HomeMy WebLinkAbout7 Donner Park Pipeline Crossing TDPUD MEMORANDUM
December 12, 2001
TO: Board of Directors
FROM: Neil Kaufman, Water System Engineer
SUBJECT: DONNER PARK PIPELINE CROSSING MODIFICATION
CHANGE ORDER #1
AGENDA #
BACKGROUND:
The Board of Directors previously awarded the Contract for construction of the Donner
Park Pipeline Crossing Modification project to Contri Construction. The project has been
completed. I am requesting a Change Order to the Contract for issues covered under five
general items.
Item 1 : The contract was originally written based on a 90 percent compaction
requirement for the backfill of the slope excavation. The Encroachment
Permit application filed with Caltrans indicated this 90 percent requirement.
At the pre-construction meeting, the Resident Inspector for Caltrans
indicated a 95 percent compaction requirement. The contractor (and the
District) had originally intended to use screened native material for the
excavation for the backfill. However, 95 percent compaction could not be
achieved using the native material. Therefore, it became necessary to
export and dispose of the excavated material from the site, and to import
new material that would meet the 95 percent compaction requirement.
Contri Construction is due $28,865.64 for this change. This covers dump
fees for the excavated material, purchase of the new material and trucking
involved in transporting the material.
Item 2: The Bid Documents indicated that the total length of water pipe and casing
pipe was 40 feet. Upon completion of the initial excavation, it was
determined that the overall length was 50 feet. Contri Construction is due
$6,677 to cover the purchase of an additional 10 feet of water pipe and
casing pipe.
Item 3: The Bid Documents indicated that the total height of the vertical manhole
was 32 feet. Upon completion of the initial excavation, it was determined
that an additional two feet should be added to the manhole height. Contri
Page 1
Construction is due $329.48 to cover the purchase of an additional 5'd x 2'h
manhole barrel.
Item 4: As noted above, an additional 10 feet of casing and water pipe was installed.
Most of this length was necessary to repair damage caused to the casing
caused by installation of the fiber optic conduits. This additional length
required that the casing and water pipe be extended out into the pavement
section and necessitated the removal and replacement of some pavement.
The original Contract Documents did not call for any pavement disturbance
and Contri Construction owed $588.10 for pavement restoration.
Item 5: The Contract Documents called for protecting the lower part of the restored
slope with a layer of shotcrete, and then reseeding the upper portion of the
slope. The Contractor placed the shotcrete, but was unable to perform the
reseeding prior to the first snowfalls. The District is receiving a$2000 credit
for work not performed, and will hire a separate landscape contractor to
complete the slope restoration in the Spring.
RECOMMENDATION:
I recommend that the Board authorize Contract Change Order #1 , in the amount of a
$34,460.22 payment to Contri Construction.
Attachment-Contract Change Order #1
Page 2
Dec-14-01 01 :02pm From-CONTRI CONSTRUCTION RENO 7757889829 T-368 P.02/02 F-081
I' E . . Change Order
a i
Contract Name: DONNER PARK PIPELINE CROSSING MODIFICATION
Contract Change Order No: 1 Ong. Contract Amt.$ 240,466.00 Days NA
Date: December 12,2001 Prev.Apprd Changes$ 0.00 Days NA
Contractor: Contri Construction This Change$ 34,460.22 Days NA
Revised Contract Art,$ 274,926.22 Days NA
This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct,
furnish equipment and materials, and perform all work as necessary or required to complete the Change Order
Items for a lump sum price agreed upon between the Contractor and District.
Increase in (Decrease) Contract Time
Contract in Contract Extension
Description of Changes Amount Amount $ da s
1) Import\Export of Backfill Material $28,865.64 NA
2) Additional Water Pipe and Casing Pipe $6,677.00 NA
3) Additional Manhole Barrel $329.48 NA
4) Paving .. $588.10 NA
5) Credit for Landscaping $2,000.00 NA
Totals $35,460,22 $2,000,00
Net change in contract amount(increase or decrease) $34.460.22
The amount of the Contract will be increased by the sum of $34,460.P2 and the Contract Time shall not be
extended. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the
contract price specified for each item including any and all supervision costs and other miscellaneous costs relating
to the change in work,and as to the extension of time allowed, if any, for completion of the entire work on account
of said Change Order, The Contractor agrees to furnish all labor and materials and perform all other necessary
work, inclusive of the directly or indirectly related to the approved time extension. required to complete the Change
order items, This document will become a supplement of the contract and all provisions will apply hereto. It Is
understood that the Change Order shall be effective when approved by the District.
Accepted: /ContracWr Date: /� i d
tsignaturs)
Approved: /District Date:
(Signature)
Page 1
�„ I
Public K DONNER
District
EL r
Resolution No. 2001 -
AUTHORIZING THE ACCEPTANCE OF THE DONNER PARK INTERCHANGE PIPELINE EXTENSION
PROJECT AND DIRECTING FILING OF THE NOTICE OF COMPLETION
WHEREAS, the Board of Directors of the Truckee Donner Public Utility District authorized the
Donner State Park Interchange pipeline Extension Project; and
WHEREAS, the contract was awarded to Contri Construction Company, and the contractor entered
into an agreement with the District to perform the work; and
WHEREAS, the District's Water Engineer has recommended that the work be accepted by the
District;
NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows:
1. That the District hereby accepts the Donner State part Interchange Pipeline Extension Project
as complete.
2. That the Clerk of the District be directed to file with the County of Nevada the Notice of
Completion, a copy of which is attached hereto.
3. That 35 days following the filing of the Notice of Completion, the 10% retained from the contractor
payments be released to the contractor if no claims have been made to the District by materiel
suppliers or laborers.
PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the
District on the 1g`h day of December 2001 by the following roll call vote:
AYES:
NOES:
ABSENT:
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
By
ATTEST:
Peter L. Holzmeister, Clerk of the Board
RECORDING REQUESTED BY:
Truckee Donner Public Utility District
WHEN RECORDED, RETURN TO:
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
Post Office Box 309
Truckee, CA 96160
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN:
1. That the name and address of the public entity for whom the improvement project was done, as owner
thereof, is the Truckee Donner Public Utility District, Post Office Box 309, Truckee, CA 96160.
2. That on December 19, 2001, the hereinafter described improvements were accepted as complete
pursuant to a resolution of the Truckee Donner Public Utility District, the awarding authority.
3. That the subject improvements of the Notice are generally described and identified as follows:
Donner State park Interchange Pipeline Extension Project.
4. That the name of the contractor for such project was: Conti Construction Contractor, P.O Box
12100 Reno, Nevada 89610
Dated: TRUCKEE DONNER PUBLIC UTILITY DISTRICT
By
Peter L. Holzmeister, General Manager
STATE OF CALIFORNIA
COUNTY OF NEVADA
On before me, Kathy Moore, personally appeared PETER L. HOLZMEISTER, personally known
to me to be the person whose name is subscribed to the within instrument and acknowledged to me that he executed
the same in his authorized capacity, and that by his signature on the instrument the person or the entity upon behalf of
which the person acted, executed the instrument.
Witness my hand and official seal.
Kathy Moore, Notary