June 21, 2000
TO: Board of Directors
FROM: Neil Kaufman, Water System Engineer
SUBJECT: IRRIGATION PIPELINE REHABILITATION PROJECT BID
AGENDA # 8
BACKGROUND:
The Board of Directors approved a project to install an irrigation water pipeline to the
Truckee Falls Golf Course. This project is to supply irrigation water from the Donner
Creek well to the golf course. The final funding for this project will be from the owners
of the Truckee Falls Golf Course either in money or land.
A portion of this project included the use of an eight-inch line under 180. After pressure
testing and TV inspection, it was determine that the pipeline has several leaks. Since
this pipeline is under 180 the best method of repair/rehabilitation is to line the pipe.
Project plans, specifications, and contract documents are complete for the Irrigation
Pipeline Rehabilitation project.
We are now asking for authorization to advertise for bids for the construction of this
project with a proposed bid opening date of July 21, 2000.
RECOMMENDATION:
I recommend that the Board authorize staff to advertise for and accept bids for
construction of the Truckee Falls Golf Course Pipeline Project with a bid opening date
of July 21, 2000.