Loading...
HomeMy WebLinkAbout7 Donner Park Pipeline Crossing TDPUD MEMORANDUM December 12, 2001 TO: Board of Directors FROM: Neil Kaufman, Water System Engineer SUBJECT: DONNER PARK PIPELINE CROSSING MODIFICATION CHANGE ORDER #1 AGENDA # BACKGROUND: The Board of Directors previously awarded the Contract for construction of the Donner Park Pipeline Crossing Modification project to Contri Construction. The project has been completed. I am requesting a Change Order to the Contract for issues covered under five general items. Item 1 : The contract was originally written based on a 90 percent compaction requirement for the backfill of the slope excavation. The Encroachment Permit application filed with Caltrans indicated this 90 percent requirement. At the pre-construction meeting, the Resident Inspector for Caltrans indicated a 95 percent compaction requirement. The contractor (and the District) had originally intended to use screened native material for the excavation for the backfill. However, 95 percent compaction could not be achieved using the native material. Therefore, it became necessary to export and dispose of the excavated material from the site, and to import new material that would meet the 95 percent compaction requirement. Contri Construction is due $28,865.64 for this change. This covers dump fees for the excavated material, purchase of the new material and trucking involved in transporting the material. Item 2: The Bid Documents indicated that the total length of water pipe and casing pipe was 40 feet. Upon completion of the initial excavation, it was determined that the overall length was 50 feet. Contri Construction is due $6,677 to cover the purchase of an additional 10 feet of water pipe and casing pipe. Item 3: The Bid Documents indicated that the total height of the vertical manhole was 32 feet. Upon completion of the initial excavation, it was determined that an additional two feet should be added to the manhole height. Contri Page 1 Construction is due $329.48 to cover the purchase of an additional 5'd x 2'h manhole barrel. Item 4: As noted above, an additional 10 feet of casing and water pipe was installed. Most of this length was necessary to repair damage caused to the casing caused by installation of the fiber optic conduits. This additional length required that the casing and water pipe be extended out into the pavement section and necessitated the removal and replacement of some pavement. The original Contract Documents did not call for any pavement disturbance and Contri Construction owed $588.10 for pavement restoration. Item 5: The Contract Documents called for protecting the lower part of the restored slope with a layer of shotcrete, and then reseeding the upper portion of the slope. The Contractor placed the shotcrete, but was unable to perform the reseeding prior to the first snowfalls. The District is receiving a$2000 credit for work not performed, and will hire a separate landscape contractor to complete the slope restoration in the Spring. RECOMMENDATION: I recommend that the Board authorize Contract Change Order #1 , in the amount of a $34,460.22 payment to Contri Construction. Attachment-Contract Change Order #1 Page 2 Dec-14-01 01 :02pm From-CONTRI CONSTRUCTION RENO 7757889829 T-368 P.02/02 F-081 I' E . . Change Order a i Contract Name: DONNER PARK PIPELINE CROSSING MODIFICATION Contract Change Order No: 1 Ong. Contract Amt.$ 240,466.00 Days NA Date: December 12,2001 Prev.Apprd Changes$ 0.00 Days NA Contractor: Contri Construction This Change$ 34,460.22 Days NA Revised Contract Art,$ 274,926.22 Days NA This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items for a lump sum price agreed upon between the Contractor and District. Increase in (Decrease) Contract Time Contract in Contract Extension Description of Changes Amount Amount $ da s 1) Import\Export of Backfill Material $28,865.64 NA 2) Additional Water Pipe and Casing Pipe $6,677.00 NA 3) Additional Manhole Barrel $329.48 NA 4) Paving .. $588.10 NA 5) Credit for Landscaping $2,000.00 NA Totals $35,460,22 $2,000,00 Net change in contract amount(increase or decrease) $34.460.22 The amount of the Contract will be increased by the sum of $34,460.P2 and the Contract Time shall not be extended. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work,and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order, The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of the directly or indirectly related to the approved time extension. required to complete the Change order items, This document will become a supplement of the contract and all provisions will apply hereto. It Is understood that the Change Order shall be effective when approved by the District. Accepted: /ContracWr Date: /� i d tsignaturs) Approved: /District Date: (Signature) Page 1 �„ I Public K DONNER District EL r Resolution No. 2001 - AUTHORIZING THE ACCEPTANCE OF THE DONNER PARK INTERCHANGE PIPELINE EXTENSION PROJECT AND DIRECTING FILING OF THE NOTICE OF COMPLETION WHEREAS, the Board of Directors of the Truckee Donner Public Utility District authorized the Donner State Park Interchange pipeline Extension Project; and WHEREAS, the contract was awarded to Contri Construction Company, and the contractor entered into an agreement with the District to perform the work; and WHEREAS, the District's Water Engineer has recommended that the work be accepted by the District; NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows: 1. That the District hereby accepts the Donner State part Interchange Pipeline Extension Project as complete. 2. That the Clerk of the District be directed to file with the County of Nevada the Notice of Completion, a copy of which is attached hereto. 3. That 35 days following the filing of the Notice of Completion, the 10% retained from the contractor payments be released to the contractor if no claims have been made to the District by materiel suppliers or laborers. PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the District on the 1g`h day of December 2001 by the following roll call vote: AYES: NOES: ABSENT: TRUCKEE DONNER PUBLIC UTILITY DISTRICT By ATTEST: Peter L. Holzmeister, Clerk of the Board RECORDING REQUESTED BY: Truckee Donner Public Utility District WHEN RECORDED, RETURN TO: TRUCKEE DONNER PUBLIC UTILITY DISTRICT Post Office Box 309 Truckee, CA 96160 NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN: 1. That the name and address of the public entity for whom the improvement project was done, as owner thereof, is the Truckee Donner Public Utility District, Post Office Box 309, Truckee, CA 96160. 2. That on December 19, 2001, the hereinafter described improvements were accepted as complete pursuant to a resolution of the Truckee Donner Public Utility District, the awarding authority. 3. That the subject improvements of the Notice are generally described and identified as follows: Donner State park Interchange Pipeline Extension Project. 4. That the name of the contractor for such project was: Conti Construction Contractor, P.O Box 12100 Reno, Nevada 89610 Dated: TRUCKEE DONNER PUBLIC UTILITY DISTRICT By Peter L. Holzmeister, General Manager STATE OF CALIFORNIA COUNTY OF NEVADA On before me, Kathy Moore, personally appeared PETER L. HOLZMEISTER, personally known to me to be the person whose name is subscribed to the within instrument and acknowledged to me that he executed the same in his authorized capacity, and that by his signature on the instrument the person or the entity upon behalf of which the person acted, executed the instrument. Witness my hand and official seal. Kathy Moore, Notary