1. WHY THIS MATTER IS BEFORE THE BOARD
The Tahoe Donner Substation Rebuild-2009 Project is complete. A resolution
accepting the project as complete requires Board approval.
2. HISTORY
This project involved rebuilding the Tahoe Donner Substation in order to improve
P
reliability, increase capacity, and ensure compliance with current code requirements.
The Board awarded the engineering contract in November 2007 and equipment
purchase contracts in December 2008. The construction contract was awarded to
PAR Electrical Contractors on July 15, 2009, in an amount not to exceed $622,247.70.
The Board of Directors also established a 10% change order allowance in the amount
of$62,000.
3. NEW INFORMATION
During the course of the project, three change orders were reviewed by staff and
approved by the General Manager. The three change orders totaled $35,486.51, and
did not exceed the $62,000 change order allowance established by the Board of
Directors. The items covered by these change orders generally fell into the following
categories:
• Additional work not included in the original contract: During the course of
the project, it was necessary to perform some additional work that was not
covered by the original bid items. This work included temporary protection of
equipment stored on site and the purchase of new transformer bushings and a
larger auxilliary panel than originally specified. This work totalled $13,851.26.
• Field conditions differing from the contract drawings: There were several
locations where the field conditions differed from the contract drawings. The
work to rectify these conditions included removal, re-installation, and repairs to
existing foundations, and reinfocement of the spill containment wall as well as
additional rock excavation. This work totalled $21,635.25.
4g n August 17, 2011, District staff performed a final walkthrough on the project. The
work performed is considered complete and should be accepted by the District.
Also attached is a draft resolution (Attachment 3) accepting the project and directing
that a Notice of Completion be filed.
4. FISCAL IMPACT
This project is funded by the Capital Projects Fund. FY11 included $1,109,963 in this
p
fund.
5. RECOMMENDATION
Adopt a resolution accepting the Tahoe Donner Substation Rebuild-2009 Project as
complete and authorize the filing of the Notice of Completion.
ollabau h Michael D. Holley
Stephen H g
Assistant General Manager General Manager
Attachment 1
Analysis of Bid Quantities vs.Actual Quantities Constructed
Tahoe Donner Substation Rebuild Project-2009
Contractor:PAR Electrical Contractors,Inc.
Bid Amounts Actual Amounts
Bid Item Description Qty Units Unit Price Subtotal Qty Units Unit Price Subtotal
1.1A 2-6"and 2-2" PVC Conduits 410 FT $ 66.10 $ 27,101.00 410 FT $ 66.10 $ 27,101.00
1.113 6"and 3" PVC and 2"Tele.Conduits 20 FT $ 64.70 $ 1,294.00 20 FT $ 64.70 $ 1,294.00
1.1C 577TD Vault w/full traffic cover 1 EA $ 11,145.20 $ 11,145.20 1 EA $ 11,145.20 $ 11,145.20
1.11) B3048 Comm. Box with full traffic cover 1 EA $ 1,819.50 $ 1,819.50 1 EA $ 1,819.50 $ 1,819.50
1.1E 6"and 2"steel risers 2 EA $ 1,953.20 $ 3,906.40 2 EA $ 1,953.20 $ 3,906.40
1.1F 611
,3" and 2"steel risers 1 EA $ 475.00 $ 475.00 1 EA $ 475.00 $ 475.00
1.1G Rock Excavation 2 HRS $ 2,821.00 $ 5,642.00 4 HRS $ 2,821.00 $ 11,284.00
Control Enclosure,Recloser Controls,
1.2 Manholes,Cable and Conduit 1 LS $ 96,212.00 $ 96,212.00 1 LS $ 96,212.00 $ 96,212.00
2A All other work as described by Contract 1 LS $474,652.40 $474,652.40 L 1 LS $474,652.40 $474,652.40
Total $622,247.50 Total $627,889.50
Attachment 2
Change OrderTRUCKEE DO,
PUblic Utility District
Contract Name: Tahoe Donner Substation Rebuild-2009
3 (Field Changes 12
a Order No: and 14 Orig. Contract Amt. $ 622,247.70 Days NA
Contract Change
Date:
8/17/11 Prev. Apprd Changes$ 20,364.51 Days NA
Contracto
r: PAR Electrical Contractors, Inc This Change$ 15,122.00 Days NA
Revised Contract Amt. $ 657,734.21 Days NA
Remaining Authorized
Change Amt. $ 26,513.49 Days NA
This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct,
furnishequipment
a ui ment and materials, and perform all work as necessary or required to complete the Change Order
Items for a lump sum price agreed upon between the Contractor and District.
Increase in (Decrease) Contract Time
Contract in Contract Extension
Description of Changes Amount $ Amount $ (days)
Field Change 12: Purchase and installation of new $10,230.00 0 days
transformer bushings
Field Change 14: Materials to repair control enclosure ($750.00) 0 days
damage 0 days
$5,642.00 Y
Additional Rock Excavation—2 hours
Totals $15,872.00 ($750.00) 0 days
Net change in contract amount(increase or decrease) $15,122.00 0 days
The amount of the Contract will be increased by the sum of$ 15,122.00 and the Contract Time shall not
be extended. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the
contract price specified for each item including any and all supervision costs and other miscellaneous costs
related to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on
account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other
necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete
the Change order items. This document will become a supplement of the contract and all provisions will apply
hereto. It is understood that the Change Order shall be effective when approved by the District.
Accepted: /Contractor Date:
(Signature)
Approved: /District Date:
(Signature)
Pagel
Attachment 3
`NNER
. ....... TRUCKEE Du
$:.
p"
' k
Resolution No. 2011
- XX
AUTHORIZING THE ACCEPTANCE OF
TAHOE D ONNER SUBSTATION REBUILD - 2009 PROJECT
AND DIREC
TING FILING OF THE NOTICE OF COMPLETION
WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the determination to
undertake the Tahoe Donner Substation Rebuild—2009 Project; and
WHEREAS, PAR Electrical Contractors, Inc., was selected by the District to perform the work; and
WHEREAS, PAR Electrical Contractors, Inc., has completed all of the Work included in the Project; and
WHEREAS,The District's Electrical Engineer,Sanna Schlosser,now certifies the completion of the project;and
WHEREAS,the District's Water Utility Manager, Michael Holley, has recommended that the work be accepted
by the District;
NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows:
1. That the District hereby accepts the Tahoe Donner Substation Rebuild—2009 Project as complete.
2. That the Clerk of the District be directed to file with the County of Nevada the Notice of Completion, a
copy of which is attached hereto.
3. That 35 days following the filing of the Notice of Completion, the monies retained from the contractor
payments be released to the contractor if no claims have been made to the District by material
suppliers, laborers, or sub-contractors.
PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the District on the
7t" day of September 2011 by the following roll call vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
By
Jeff Bender, President of the Board
ATTEST:
Michael D. Holley, Clerk of the Board
RECORDING REQUESTED BY:
Truckee Donner Public Utility District
WHEN RECORDED, RETURN TO:
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
11570 Donner Pass Road
Truckee, CA 96161
THE UNDERSIGNED DECLARES
DOCUMENTARY TRANSFER TAX-NONE
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN:
1. That the name and address of the public entity for whom the improvement project was done, as owner
s
thereof, i the Truckee Donner Public Utility District, 11570 Donner Pass Road,Truckee, CA 96161.
2. Nature of interest or estate of owner: beneficial interest of a public utility easement for installation of
water facilities.
p
3.
That on September 7, 2011 the hereinafter described improvements were accepted as complete
pursuant to Resolution 2011-XX of the Truckee Donner Public Utility District, the awarding authority.
4. That the subject improvements of the Notice are generally described and identified as follows:
Tahoe Donner Substation Rebuild—2009 Project, Truckee, California.
5. That the name and address of the contractor for such project was: PAR Electrical Contractors,
Inc., 1465 West 4th Street, Reno, NV. 89503
1 certify under penalty of perjury under the laws of the State of
California that the foregoing is true and correct.
Dated: TRUCKEE DONNER PUBLIC UTILITY DISTRICT
By
Michael D. Holley, General Manager
MAIL TAX STATEMENTS TO:
SAME AS ABOVE
Legal References: CC-3093,CCP-2003(oath), 2015.5(unsworn statement)