HomeMy WebLinkAbout2000-04-05 Agenda Packet - Board (11) TDPUD Memorandum
March 31, 2000
TO: Board of Directors
FROM: Neil Kaufman, Water System Engineer
SUBJECT: HIGHWAY 89 IRRIGATION PIPELINE (TRUCKEE FALLS GOLF COURSE)
PROJECT BID
Agenda # 8
BACKGROUND
The Board of Directors in the 2000 budget approved a project to install an irrigation water pipeline
to the Truckee Falls Golf Course. This project is to supply irrigation water from the Donner Creek
well to the golf course. The final funding for this project will be from the owners of the Truckee Falls
Golf Course either in money or land. It is important that this project is completed before the high
water demand summer usage season in Truckee. Project plans, specifications, and contract
documents are complete for the Truckee Falls Golf Course Pipeline project.
We are now asking for authorization to advertise for bids for the construction of this project with a
proposed bid opening date of April 27, 2000. This bid opening date will be after the CEQA is
complete and approved.
Attached is the engineer's estimate for the project in the amount of $260,220..
RECOMMENDATION
I recommend that the Board authorize staff to advertise for and accept bids for construction of the
Truckee Falls Golf Course Pipeline Project with a bid opening date of April 27, 2000.
Truckee Falls GC Irrigation Pipeline-2000
Description Quantity Units Unit Price Total
Mobilization 1 LS $ 10,000 $ 10,000
8" PVC Water Main 1,750 LF $ 60 $ 105,000
8" DIP Water Main 800 LF $ 75 $ 60,000
Blow Off Assembly 1 EA $ 2,000 $ 2,000
Meter Assembly 1 EA $ 12,000 $ 12,000
24" Casing 125 LF $ 250 $ 31,250
Connect to 8" Main 2 EA $ 2,000 $ 4,000
Traffic Control 1 LS $ 6,000 $ 6,000
Aggregate Base Shoulder 270 Sq. Yards $ 23 $ 6,210
Paving & Base 330 Sq. Yards $ 72 $ 23,760
Total $ 260,220