HomeMy WebLinkAbout#10 On Call Construction RK AGENDA ITEM #10
Public Utility District m
MEETING DATE: November 6, 2024
TO: Board of Directors
FROM: Jared Carpenter, Electric Utility Director
Cody Laplaca, Electric Operations Manager
SUBJECT: Consideration of Approving an Amendment to the 2024 On Call
Construction Services Contract with RK Contractors Inc.
APPROVED BY:
Brian C. Wright, General Manager
RECOMMENDATION:
Authorize the General Manager to execute a contract amendment in the amount of
$100, 000 with RK Contractors INC., for additional On-all Construction Services with a
total not to exceed contract amount of$300,000.
BACKGROUND:
At the December 6th, 2023 Board meeting, the Board approved the Consideration of
FY24 Annual Contract and Procurements, which reccommended authorizing the routine
annual procurements totaling $11,857,800 from the vendors listed, and authorize the
General Manager to execute the required documents necessary to procure the
products and services. One of these services, the On-call contract, is used by the
Electric and Water Departments occasionally to assist with infrastructure maintenance,
construction, snow removal, hazardous waste remediation and other miscellaneous
services. However, the need for these services cannot be reliably predicted. These
services may be required for several reasons, including but not limited to; extreme
snow conditions, availability of District resources, storm damage, failed electric
distribution facilities, and other circumstances that may arise. The purpose of this
agreement is to establish payment and other provisions between the District and the
Contractor necessary to perform these types of work. The scope of services resulting
from any and all circumstances will be determined by District personnel on a case-by-
case basis and communicated to the Contractor verbally or in writing. The work of this
Contract comprises of construction services for calendar year 2024, with the option to
extend the contract for four additional years (Option years 2025-2028).
ANALYSIS AND BODY:
The estimates that were included in the December 2023 Board of Directors meeting
may not be adequate due to a productive and successful construction year, resulting in
various projects completed, including extensive wildfire mitigating system hardening,
increased utility pole replacements, increase in utility undergrounding projects,
Page 1 of 2
Page 19 of 153
transformer installations for new developments, and much more. To deliver this work,
staff successfully created new methods to increase the District's efficiency resulting in
more projects being completed, for less cost than expected per project. To date, the on-
call contract has spent $146,460.87 of the $200,000 budget limit. While staff does not
anticipate exceeding the approved contract amount, YTD expenses are close enough
that an amendment to the contract would ensure sufficient funds are available in the
event additional contracted services become necessary before the end of the calendar
year (winter storms, emergency repairs, additional capital and maintenance work).
Therefore, staff is requesting an amendment to the 2024 contract, increasing the
authorized contract amount by $100,000, for a new not to exceed amount of $300,000.
GOALS AND OBJECTIVES:
District Code 1 .05.020 Objectives:
1. Responsibly serve the public.
3. Provide reliable and high quality water supply and distribution system to meet
current and future needs.
4. Provide reliable and high quality electric supply and distribution system to meet
current and future needs.
6. Manage the District in an effective, efficient and fiscally responsible manner.
District Code 1 .05.030 Goals:
1. Manage for Financial Stability and Resiliency
4. Take the best of private sector thinking to modernize the utility and add value to our
communities.
FISCAL IMPACT:
Approximately 90% of the On-call services are applied to work orders for either
previously approved capital projects, or developer work. Developer work is paid back to
TDPUD through other standard fees. Around 10% of the On-call services are for
materials under G.L. code 1.6.583.00.670. The request is to increase the limit from
$200,000 to $300,000 for 2024, as a contingency for projects and potential on-call
services. Staff does not forecast the increase to cause an overage in electric utility
operating expenses nor capital expenditures, as approved.
ATTACHMENTS:
None
Page 2 of 2
Page 20 of 153