HomeMy WebLinkAbout8 Pipeine extinction i
TRUCKEE DONNER
Tublic Utility District
Memorandum
To: Board of Directors
From: Ed Taylor, Water Superintendent
Date: 07/13/01
Subject: Authorization to bid for construction of an extension of the Districts Interstate
80 under crossing pipeline extinction.
BACKGROUND:
Caltrans is going to widen Interstate 80 from Donner Pass Road interchange to the to of
Donner summit. The District has a pipeline under crossing of Interstate 80 in the area, which
is to be widened. Caltrans has notified the District staff that the under crossing of the pipeline
must be extended outside of the Interstate 80 right of way. This project also involves the
fiber conduits inside the casing under the roadway.
The plans and specifications for the construction of the extension of the Districts 180 under
crossing are complete. We are now asking authorization to advertise for, accept and open
bids for the construction of the extension of the Districts Interstate 80 under crossing.
RECOMMENDATION:
I recommend that the Board authorize staff to advertise for, accept and open bids for the
construction of the extension of the Districts Interstate 80 under crossing with a bid opening
on August 8, 2001.
0 Page 1