee Donner Public Utility District
P.O. Box 309
Truckee, CA 96160
Dear Steve:
Subject: 607 Underbuild Project
Please find the following estimate and request for a letter of intent pursuant to the Pole Contact
Agreement between Sierra Pacific Power Company, dba NVEnergy, (Sierra) and Truckee
Donner Public Utility District (TDPUD). This Agreement grants TDPUD a license to own and
operate a 12.47kV distribution feeder along Sierra's#607 60kV transmission line as specified in
the referenced contract Agreement.
The#607 transmission line is part of the defined Path 24,the"Sierra Summit Path", which tics
our system to the California Independent System Operator(ISO)Corporation. It has been
determined to be an operationally significant connection between Sierra and PG&E by Western
Electricity Coordinating Council (WECC). Sierra will commence rebuilding this line to
accommodate TDPUD's distribution circuit this fall with the understanding that a May 1, 2010
date is requested for project completion.
Sierra must order long lead materials now to meet the required construction window beginning
in September, 2009. A letter of intent to construct and acknowledgement that payment will be
required upon delivery of materials is requested as assurances for ordering the non-stock
materials. This includes light duty steel poles that have a ten week lead time for$91,379 and
non-stock wood poles that have a 4 week lead time for$166,529, Once construction begins,
TDPUD will be invoiced for the remaining materials and progress payments for the labor.
The estimate for construction of the#607 60kV line is from $1,045,455 to $1,444,013.
Construction time ranges from six to ten weeks. This estimate includes the cost component to
cover Sierra's estimated liability for Federal Income Tax in accordance with California Public
Utilities Decision No. 87-09-026 issued in Investigation No. 86-11-019. Costs have been
estimated for this project by the least expensive method which is also in accordance with Sierra's
engineering and construction practices. The estimate also assumes:
• Worst case scenario for a ten week construction period
• A small amount of road construction for construction access
• A moderate amount of blasting will be required
• Traffic control on 1-80
P.O.BOX 98910, LAS VEGAS,NEVADA 89151-0001 6226 WEST SAMARA AVENUE,LAS VEGAS,NEVADA 89146
P.O.BOX 10100,RENO,NEVADA 89520-0024 6100 NEIL ROAD,RENO,NEVADA 89511 NVEnergy.com
o TDPUD will obtain and meet all mitigation measures outlined in the Federal, State and
Local permits. This includes obtaining required biological surveys prior to construction
and securing a contractor who will implement storm,water pollution prevention measures
as required by your permits.
o An on-site fire crew
o Other items as detailed in the Agreement
Sierra welcomes the opportunity to accommodatc'FDPUD's request to utilize Our facilities for
this project. Please contact me if you have any questions or concerns,
Sincerely,
Shauna K. Adams
Manager Major Projects
Cc: Sanna Schlosser, TDPUD
Joe Florvath, 'FDPUD
Mike Braithwaite, NVE
Greg Lambert,NVE
Gary Porter,NVE
Colin Harlow, NVE
Kelly Toulouse, NVE
Ellen Costanza,NVE
INLAND ECOSYSTEMS, Inc.
WMI 3239 Reno Vista Drive
Reno,NV 89512
IN LAN E) Phone: (775) 786-3223
e-mail: gmerron(a,inlandecosystems.com
ECOSYSTEMS www.inland ecosystems
Mr. Joe Horvath, P.E. July 29, 2009
Electric System Engineer
Truckee Donner Public Utility District
P.O. Box 309
Truckee, CA 96160
Subject: Proposal to Assist the Truckee Donner Public Utility District with
Implementation of California Environmental Quality Act Mitigation
Measures for the Electric System Distribution Project
Dear Mr. Horvath:
Inland Ecosystems (IE) is pleased to submit this Proposal to the Truckee Donner Public Utility
District (District) to assist with the implementation of California Environmental Quality Act
(CEQA) Mitigation Measures for the Electric System Distribution Project. Capital improvements
to the District's electric system are required to provide for load growth, increase system capacity,
and to maintain the operational flexibility of the system.
1.0 SCOPE OF WORK
The following project includes:
1) Installation of 12,000 feet of new distribution feeder to be underbuilt on an
existing transmission line that connects Donner Lake and Tahoe Donner
Substations.
A CEQA Initial Study for this project was undertaken and prepared in accordance with State
Guidelines. The Initial Study concluded that with implementation of Mitigation Measures
outlined below the project would not have a significant effect upon the environment.
TASK 1: Biological Resources
Mitigation Measure BIO-2: Implement Avoidance Measures on Sensitive Habitats
Prior to beginning construction, Inland Ecosystems will delineate Environmentally Sensitive
Areas (ESAs) for limiting work areas near sensitive habitats to the minimum possible area.
1
These areas include wetland habitat at the crest of the hill and near Interstate-80. The ESAs will
be delineated with orange safety fencing. Fencing shall remain in place until all work is
complete. The three (3) drainages areas also at the crest of the hill will need to be covered with
steel plates by contractors where these cross the existing access road to avoid temporary and
permanent impacts. Inland Ecosystems will install the orange safety fencing and provide an
environmental monitor during work near sensitive habitats to prevent impacts. Inland
Ecosystems estimates this task to cover approximately 24-working hours.
TASK 2: Cultural Resources
Mitigation Measure CULT-1: Provide an Environmental Monitor to Minimize
Construction Impacts on Cultural Resources and Retain a Registered Professional
Archeologist and
During project activities, Inland Ecosystems will have a Registered Professional Archeologist
on-call. In the event that evidence of cultural resources is encountered during project activities,
the archeologist would be notified to record such resources and gather available information. An
environmental monitor would be on-site to cover the section of the underbuilt from the crest of
the hill south to 1-80 and areas where new poles may be required to ensure no cultural resources
are impacted. If any potentially undiscovered cultural resources are identified appropriate
measures will be taken to avoid impacts. Inland Ecosystems will coordinate any findings with
the appropriate state, federal, and tribal entities according to standard reporting procedures to
avoid disruption of any archaeological and historical resources. Based on discussion with Joe
Horvath, it is estimated to take approximately 9 working days to complete that section of the
work. In addition, Inland has estimated an additional 3 days time to monitor any sites where
excavation may be required for the underbuilt installation at other locations along the entire
transmission corridor. A total of 120 hours has been allocated to this task.
TASK 3: Hydrology and Water Quality
Mitigation Measure HWQ-1: Implement Best Management Practices (BMPs) and Erosion
Control Measures to Prevent Discharge of Construction Related Pollutants to Surface
Waters
Inland Ecosystems will ensure the project is conducted in accordance with the State Water
Resources Control Board (SWRCB) statewide National Pollutant Discharge Elimination System
(NPDES) General Permit for Discharges of Storm Water Associated with Construction Activity
and includes compliance with a Storm Water Pollution Prevention Plan (SWPPP) for the
protection of water quality. The District's SWPPP meets the requirements of the SWRCB for
this project. Inland Ecosystems will assist the District with implementation of the SWPPP.
Inland Ecosystems will carry out an on-site training workshop to identify where Best
Management Practices (BMPs) and erosion control measures must be in place. Inland
Ecosystems estimates this task to cover approximately 24 working hours.
2
TASK 4: Mitigation Measure HWQ-2: Implement a Hazardous Spill Prevention and
Control Program
Inland Ecosystems shall develop a spill prevention and control program to minimize the potential
for spills of hazardous substances during construction activities. The plan will be completed
before any construction activities begin, and shall include provisions for preventing, containing,
and reporting spills of hazardous materials. Inland Ecosystems will carry out an on-site training
workshop to identify the spill prevention program concurrent with identification of where Best
Management Practices and erosion control measures must be in place. Inland Ecosystems
estimates this task to cover approximately 16 man hours.
2.0 INLAND ECOSYSTEMS TEAM
The IE team members have worked together on numerous projects and are highly trained
biologists and cultural resource specialists. Dr. Glenn Merron will supervise all aspects of the
proposed scope of work. He has over 25 years of experience and has served as Project Manager
for numerous District projects. We have a proven track record of delivering quality products.
Our costs to carry out this work will be on a "Time and Materials"basis, not-to-exceed $13,810.
Thank you for this opportunity to respond to your Request for this Proposal. Should you have
any questions pertaining to this proposal please contact me at (775) 786-3223.
Sincerely,
Glenn Merron, Ph.D.
3
WORK AUTHORIZATION ORDER
2009 ELECTRIC SYSTEM
MITIGATION MONITORING
July 29, 2009
This Work Authorization Order confirms the agreement between the Truckee Donner
Public Utility District (District) and Inland Ecosystems (Contractor) to provide certain services
pursuant to and in accordance with the Scope of Work as defined above.
(i) Schedule, Completion Date
TASK 1: Mitigation Measure BI0-2: Implement Avoidance Measures on Sensitive
Habitats
TASK 2: Mitigation Measure CULT-1: Provide an Environmental Monitor to
Minimize Construction Impacts on Cultural Resources and Retain a
Registered Professional Archeologist
TASK 3: Mitigation Measure HWQ-1: Implement Best Management Practices and
Erosion Control Measures to Prevent Discharge of Construction Related
Pollutants to Surface Waters
TASK 4: Mitigation Measure HWQ-2: Implement a Hazardous Spill Prevention and
Control Program
(ii) Compensation, Invoicing and Payment:
a. Fee. The fee for Work performed by Contractor pursuant to this Work Authorization
Order will be on a "Time and Materials" basis, not-to-exceed $13,810. The fee is based
on the following breakdown:
TASK 1 = $2,045
TASK 2 = 8,165
TASK 3 = 2,140
TASK 4 = 1,585
b. Invoicing and Payment. Consultant will submit an invoice to the District within seven
(7) days after the end of each month on which Work is performed. Payment is due within
fourteen (14) days of receipt of each invoice.
ACCEPTED:
Truckee Donner Public Utility District Inland Ecosystems, Inc.
By: By:
Title: Title:
Date: Date:
4
TABLE 1: Estimated Costs: CEQA Compliance for the Electric System Distribution Project.
Estimate of hours by task
TASK 1 TASK 2 TASK 3 TASK 4 TOTAL
Personnel:
G. Merron 12 16 16 44
A. Bell 12 120 8 140
f
TOTAL HOURS 24 120 24 16 184
184
RATE
G. Merron $95 $1,140 $0 $1,520 $1,520 $4,180
A. Bell $65 $780 $7,800 $520 $0 $9,100
LABOR COST $1,920 $7,800 $2,040 $1,520 $13,280
OTHER DIRECT COSTS TASK 1 TASK 2 TASK 3 TASK 4 TOTAL
PERS MILE $0.51 $50 $350 $50 $50 $501
MISC SUPPLIES $75 $15 $50 $15 $155
TOTAL $125 $365 $100 $65 $530
TOTAL COSTS $2,045 $8,165 $2,140 $1,585 $13,810
Tasks:
1 Implement Avoidance Measures on Sensitive Habitats
2 Provide Environmental Monitor and Retain on-call Archeologist.
3 Implement BMP and Erosion Control Measues
4 Implement a Hazardous Spill Prevention and Control Program