Memorandum
To: Board of Directors
From: Peter Holzmeister
Date: March 16, 2001
Subject: Request for additional compensation for Sauers Engineering
Please review the attached letter from Keith Knibb Dated March 7, 2001. He is asking
that we consider increasing the compensation authorized to Sauers Engineering for
preparation of the Donner Lake CEQA because they had to do additional work in
revising the documents to eliminate the treatment plant. The first set of documents were
based on construction of a treatment plant and use of a lake intake. So many critical
comments were submitted that we modified the project to eliminate surface water and
use ground water. This required that a new Negative Declaration be prepared and
circulated, thus requiring additional work on the part of the Sauers Engineering staff.
RECOMMENDATION: I recommend that the Board approve the request submitted by
Sauers Engineering for an increase in their authorization of$4,081.76 for preparation of
the Donner Lake environmental documents.
Sauers Engineering, Inc.
Civil & Environmental Engineers
March 7, 2001
Mr. Peter Holzmeister
Truckee Donner Public Utility District
P.O. Box 309
Truckee, CA 96160-0309
SUBJECT: DONNER LAKE WATER SYSTEM CEQA
Dear Peter:
In September 2000, the District authorized Sauers Engineering, Inc. to provide services
related to the preparation of the CEQA environmental review for the Donner Lake water
system. Based on our proposal, the authorization was for a fixed fee of$6,000.00. This
is typical for District projects requiring a negative declaration. In the case of the Donner
Lake project, however, significant additional work was needed based on a change in
project scope including an amended initial study and negative declaration, and the
recirculation of the documents. I am requesting an increase in authorization to cover the
additional work.
Our actual costs on this project totaled $10,081.76. I am therefore requesting an increase
in authorization of$4,081.76. Included with this letter is the final invoice for this project
which reflects the increased amount. If this acceptable, please process the enclosed
invoice. If this is not acceptable, please let me know and we will prepare a final invoice
for the original amount.
Yo ly,
Keith Knibb
Enc.
440 Lower Grass Valley Road, Suite A, Nevada City, CA 95959 (530) 265-8021 Fax (530) 265-6834
Sauers Engineering, Inc.
Civil & Environmental Engineers
INVOICE
Date 03/07/01
Truckee Donner PUD Invoice 4 2502
PO Box 309
Truckee CA 96160-309 Job 4 95-006-81
Client Code TDPUD-81
Job Description: Dormer Lake Water Svstem Environmental Review
FOR PROFESSIONAL SERVICES:
Progress Billing -March 2001
Contract Amount Job Status Amount to Date Less Previous Invoices Amount Due
Origginal
$6,000.00 100.00% $6,000.00 $5,700.00 $300.00
Additional Authorization
$4,081.76 100,00% $4,081.76 $0.00 $4,081.76
Total Due $4381.76