HomeMy WebLinkAbout6 Interstate 80 Pipeline rehab TDPUD MEMORANDUM February 16, 2001 TO: Board of Directors FROM: Neil Kaufman, Water System Engineer SUBJECT: INTERSTATE 80 PIPELINE REHABILITATION CHANGE ORDER NO. 1 AGENDA # BACKGROUND: In the fall of 200, the Board of Directors awarded the Contract for the INTERSTATE 80 PIPELINE REHABILITATION project to Hydrotech Incorporated. The project has been completed and I am requesting a Change Order covering 2 items,which represent the only outstanding issues for this contract . Item 1: The original Contract indicated that all earthwork and excavations would be performed by the District. There were concerns related to stability of the excavations and ii was decided that temporary shoring should be utilized. The cost of this item ($2,052.75) represents the Contractor's labor involved in installation of the shoring. Item 2: There is a valve assembly located exposed and aboveground adjacent to the excavation on the south side of Donner Creek. One of these valves froze and split causing a leak than washed dirt and debris into the excavation and the newly lined pipe. This total ($2,052.75) represents costs involved removing debris from the excavation and use of a vacuum cleaning truck to remove debris from inside of the pipe. RECOMMENDATION: I recommend that the Board authorize Contract Change Order #1 in the amount of $4,205.55 with no change in the Contract completion date. Attachment-Contract Change Order#1 FEB-16-2001 09:40 HYDROTECH 01 TRUCKEE DONNER Change Order Contract Name: INTERSTATE 80 PIPELINE REHABILITATION Contract Change Order No: t Ong, Contract Amt S 76,346.00 Days NA Date: February 15,2001 Prev,Appid Changes S 0.00 Days NA Contractor: HYDROTECH INCORPORATED This Change$ 4,Z06.55 Days NA Revised Contract Amt. $ 80,551.55 Days NA This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items for a lump sum price agreed upon between the Contractor and District. Increase in (Decrease) Contract Time Contract in Contract Extension Description of Changes Amount $ Amount $ (days) 1) Installation of Shoring S2,052-75 NA 2) Cleanup Work related to Main Break S2,152.80 NA Totals $4,205.55 Net change in Contract amount(increase or decrease) $4,205.55 The amount of the Contract will be increased (decreased) by the sum of$4,205.55 and the Contract Time shall not be extended. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract prim specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order, The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete the Change order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved try the District. Accepted: !Contractor Dater (Signature) Approved: /District Date: (Signature) rnTni o r+ 'VIII TRUCKEE DONNER Publici District Resolution No, 2001 -_ AUTHORIZING THE ACCEPTANCE OF THE INTERSTATE 80 PIPELINE REHABILITATION PROJECT AND DIRECTING FILING OF THE NOTICE OF COMPLETION WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the determination to rehabilitate the Interstate 80 pipeline; and WHEREAS, the contract was awarded to Hydrotech, Inc., and the contractor entered into an agreement with the District to perform the work; and WHEREAS, the District's Water Engineer, Neil Kaufman, has recommended that the work be accepted by the District; NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows: 1. That the District hereby accepts the Interstate 80 Pipeline Rehabilitation Project as complete. 2. That the Clerk of the District be directed to file with the County of Nevada the Notice of Completion, a copy of which is attached hereto. 3. That 35 days following the filing of the Notice of Completion, the 10% retained from the contractor payments be released to the contractor if no claims have been made to the District by materiel suppliers or laborers. PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the District on the 20'"day of February 2001 by the following roll call vote: AYES: NOES: ABSENT: TRUCKEE DONNER PUBLIC UTILITY DISTRICT By James A. Maass, President of the Board ATTEST: Peter L. Holzmeister, Clerk of the Board smc RECORDING REQUESTED BY: Truckee Donner Public Utility District WHEN RECORDED, RETURN TO: TRUCKEE DONNER PUBLIC UTILITY DISTRICT Post Office Box 309 Truckee, CA 96160 NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN: 1. That the name and address of the public entity for whom the improvement project was done, as owner thereof, is the TRUCKEE DONNER PUBLIC UTILITY DISTRICT, Post Office Box 309, Truckee, CA 96160. 2. That on February 20, 2001, the hereinafter described improvements were accepted as complete pursuant to a resolution of the Truckee Donner Public Utility District, the awarding authority. 3. That the subject improvements of the Notice are generally described and identified as follows: Interstate 80 Pipeline Rehabilitation. 4. That the name of the contractor for such project was: Hydrotech, Inc., 155 Lyon Drive, Fernley, NV 89408. Dated: TRUCKEE DONNER PUBLIC UTILITY DISTRICT By Peter L. Holzmeister, General Manager STATE OF CALIFORNIA COUNTY OF NEVADA On before me, Susan M. Craig, personally appeared PETER L. HOLZMEISTER, personally known to me to be the person whose name is subscribed to the within instrument and acknowledged to me that he executed the same in his authorized capacity,and that by his signature on the instrument the person or the entity upon behalf of which the person acted, executed the instrument. Witness my hand and official seal. Susan M. Craig, Notary