Loading...
HomeMy WebLinkAbout#8 6170 Tank Completion AGENDA ITEM #8 Public Utility District m MEETING DATE: September 4, 2024 TO: Board of Directors FROM: Neil Kaufman, System Engineer Chad Reed, Water Utility Director SUBJECT: Consideration of Adopting Resolution 2024-15 Accepting the 6170 #2 Tank Construction as Complete and Authorizing the Filing of the Notice of Completion. APPROVED BY: Brian C. Wright, General Manager RECOMMENDATION: Adopt Resolution 2024-15 accepting the 6170 Tank #2 project as complete and authorize the filing of the Notice of Completion. BACKGROUND: The Bridge Street 6170 Tank #1 is a 1.5 million gallon, welded steel tank located on District-owned property. The tank site is north of Interstate 80 and east of Bridge Street. The access driveway to the site is located on Pioneer Trail, adjacent to the TNT Materials concrete batch plant. Tank #1 was constructed in 2002. The site design for the project envisioned the construction of a second storage tank at the site. The site grading work in 2002 included sufficient space for this second tank, and the site piping included valves to serve as the points of connection for the second tank. The project description included in the CEQA review for the project also included the second tank. At the December 7, 2022, Board meeting, a contract was awarded to Sauers Engineering to develop the design and prepare contract documents for the second storage tank. The Sauers contract also included bid phase and construction phase services. The contract documents were completed, and advertising for bids began in mid- February of 2023. The bid opening was held on March 2, 2023, and a construction contract was awarded to Crosno Construction on March 15, 2023. The bid price for Crosno was $2,686,720. The Board also established a change order allowance of $268,680, for a total authorization not to exceed $2,955,400. ANALYSIS AND BODY: Page 1 of 4 Page 13 of 72 Crosno completed all the site piping, paving, tank foundation and steel construction work in October 2023. After completion of the steel construction, the final steps would be the application of the interior and exterior coatings, followed by disinfection of the tank. Application of the coatings is sensitive to both temperature and humidity levels, and takes about 6-8 weeks to complete. Given the time frame (October) and the onset of winter conditions, it was decided to postpone the application of the coatings to the summer of 2024. Crosno remobilized to the site at the end of May 2024 and began the coating work. The project is now complete and should be accepted by the District. Attached is a draft resolution (Attachment 1) accepting the project and directing that a Notice of Completion be filed. There were six change order requests during the project: 1. As noted above, the grading work associated with the construction of Tank #1 in 2002 included rough grading of the location for Tank #2. Over the past 20 years, the Water Department has used this area for storage of various soil materials, piping and equipment. This has resulted in changes to the surface elevation. In addition, there has been sloughing of soil material off the cut slope on the north side of the tank pad. The actual pre-construction site elevation was higher than anticipated by up to two feet in some locations. Removal of this additional material costs $44,520.00. 2. The project design relied on the original site survey from 2002. Using this survey, a 117-foot diameter tank with a volume of 2.5 million gallons was planned. After removal of the excess material noted above, the footprint of the tank was laid out. It was found that removal of a large rock outcropping on the west edge of the tank pad would be required. District field personnel also expressed concern about whether there was sufficient space between the two tanks for snow removal operations. After considering these two issues, it was decided to downsize the tank to a diameter of 110 feet with a volume of 2.25 million gallons. This size would allow the access road around the west side of the tank and provide additional clearance between the two tanks. This downsizing results in a credit of $54,888.11 for the District. 3. The design drawings for the tank called for installation of an 8" overflow flow. However, revised calculations during the shop drawing process determined that this pipe should be 16" in diameter. There is a cost of $52,925.25 associated with upsizing this piping. 4. The majority of the bid schedule included lump sum/fixed price items. Payment for asphalt paving work and rock excavation was based on the unit price bid. The original bid included 6,700 square feet of new paving. This quantity did not include the removal and replacement of existing pavement required to run communication and electrical conduits to a panel located southeast of Tank #1. This required an additional 1,500 square feet of paving at a cost of $22,775. 5. The original bid included 10 hours of rock excavation. However, an additional 58 hours of rock excavation was needed to accomplish the project at a cost of $61,074. Page 2 of 4 Page 14 of 72 6. After completion of the final grading and prior to paving, a field inspection was performed to review the site drainage. It was determined that some modifications to the site grading and the transition from the access driveway to the tank pad were needed. After discussion of these issues, a price of $39,328.28 was agreed upon. GOALS AND OBJECTIVES: District Code 1 .05.020 Objectives: 1. Responsibly serve the public. 3. Provide reliable and high quality water supply and distribution system to meet current and future needs. 5. Manage the District in an environmentally sound manner. 6. Manage the District in an effective, efficient and fiscally responsible manner. District Code 1 .05.030 Goals: 1. Manage for Financial Stability and Resiliency 2. Environmental Stewardship: Create a sustainable, resilient environment for all our communities. FISCAL IMPACT: The original bid price was $2,686,720.00. The Board also established a change order allowance of $268,680, for a total authorization not to exceed $2,955,400. Once adjustments are made for the items described above, the final contract price is $2,852,454.82. Item Amount Original bid price $2,686,720.00 Tank pad material removal $44,520.00 Downsizing of tank to 110' diameter ($54,888.11) Overflow pipe upsizing $52,925.25 Reconciliation of bid vs. actual quantities $83,849.00 Additional site grading $39,328.28 Total $2,852,454.42 The funding source for this project is water utility 2022 debt project proceeds (68%) and facility fee funds (32%). In addition to the amount paid to Crosno Construction, the District has incurred additional outside expenses for construction inspection and geotechnical testing. ATTACHMENTS: 1. r2024-15- Notice of Completion_617013 tank 2 Page 3 of 4 Page 15 of 72 Public Resolution No. 2024-15 AUTHORIZING THE ACCEPTANCE OF THE 6170 TANK #2 PROJECT AND DIRECTING FILING OF THE NOTICE OF COMPLETION WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the determination to undertake the 6170 Tank#2 project; and WHEREAS, Crosno Construction was selected by the District to perform the work; and WHEREAS, Crosno Construction has completed all of the Work included in the Project; and NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows: 1. That the District hereby accepts the 6170 Tank#2 project as complete. 2. That the Clerk of the District be directed to file with the County of Nevada the Notice of Completion, a copy of which is attached hereto. 3. That 35 days following the filing of the Notice of Completion, the monies retained from the contractor payments be released to the contractor if no claims have been made to the District by material suppliers or laborers. PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the District on the 4th day of September 2024, by the following roll call vote: AYES: NOES: ABSTAIN: ABSENT: TRUCKEE DONNER PUBLIC UTILITY DISTRICT By Jeff Bender, President of the Board ATTEST: Brian Wright, General Manager Page 17 of 72 RECORDING REQUESTED BY: Truckee Donner Public Utility District WHEN RECORDED, RETURN TO: TRUCKEE DONNER PUBLIC UTILITY DISTRICT Brian Wright, General Manager 11570 Donner Pass Road Truckee, CA 96161-4947 THE UNDERSIGNED DECLARES DOCUMENTARY TRANSFER TAX- NONE NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN: 1. That the name and address of the public entity for whom the improvement project was done, as owner thereof, is the Truckee Donner Public Utility District, 11570 Donner Pass Road, Truckee, CA 96161. 2. Nature of interest or estate of owner: beneficial interest of a public utility of electric and water facilities. 3. That on September 4, 2024 the hereinafter described improvements were accepted as complete pursuant to Resolution 2024-15 of the Truckee Donner Public Utility District, the awarding authority. 4. That the subject improvements of the notice are generally described and identified as follows: 6170 Tank#2 project. 5. That the name and address of the contractor for such project was: Crosno Construction, 819 Sheridan Road, Arroyo Grande, California 93420. 1 certify under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Dated: TRUCKEE DONNER PUBLIC UTILITY DISTRICT By Brian Wright, General Manager MAIL TAX STATEMENTS TO: SAME AS ABOVE Legal References: CC-3093,CCP-2003 (oath), 2015.5 (unsworn statement) Page 18 of 72