February 11, 2000
To: Board of Directors
From: Joe Horvath, Distribution Engineer
Subject: Transformer Bids-2000
Bids have been opened and analyzed for the District's purchase of padmount and polemount
transformers. These transformers are required to meet our customer obligations and their
purchase has been budgeted. Attached is a summary schedule of the bid information received.
The schedule shows the description and quantity of transformers required, vendor name,
quoted price, adjusted price, delivery time, and if they meet our specifications. The following
factors were used in determining the successful bidder.adjusted price, adherence to our
contract and specifications, and delivery time. As shown on the summary schedule, the quoted
base price versus the price adjusted for losses can change the outcome of the bid. Adherence
to our contract and specifications is very important, however minor deviations from our
specifications may be permitted based on our review of the particular situation
Recommendation:
I recommend the Board approve the following Schedules be awarded to vendors as shown
below for the purchase of transformers for the Districts electric system:
Extended Price
Schedule Vendor Quantity Unit Price Not to Exceed
A Western States 15 $465.00 $6,975.00
B Western States 12 $583.00 $6,996.00
C Western States 5 $720.00 $3,600.00
D Western States 10 $960.00 $9,600.00
E Western States 3 $1135.00 $3,405.00
F Western States 2 $3244.00 $6,488.00
G Western States 1 $3286.00 $3,286.00
H Western States 1 $4158.00 $4,158.00
1 Western States 1 $4803.00 $4,803.00
J Western States 1 $7505.00 $7,505.00
K Western States 1 $3263.00 $3,263.00
Total $60,079.00
TRANSFORMER BID SUMMARY - 2000
Schedule A
25kva, 7200/12470v, 120/240v, Pole Mount, Quantity: 15
Quoted Adjusted
Bidder Manuf. Price (ea) Price (ea) Delivery Time Meets Specs
G.E. Supply G.E. $566.00 $1,067.67 30-40 weeks
General Pacific Ermco $622.00 $1,047.82 20-22 weeks
General Pacific Kuhlman $595.00 $1,076.48 12-14 weeks
Howard Industries Howard $550.00 $1,040,32 14-16 weeks
Moloney Electric Moloney $647.00 $1,152.71 8-10 weeks
Wesco Distribution ABB $678.00 $1,104.90 13 weeks NO
Western States Cooper $465.00 $979.09 10 weeks
Western States Pauwels NO
Schedule B
37.5kva,7200/12470v, 120/240v, Pole Mount, Quantity: 12
Quoted Adjusted
Bidder Manuf. Price (ea) Price (ea) Delivery Time Meets Specs
G.E. Supply G.E. $719.00 $1,366.46 30-40 weeks
General Pacific Ermco $785.00 $1,376.45 20-22 weeks
General Pacific Kuhlman $715.00 $1,360.36 12-14 weeks
Howard Industries Howard $670.00 $1,320.85 14-16weeks
Moloney Electric Moloney $759.00 $1,394.48 8-10 weeks
Wesco Distribution ABB $761.00 $1,346.02 13 weeks NO
Western States Cooper $583.00 $1,246.15 10 weeks
Western States Pauwels NO
Schedule C
50 kva, 7200/12470v, 120/240v, Pole Mount, Quantity: 5
Quoted Adjusted
Bidder Manuf. Price (ea) Price (ea) Delivery Time Meets Specs
G.E. Supply G.E. $803.00 $1,613.83 30-40 weeks
General Pacific Ermco $938.00 $1,676.31 20-22weeks
General Pacific Kuhlman $820.00 $1,642.37 12-14weeks
Howard Industries Howard $829.00 $1,604.54 14-16weeks
Moloney Electric Moloney $869.00 $1,648.57 8-10 weeks
Wesco Distribution ABB $938.00 $1,643.99 13 weeks NO
Western States Cooper $720.00 $1,534.96 10 weeks
Western States Pauwels NO
Page 1 of 3 02/11/2000
Schedule D
25kva, 7200/12470v, 240/120v, Padmount, Quantity: 10
Quoted Adjusted
Bidder Manuf. Price (ea) Price (ea) Delivery Time Meets Specs
G.E. Supply G.E. $1,066.00 $1,530.89 12-20weeks
General Pacific Ermco $1,144.00 $1,563.67 30-32weeks
General Pacific Kuhlman NQ
Howard Industries Howard $941.00 $1,427.84 22-24weeks
Wesco Distribution ABB $1,204.00 $1,676.65 14-16weeks NO
Western States Cooper $960.00 $1,403.22 10 weeks
Western States Pauwels NO
Schedule E
50kva, 7200/12470v, 240/120v, Padmount, Quantity: 3
Quoted Adjusted
Bidder Manuf. Price (ea) Price (ea) Delivery Time Meets Specs
G.E. Supply G.E. $1,376.00 $2,188.31 12-20weeks
General Pacific Ermco $1,374.00 $2,148.73 30-32weeks
General Pacific Kuhlman NQ
Howard Industries Howard $1,203.00 $1,999.40 22-24weeks
Wesco Distribution ABB $1,336.00 $2,174.91 14-16 weeks NO
Western States Cooper $1,135.00 $1,953.62 10 weeks
Western States Pauwels NQ
Schedule F
45kva,7200112470v,208/120v, Padmount, Quantity: 2
Quoted Adjusted
Bidder Manuf. Price (ea) Price (ea) Delivery Time Meets Specs
G.E. Supply G.E. $4,245.00 $5,062.21 14-22 weeks
General Pacific Ermco NO
General Pacific Kuhlman NO
Howard Industries Howard $3,691.00 $4,656.23 20-22 weeks
Wesco Distribution ABB $3,229.16 $4,113.46 20-22 weeks NO
Western States Cooper $3,244.00 $4,252.33 10-12 weeks
Western States Pauwels $3,480.00 $4,355.49 18-20 weeks
Schedule G
45kva,7200/12470v, 277/480v, Padmount, Quantity: 1
Quoted Adjusted
Bidder Manuf. Price (ea) Price (ea) Delivery Time Meets Specs
G.E. Supply G.E. $4,295.00 $5,142.44 14-22 weeks
General Pacific Ermco NO
General Pacific Kuhlman NO
Howard Industries Howard $3,914.00 $4,758.46 20-22 weeks
Wesco Distribution ABB $3,468.42 $4,283.44 20-22 weeks NO
Western States Cooper $3,286.00 $4,302.51 10-12 weeks
Western States Pauwels $4,447.92 $5,375.85 18-20 weeks
Page 2 of 3 02/11/2000
Schedule H
150kva, 7200112470v, 208/120v, Padmount, Quantity: 1
Quoted Adjusted
Bidder Manuf. Price (ea) Price (ea) Delivery Time Meets Specs
G.E. Supply G.E. $5,098.00 $7,048.58 14-22 weeks
General Pacific Ermco NO
General Pacific Kuhlman NO
Howard Industries Howard $4,912.00 $7,140.26 20-22 weeks
Wesco Distribution ABB $4,083.00 $6,160.55 20-22 weeks NO
Western States Cooper $4,158.00 $6,571.43 10-12 weeks
Western States Pauwels $4,545.00 $6,743.95 18-20 weeks
Schedule I
225kva, 7200/12470v, 277/480v, Padmount, Quantity: 1
Quoted Adjusted
Bidder Manuf. Price (ea) Price (ea) Delivery Time Meets Specs
G.E. Supply G.E. $6,299.00 $8,140.56 14-22 weeks
General Pacific Ermco NQ
General Pacific Kuhlman NO
Howard Industries Howard $5,270,00 $8,394.83 20-22 weeks
Wesco Distribution ABB $4,652.63 $7,407.22 20-22 weeks NO
Western States Cooper $4,803.00 $7,800.98 10-12 weeks
Western States Pauwels $5,475.00 $8,299.60 18-20 weeks
Schedule J
500kva, 7200/12470v, 120/208v, Padmount, Quantity: 1
Quoted Adjusted
Bidder Manuf. Price (ea) Price (ea) Delivery Time Meets Specs
G.E. Supply G.E. $8,199.00 $13,742.75 14-22 weeks
General Pacific Ermco NO
General Pacific Kuhlman NO
Howard Industries Howard $7,974.00 $13,796.26 20-22 weeks
Wesco Distribution ABB $6,968.42 $12,665.64 20-22 weeks NO
Western States Cooper $6,819.00 $13,453.67 10-12 weeks
Western States Pauwels $7,505.00 $13,234.88 18-20 weeks
Schedule K
45kva, 14400v Delta, 120/208v, Padmount, Quantity: 1
Quoted Adjusted
Bidder Manuf. Price (ea) Price (ea) Delivery Time Meets Specs
G.E. Supply G.E. $4,486.00 $5,231.61 14-22 weeks
General Pacific Ermco NO
General Pacific Kuhlman NO
Howard Industries Howard $3,878.00 $4,766.98 20-22 weeks
Wesco Distribution ABB $3,322.91 $4,176.21 20-22 weeks NO
Western States Cooper $3,263.00 $4,270.91 10-12 weeks
Western States Pauwels $3,480.00 $4,341.05 18-20 weeks
Page 3 of 3 02/11/2000