To: Board of Directors
From: Neil Kaufman, Water Systems Engineer
Date: May 20, 2002
Subject: Surveying for Glenshire Drive Pipeline West of the Glenshire Drive
Bridge
BACKGROUND:
As a result of the acquisition of Glenshire Mutual water system, it is necessary to
construct a pipeline to provide additional water supply to the Glenshire area. For
design purposes, the pipeline has been broken into three parts.
GLENSHIRE DRIVE WELL TO THE GLENSHIRE DRIVE BRIDGE
As discussed at the Board meeting on May 15, a favored alignment has been
identified. I had originally contacted Mike Sullivan of Sierra Nevada Civil
Engineers (SNCE) to perform the necessary survey work for the design. SNCE
performed the surveying for development of the tentative and final maps in this
area. Upon further discussion with Mr. Sullivan, it was determined that he is too
busy with other work and could not commit to performing the necessary work in a
time frame to meet the District's needs.
I then contacted Andregg Inc. and requested a proposal to expand the survey
work currently being performed along Glenshire Drive to cover the entire pipeline
alignment. Andregg has indicated that the work can be performed in a timely
manner with delivery of the mapping expected towards the end of June into early
July.
GLENSHIRE BRIDGE-TRUCKEE RIVER CROSSING
Dokken Engineering is currently working on the design of the pipeline across the
bridge under a contract previously approved by the Board.
GLENSHIRE DRIVE BRIDGE TO THE GLENSHIRE SUBDIVISION
As approved at the Board Meeting on May 1, Andregg is currently surveying this
portion of the alignment. I am anticipating delivery of the mapping in the middle
of June.
PERMITTING AND ENVIRONMENTAL REVIEW
Garcia and Associates has begun the environmental review for the pipeline. A
meeting is scheduled with Lahontan RWQCB for this week to perform a field walk
of the alignment. I am anticipating that the draft Initial Study will be presented to
the Board at the meeting on June 5.
PIPELINE DESIGN
I have begun some preliminary design work and specification writing for the
pipeline. I am awaiting the final survey work before I can proceed much further.
RECOMMENDATION:
The District enter into a contract with Andregg Inc. in an amount not to exceed
$25,000 for the survey work described in the attached proposal. The $25,000 is
based on the proposed amount of$22,780 plus a 10% contingency.
MAY-21-2002 18:02 FROM RNDREGG INC. TO 5871189 P.01i01
ANDIIEGG INC.
MEN M
May 21, 2002
Truckee Donner Public Utilities District
P_O. Box 309 Phone 530-582-3969
Truckee, CA 96160 Fax 530-587-1189
Attention: Neil Kaufman
Re: West Glenshire Transmission Pipeline
Truckee,Nevada County, CA
As requested herewith is our proposal for surveying and mapping services for the proposed
pipeline route indicated in your RFP of May 15, 2002.Mapping of the route shall be a strip
approximately 6000 feet long and 200 feet wide.The horizontal datum shall be NAD83 (1991.35)
California State Plane Coordinate System,Zone 2 and the vertical datum shall be NGVD29.
Our proposed scope of work and estimate of fees are as follows:
Tasks
-Set&survey aerial targets, obtain aerial photography and provide conventional
photogrammetric mapping at a scale of 1"=100' with 2 ft contours.
-Locate existing edge of pavement along Glen shire Drive portion of alignment.
-Locate all trees larger than 6"DBH within 50 feet of the proposed centerline alignment.
- Locate large rock outcroppings within 50 feet of the proposed centerline alignment
-Locate surface evidence of utilities along the proposed alignment.
-Set stakes at 200 foot intervals along property/centerline of proposed alignment.
-Locate edges of the Environmentally Sensitive Area(determined by TDPUD representative)
within 50 feet of the centerline alignment
-Prepare one legal description and exhibit plat for a Permanent Pipeline Easement crossing Lot
26 of the Boca Sierra Estates Subdivision and one legal description and exhibit plat for a
Temporary Construction Easement for the pipeline crossing Lot 26.
Total Fees S22,780.00
Mapping deliverables shall be in hardcopy and digital format in AutoCAD standard drawing files in
model space rather than paper space,with no XREF.Digital Terrain.Model,(DTM)or Triangulated
Irregular Network TIN surfaces,fault,break and boundary lines shall NOT be provided or
generated Unless otherwise provided for in tabular and digital format (as an AntoCAD template
file),layering,blocks,point codes, line types,text fonts and other drawing standards shall follow
the AN"DREGG, INC, standard AutoCAD format which includes separate layers for points,
contours,boundaries, text, sewer, storm drain, and other utilities and improvements.
The above estimated fees shall not be exceeded without prior authorization from client and shall
remain valid for 30 days.
Thank you for this opportunity.If you have any questions or need additional information, please call.
Sincerely,
ANDREGG,Inc.
Mark J. Bardakiian, PLS
QDC\sys\PR0P0SA1AM]HIW.ulcnslae Transmission Line.doc