HomeMy WebLinkAbout2000-11-15 Agenda Packet - Board (10) TDPUD MEMORANDUM November 7, 2000 TO: Board of Directors FROM: Neil Kaufman, Water System Engineer SUBJECT: TRUCKEE FALLS GOLF COURSE IRRIGATION PIPELINE CHANGE ORDER #2 AGENDA # BACKGROUND: The Board of Directors awarded the Contract for construction of the Truckee Falls Golf Course Irrigation Pipeline to Longo Construction in the amount of $294,725. Change Order No. 1 was approved by the Board on September 6, 2000 for $35,334.36 with a revised Contract Amount of$330,059.36. 1 am requesting approval of Change Order No. 2 to the Contract. This Change Order covers 2 items and closes all outstanding issues related to this Contract: Item 1: In order to eliminate some uncertainties during the Bidding process, the Bidding Documents were changed to state that pavement restoration in excess of 4-inches in thickness would be treated as a "Changed Condition" and the contractor would be entitled to additional compensation. Pavement restoration less than 4-inches in thickness would be included in the Contractor's Bid. The pavement thickness across Donner Pass Road is about 10 inches and an amount of$9,601.81 is due to Longo Incorporated. Item 2: In order to eliminate some uncertainties during the Bidding process, the Bidding Documents were changed to state that pavement restoration in excess of 4-inches in thickness would be treated as a "Changed Condition" and the contractor would be entitled to additional compensation. Pavement restoration less than 4-inches in thickness would be included in the Contractor's Bid. The pavement thickness across the driveway at the Shell Station is about 6 to 7 inches and an amount of $1,258.92 is due to Longo Incorporated. RECOMMENDATION: I recommend that the Board authorize Contract Change Order #2 in the amount of $10,860.73. The revised contract total would be $340,920.09. Attachment- Contract Change Order No. 2 TR . . - Change Order rIct trict Contract Name: TRUCKEE FALLS GOLF COURSE IRRIGATION PIPELINE Contract Change Order No: 2 Orig. Contract Amt. $ 294,725.00 Days NA Date: November 7, 2000 Prev. Apprd Changes$ 35,334.36 Days NA Contractor: LONGO INCORPORATED This Change$ 10,860.73 Days NA Revised Contract Amt. $ 340,920.09 Days NA This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items for a lump sum price agreed upon between the Contractor and District. Increase in (Decrease) Contract Time Contract in Contract Extension Description of Changes Amount ($)._ Amount $ da s 1) Additional pavement and sawcutting at SR 89 and 9,601.84 NA Donner Pass Road 2) Additional pavement and sawcutting at Shell Station 1,258.92 NA Driveway Totals 10,860.73 Net change in contract amount (increase or decrease) $10,860.73 The amount of the Contract will be increased (decreased) by the sum of $10,860.73 and the Contract Time shall not be modified. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete the Change order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the District. Accepted: -- "= /Contractor Date: (Signature) Approved: /District Date: (Signature) Change Order Form I TRUCKEE DONNER F—L, Public Utility District Resolution No, 2000-_ AUTHORIZING THE ACCEPTANCE OF THE COYOTE MOON GOLF COURSE IRRIGATION PIPELINE PROJECT AND DIRECTING FILING OF THE NOTICE OF COMPLETION WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the determination to construct the Coyote Moon Golf Course Irrigation Pipeline Project; and WHEREAS, the contract was awarded to Longo Incorporated of Alpine Meadows, California, and the contractor entered into an agreement with the District to perform the work; and WHEREAS, the Districts Water Engineer, Neil Kaufman, has recommended that the work be accepted by the District; NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows: 1. That the District hereby accepts the Coyote Moon Golf Course Irrigation Pipeline Project as complete. 2. That the Clerk of the District be directed to file with the County of Nevada the Notice of Completion, a copy of which is attached hereto. 3. That 35 days following the filing of the Notice of Completion, the 10% retained from the contractor payments be released to the contractor if no claims have been made to the District by materiel suppliers or laborers. PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the District on the 2000 by the following roll call vote: AYES: NOES: ABSENT: TRUCKEE DONNER PUBLIC UTILITY DISTRICT By J. Ron Hemig, President of the Board ATTEST: Peter L. Holzmeister, Clerk of the Board smc RECORDING REQUESTED BY: Truckee Donner Public Utility District WHEN RECORDED, RETURN TO: TRUCKEE DONNER PUBLIC UTILITY DISTRICT Post Office Box 309 Truckee, CA 96160 NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN: 1. That the name and address of the public entity for whom the improvement project was done, as owner thereof, is the TRUCKEE DONNER PUBLIC UTILITY DISTRICT, Post Office Box 309, Truckee, CA 96160. 2. That on the hereinafter described improvements were accepted as complete pursuant to a resolution of the Truckee Donner Public Utility District, the awarding authority. 3. That the subject improvements of the Notice are generally described and identified as follows: Coyote Moon Golf Course Irrigation Pipeline Project 4. That the name of the contractor for such project was: Longo Incorporated, 150 Alpine Meadows Road, Suite 4,Alpine Meadows, CA 96146. Dated: TRUCKEE DONNER PUBLIC UTILITY DISTRICT By Peter L. Holzmeister, General Manager STATE OF CALIFORNIA COUNTY OF NEVADA On before me, Susan M. Craig, personally appeared PETER L. HOLZMEISTER, personally known to me to be the person whose name is subscribed to the within instrument and acknowledged to me that he executed the same in his authorized capacity, and that by his signature on the instrument the person or the entity upon behalf of which the person acted, executed the instrument. Capacity claimed by signer: Corporate officer-ClerktEx-officio Secretary of the Truckee Donner Public Utility District. Witness my hand and official seal. Susan M. Craig, Notary