HomeMy WebLinkAbout7 Agreement Southwest Gas ONNERR� II rl IE D Public 1i Utility District Memorandum Item , To: Board of Directors From: Ed Taylor, Water Superintendent Date: 07/13/01 Subject: Consideration of a draft joint trench agreement with Southwest Gas Company. BACKGROUND: The District has constructed joint trench projects with Southwest Gas Company (SWG) several time over the last four years. Currently the District is constructing a project in Donner Lake in which the Districts contractor is digging the trench and SWG is installing gas pipeline in conjunction with our contractor. SWG is proposing to install 13000 + feet of gas pipeline in the west end area of Donner Lake. SWG has proposed a joint trench agreement with the District to excavate the trench, backfill and repave the trench line for a fee of$33.25 per foot. The District will furnish and install in the open trench the pipe and all fittings. The District will install new service next construction season. RECOMMENDATION: I recommend that the Board authorize the General Manager to inter into an agreement with Southwest Gas Company for joint trenching of pipelines in the Donner Lake Area. •Page 1 SOUTHWEST GRS [ORPORRTIOR W July 11, 2001 Ed Taylor Truckee Donner Public Utility District 11570 Donner Pass Road Truckee, CA 96160 RE: West Donner Lake/Gas Common Trench Dear Mr. Taylor: The purpose of this letter is to establish an agreement between Southwest Gas Corporation and Truckee Donner Public Utility District Water (TDPUD) regarding a joint-use trench for the above referenced project. Enclosed please find a project drawing designating the approximate location of the joint trench area. Additionally, please note the trench cross-section in Attachment "A". TDPUD's portion of the total trenching cost amounts to $33.25 per foot in joint trench areas designated in Attachment "A". By signing this Letter of Agreement, TDPUD agrees to pay Southwest Gas Corporation for the use of a trench provided by Southwest Gas Corporation or its subcontractor. Southwest Gas Corporation shall be paid for approximately 13,500 lineal feet of joint trench installed. If TDPUD requires additional facilities, separate negotiations will be required for each addition. In the event TDPUD's 8-inch pipe and materials are not ready for installation at the time the gas line is installed, the trench will be completed without the proposed TDPUD pipe. TDPUD will be held responsible for payment specified in this Agreement, even if trench is completed without the TDPUD pipe installed due to TDPUD's delays or failure to provide materials. Southwest Gas Corporation assumes no liability for any TDPUD facilities. Scheduling of TDPUD's pipe installation must be coordinated between TDPUD and Southwest Gas' contractor. TDPUD will be responsible for all materials installation and inspection of their facilities. This agreement does not include re-excavating for tie-ins after backfilling. All materials to install 8-inch pipe will be supplied by TDPUD (i.e. fused pipe, end caps, locator wire, etc.) 400 Eagle Station Lane/ P.O. Box 1190/ Carson City, Nevada 89702-1190/(775) 882-2126 Ed Taylor Page Two July ... .... Should complications arise beyond the anticipated scope of construction, additional costs will be negotiated at the time they occur. These 1 ` complications include, but are not limited to, the inability to obtain adequate trench depth for any reason and unanticipated environmental remediation requirements. In the event that additional costs cannot be negotiated at the time complications occur, this Joint Trench Agreement will be terminated. Southwest Gas Corporation assumes responsibility associated with the trenching, backfill, and overall integrity of the supplied trench only. Southwest Gas Corporation is not responsible for acquisition, delivery, fabrication, installation, or integrity of materials of TDPUD facilities installed in the joint-use trench. The joint trench area covered in this agreement is west and south of South Shore Drive in Donner Lake. This area includes Summit Court, Willow Street, Fir Street, Pine Street, Spruce Street, Eder Court, Ute Drive, Pine Court, Pine Drive, Aspen Street, Fawn Street, Salmon Street, Washoe Road, Maple Street, Cedar Drive, Dogwood Street, Larch Street, Conifer Drive and Cottonwood Drive. Trench Description Cost/Ft. Provide trench for one 8-inch water line $33.25/LF This price is contingent upon the ability to pump any groundwater encountered into the TSD sanitary sewer system. Additional costs will need to be negotiated if haul-off of groundwater is required. Southwest Gas Corporation will invoice TDPUD as the Work is completed. Please sign below and return this Letter of Agreement to my attention. Upon execution, a copy will be returned to you for your file. Should you have any questions regarding this Agreement, please call me at (775) 887-2855. Sincerely, Eric DeBonis Manager/Engineering Northern Nevada Division gd Attachment Ed Taylor Paee Two July 11, 2001 Accepted By: SOUTHWEST GAS CORPORATION TDPUD (Water) Signature Date Signature Date Title Title -"tN ITIJAUcC tc. tr�r (k c `v L +j 2xlAIAJ. �N11NuS hLWD (.��rt� Cl r) 3 PU(7 rti<r(rtJ =. TFfe AL&MLi 011RNwp-PRR9ME if51 0/.iA W.P.No. U tM. nw._______ eR W Mu0»W..[MO MYCGIM Sd..RW. PRw. __ eww IpfY.41 ho .Cmtxt t M wNTX� aowi snwi xo. .r xa. om. SOOTNfPSf W OOFPOPA710N arm e.uw LLLP- isouna MEA o..,er mxa er +caw.er waves Puwr avw»Ana nu. M as lawlbn Wn. xm Rn. wn �'— mw rama__ /11•s..,.hl(7N ")Zt%&k'H aRartnrr wnrs •W+ w ww ram n oa__ TP • � • NER DistrictIlity NN IC Memorandum To: Board of Directors From: Ed Taylor, Water Superintendent Date: 07/13/01 Subject: Authorization to bid for installation of 8 inch water main for the joint TDPUD- SWG pipeline project at Donner Lake BACKGROUND: Staff has recommended a joint project for pipeline installation with Southwest Gas Company. The Southwest gas contractor will dig the trench, backfiii and compact. The District will provide the material. This contract would be strictly for the installation of the pipe. We are now asking authorization to advertise for, accept and open bids for the installation of eight-inch pipe with a bid opening date of July 30, 2001. RECOMMENDAVON: 1 recommend that the Board authorize staff to advertise for, accept and open bids for the installation of eight-inch pipe for the Joint TDPUD-SWG project at Donner Lake on July 30, 2001. 0 Page 1 DONNER t� -�� TRUCKEE C4 Public Utility District -1d Memorandum ItemAW To: Board of Directors From: Ed Taylor, Water Superintendent Date: 07/13/01 Subject: Consideration of a contract for service with Garcia and Associates. BACKGROUND: The reconstruction of the water system at Donner Lake will affect areas that are wetlands. To properly address all of the issues which will effect the area and the mitigation of these issues requires a complete study to determine the actions required. Garcia and Associates has extensive knowledge of the area and come highly recommended to provide the services needed to complete the Donner Lake project. Staff has reviewed the proposal from Garcia and Associates and recommends that the Board approve the service contract. RECOMMENDATION: I recommend that the Board authorize the General Manager to inter into an agreement with Garcia and Associates of services related to wetlands issues at Donner Lake for an amount not to exceed$92,971. 0 Page 1 TDPUD MEMORANDUM July 13, 2001 TO: Board of Directors FROM: Ed Taylor , Water System Superintendent SUBJECT: DONNER LAKE INTAKE - CHANGE ORDER #1 AGENDA # "E` BACKGROUND: The Board of Directors previously awarded the Contract for construction of the Donner Lake Intake Replacement to F & M Engineering. After the start of the project additional items were identified by staff, which required modification to the project. Item 1: Increase the size of the lake intake screen. Item 2: Increase the number of anchor blocks. Item 3: Additional subsurface and underwater survey work which required additional diving mobilization. RECOMMENDATION: I recommend that the Board authorize Contract Change Order #1 in the amount of $15,391.02. Attachment-Contract Change Order#1 F & MENGINEERING CONTRACTORS, INC. CA. LICENSE NO. 222362 Truckee Donner Public Utility District June 28, 2001 P.O. Box 309 Truckee, Ca 96160 Attn: Ed Taylor Re: Donner Lake Temporary Intake Ed; The following is our Change Order Request No. I for the referenced project. Increase size for stainless steel intake manifold: Increase from 5'-0" overall to 12'-4" overall with support legs. + $ 4,997.55 Increase number of anchor blocks for even distribution: Increase from I 1 anchors to 16 anchors total. 5 Anchors @ $462.84 Ea. _ + $ 2,314.20 Subtotal on material adds $ 7,311.75 15% GC Mark Up $ 1,096.77 Additional mobilization for Underwater Resources + $ 3,240,00 Subsurface and underwater survey + $ 3,410.00 Subtotal on Subcontractor adds $ 6,650.00 5% GC Mark Up $ 332.50 Total This Change Order Request $ 15,391.02 At this time we would also request a 5 day time extension to be added to the overall contract time due to the 4th of July week Lake activities. Please feel free to call with any questions. Sincerely, Clete McConville P.O.BOX 315 FREEDOM,GA.95019 PHONE:(831)728-8757 FAX:(831)728-8784 WWW.FANDM.NET W Ublic Utility District .... Memorandum To: Board of Directors From: Ed Taylor, Water Superintendent Date: 07/13/01 Subject: Authorization to bid for construction of a 600,000-gallon water storage tank at the Donner Lake Southside location. BACKGROUND: The plans and specifications of water storage tank at the Donner Lake Southside location. This project is part of the emergency complaint order for the State Health Department with a requirement for completion this year. We are now asking authorization to advertise for, accept and open bids for the construction of a 600,000-gallon water storage tank at the Donner Lake Southside location. RECOMMENDAVON. I recommend that the Board authorize staff to advertise for, accept and open bids for the construction of a 600,000-gallon water storage tank at the Donner Lake Southside location with a bid opening on August 10, 2001. •Page 1