Memorandum
To: Board of Directors
From: Neil Kaufman, Water Systems Engineer
Date: May 10, 2002
Subject: PROPOSAL TO PERFORM SURVEYING ALONG DONNER PASS ROAD
BACKGROUND:
As part of the ongoing reconstruction of the Donner Lake Water System, I am anticipating
construction of a 12-inch pipeline along Donner Pass Road from the Tahoe Donner
Association's beach house to Eddy Avenue.
At the TD Beach House, this 12-inch pipeline would be connected into the existing 18-inch
steel pipeline in Donner Pass Road. The 18-inch pipe would be inspected and rehabilitated
(likely either cleaned and concrete-lined, or slip-lined) as necessary to place it into service.
This combination 12/18-inch pipeline would serve as the primary feed for groundwater from
the Gateway area into Donner Lake.
There are a number of existing utilities in Donner Pass Road through this area including:
• Two potable water lines
• One gravity sanitary sewer
• One sanitary sewer force main
• Underground telephone ducts (Pacific Bell)
• Underground power, telephone and cable TV drops to individual structures
• Underground fiber optic conduits (Williams)
• Natural gas piping
In order to properly design, permit and construct the pipeline, I believe it is necessary to
have this portion of Donner Pass Road completely surveyed.
I have asked Sagebrush Surveying to provide a proposal to perform this survey work.
Sagebrush has done survey work at a number of locations in the Donner Lake area and
likely has best established control network in this area.
RECOMMENDATION:
Accept the Proposal from Sagebrush Surveying to perform survey work along Donner Pass
Road in the amount of$25,760.
Saeusi
PLANNING • SURV11MG • CONSULTING
P.O. Box 516 Truck• ei,-, "160 • (530) 587-6902
Date: May,4, 2002
TRUCKEE DONNER P.U.D.
Attn: Neil Koffman
P.O. Box 309
Truckee, Ca. 96160
Re: Topographic Survey-Donner Pass Road
Eddy Avenue east to Tahoe Donner Assoc. Beach
Town of Truckee, Nevada Co., Calif
Dear Neil,
Thank you for the opportunity to submit this proposal and estimate for the above referenced
project. Our cost for supplying the necessary services to do a strip topography from the centerline
of Donner Pass Road to the middle of all buildings along its frontage is as follows:
Scope of Work:
Element #1: Records & Document Research
Project Coordination
Principle Surveyor—24 hrs @ $85.00 = $2040.00
Element 42: Control Traverse & Monument Search
2 Man Survey Crew - 48 hrs @ $135.00 = $6480.00
Element 93: Strip Topography
2 Man Survey Crew - 64 hrs @ $135.00 = $8640.00
Element #4 Calculations&Field Data Reduction
Right of Way& Abutting Property Line Resolution
Principle Surveyor - 40 hrs @ $85.00 = $3400.00
Element #5 Prepare Strip Topo Map
Cad Drafting— 80 hrs @ $65.00 = $5200.00
TOTAL ESTIMATE: $25,760.00
1
T.D.P.U.D.- Donner Pass Road Strip Topography Proposal Continued:
Note: Surveying&Drafting Services To Include The Following:
a. Tie in Right of Way&Boundary Monuments (sufficient enough to be able to determine
abutting ownerships within V horizontal accuracy.)
b. Elevation Datum—NGVD 29
c. Contours @ 1' Interval
d. Trees 6"Dia.>
e. Rock Outcroppings
f. Property Improvements (Buildings, Driveways, Fences, Retaining Walls, Landscaping
and other visible improvements.)
g. Highway Drainage (DI's, Culverts&Ditches)
h. Utilities (all visible utility mainline & services)
Sagebrush will supply electronic file -AutoCAD LDD3.
T.DP.U.D will supply Underground Service Alert marking& coordination.
Any additional work over and above the scope of this proposal will be supplied on a time and
material bases (See attached fee schedule).
If this proposal meets with your approval, please sign and return the enclosed Work Order
Authorization.
Should you have any questions or desire any additional information please feel free
to call or write.
Thank you sincerely,
Charles R. Sage Jr. P.L.S.
2
Sa r uSH
PLANNING • SURVMING • CONSULTING
P.O. Box 516 • Truckee;C.AL 46160 • (530) 587-6902
WORK ORDERAUTHORIZATIOPI
Date:Ma 4. 2002 Sob#
FOR THE ACCOUNT OF :
Name of Client:. Truckee Donner P.U.D.
CIO : Neil Koffman-'
Address:P O_Box 309
City and State: Trochee_Ca. 96160 Telephone:
DESCRIPTION OF WORK ORDERED: Strip Topography-Donner Pass Road.from Eddv P ve. east
to the Tahoe Donner Assoc Beach {See attached pzo�osal&estimate)
.LEGAL DESCRIPTION:Donner Pass Rd Portion Sec 13 T17N R15E&Sec.18 T17N R16E MDM
GENERAL LOCATION OF PROPERTY: Town of Truckee. Calif. (Donner Lake)
Order Received By C.S. Personal Call X_Telephone_Letter_
Approximate date of completion ASAP
AGREEMENT
I.It is agreed that the above work is to be performed for my/our account and that I/we will be billed on a
time and material basis at the prevailing rates as said work progresses,unless exception is shown in
writing on the following lines. SEE ATTACHED PROPOSAL&ESTIMATE
2. Uwe agree to pay the ABOVE NAMED FIRM, upon presentation of billings,and to pay interest at
1.5%per month on billings not paid when due.
3. I/we agree that Uwe shall be responsible for payment of all costs and expenses incurred by ABOVE
NAMED FIRM, including such monies as they may at their option advance for my/our account for
fees, and other incidental expenses,up to date of completion of the entire work of which this order
may be a part,or until such time as Uwe give you written notice requesting you to cease further work
in the event of such written notice to you,all sums due you shall be immediately payable.
4. In the event you should file suit to enforce payment hereof, I/we do promise and agree to pay
reasonable attorney's fees and court costs.
5. In the event you should assign my account to collection for amount due,Uwe do promise and agree
to pay reasonable costs of collection.
6.All fees stated herein do not include reproduction costs and fees required by governmental agencies.
Title companies etc.
7.All accounts to be paid current prior to release/submittal/or recording of documents.
ACCEPTED AND AGREED BY:
By: Date: By:
Sag uSill
PLANNING • SURVnING • CONSULTING
P.O. Box 516 • Truckees +aAh 34160 • (530) 587-6902
SAGEBRUSH 2O02 FEE SCHEDULE
Services provided by SAGEBRUSH staff are billed on.a hourly basis unless otherwise
specified in the contract. Current hourly rat)69sre as follows.
OFFICE PERSONNEL
Surveyor (Registered L.S $85.00
Suveyor(L.S.LT.) $70.00
Chief of Surveyors $60.00
Survey Technician $50.00
Cadd Draftsman $65.00
Clerical $45r00
GPS SURVEYS
GPS Crew Chief $75.00
Equipment/2 GPS Receivers $100.00
FIELD SERVICES
3-Man Survey Crew $185.00
2-Man Survey Crew $135.00
CONSULTING
Expert Witness (Registered L.S. ) $200.00
Reimbursable Charges:
All reimbursable items will be invoiced at the amount billed to SAGEBRUSH or at
SAGEBRUSH in-house services rates, as applicable, plus ten (10) percent )
Prints, Photos, Reproduction Actual Cost
Transportation .36/mile
Meals, Per Diem $35/Day/Person
Lodging Actual Cost
Sub-Consultant Actual Cost
The above rates are subject to revision annually.