HomeMy WebLinkAbout#12 Approve Tahoe Donner Ski Lodge Project AGENDA ITEM #12
Public Utility District m
MEETING DATE: May 1, 2024
TO: Board of Directors
FROM: Neil Kaufman, System Engineer
SUBJECT: Consider Approval of the Development Agreement for the Tahoe
Donner Downhill Ski Lodge Project
APPROVED BY:
Brian C. Wright, General Manager
RECOMMENDATION:
Approve the development agreement between the District and the Tahoe Donner
Association for the Tahoe Donner Downhill Ski Lodge Project.
BACKGROUND:
The Tahoe Donner Association (TDA) operates a downhill ski area located on Slalom
Way within the Tahoe Donner Subdivision. The District provides potable water and
electrical service to the base lodge in the ski area. The existing base lodge structure
was constructed in the early 1970s and is approaching the end of its useful life.
ANALYSIS AND BODY:
TDA is undertaking a project to replace the existing base lodge structure with a new
structure. As part of this project, both the water and electrical utility service entrances
to the structure will be relocated. There will also be grading modifications and
replacement of the pavement in the vicinity of the structure. The attached drawings
show the planned scope of work.
The District owns and maintains the water distribution system throughout the Ski Bowl
Condominiums complex, and has existing pipes in close proximity to the project
site. This distribution system piping is in poor condition and requires repeated
repairs. In August 2021, the Board of Directors approved a contract with Sage Land
Surveying to perform a utility survey within the complex, so that the design for a
pipeline replacement project could be developed. This design work is about 75%
complete.
The Water Department had originally planned to undertake this pipeline replacement
project in the summer of 2024. However, the project was delayed to avoid conflict with
the TDA base lodge replacement project. This delay also allowed the replacement of
water pipes on Northwoods Boulevard in advance of the Town of Truckee's paving
overlay project. It is planned to proceed with the pipeline replacement project when
Page 1 of 2
Page 30 of 215
construction of the new base lodge has been completed.
The replacement water pipelines will be located within areas that will be repaved as
part of the TDA project. District staff and TDA representatives have been discussing
the planned work for both projects. To avoid disturbing the newly placed paving work, it
was agreed to have the TDA contractor install about 455 feet of water pipeline in the
areas that will be paved. The TDA contractor has provided a price of $234/ft for the 8-
inch main line pipe. This can be compared to the price of about $245/ft given in the
recently awarded District Pipeline Replacement— 2024 project. The total cost
proposal from the contractor awarded the TDA project for the replacement of the
District-owned water pipeline is $192,520.76. This total includes associated
appurtenances, such as isolation valves, one fire hydrant and two water services within
the project area, along with a proportionate share of common costs, such as
mobilization, the best management practices (BMP) implementation and insurance. It
is recommended that a ten percent change order allowance be established for this
work, which would correspond to a total expenditure of about $211,800.
Attached is a copy of the draft Development Agreement between the District and the
Tahoe Donner Association. This agreement uses the District's standard development
template with one modification. This modification is the insertion of Article 29, which
discusses the reimbursement from the District to TDA for installation of the water
pipeline.
GOALS AND OBJECTIVES:
District Code 1 .05.020 Objectives:
1. Responsibly serve the public.
3. Provide reliable and high quality water supply and distribution system to meet
current and future needs.
6. Manage the District in an effective, efficient and fiscally responsible manner.
District Code 1 .05.030 Goals:
1. Manage for Financial Stability and Resiliency
3. Engage with our customers and communities in a welcoming and transparent way to
identify opportunities.
FISCAL IMPACT:
This item is included in the water utility's 10-year capital improvement plan, within the
$23AM, 10yr pipeline replacement component. The water utility has sufficient funds
for this capital expenditure in 2024.
ATTACHMENTS:
1. Board Figure 1
2. Board Figure 2
3. Board Figure 3
4. Board Figure 4
5. Electric Water Development Agreement Tahoe Donner Downhill Ski Lodge
Page 2 of 2
Page 31 of 215
Pb :,jajjjjjjjhw..jv
Xv
;,�;�,. ' .•�•` -�?� •.��` � : �� ..` _ •~ mil.-• :`�' -y �j Q..
SLALOM WAY
,a s SKI L ti u`;_,, _ .�•• t ti' !; •: '4
<; • „ '!°�,, ``—Y PARKING
•� � � �.• :sue ..,. • '. :�..
vat
71
Zq
iO�.Aka�.
If
21
• �` ,.
'1
1 y♦
N
OVERALL SITE: AERIAL VIEW G
fAHOE DONNER DOWNHILL SKI RESORT 4 bull stockwell alley i
J U LY 25, 2022
ARCHITECTURE+ INT5�lOF
�0F215
* SITE PLAN KEYNOTES
APN Tf (P)GENERATOR
046-250-012
2. (P)RETAINING WALL(5'MAX HEIGHT,SEE GRADING PLAN)
26' WITH RAILING,SEE DETAIL BELOW.
3. (P)TRENCH DRAIN
(E)GARAGE E)DUMPSTERS
4. (P)INFILTRATION CHAMBER
5. (E)PLANTER
APN 6. (P
)CURB
046-570-023 6
_ 7. (P)TRASH ENCLOSURE,SEE ARCHITECTURAL PLAN
_ 8. (P)STAIRWAY LEVEL 2 TO LEVEL 3
APN 3
9. FIRE TRUCK TURNING MOVEMENT
046-250-013 —
g 10. ADA PARKING
(E)LIFT / — ; SLALOM WAY a 11. PENDING FUTURE LLA APPLICATION APPROVAL.
MAI NT- I (E)PARCELS O46-250-005,046-250-007,AND 046-250-009 TO BE
ENANCE ��d / R MERGED
0 '2
"6' 046 250-013
6 VAR3ES,REFER TO IAVOVi PLANS.
6 I 3 I 1'X?PAINTED STEEL
17' I CHANNEL
6 20 6 20 6 r EQ. R"TY4'TYP, EQ.
4 }"X}'PAINTED STEEL
PICKET,4"0.C.
:�,• :• 14' ` 6 �R / 6 1"X PAINTPO STEELEL.
20•
U-GHHNN
n i •• \ \ O / 2 FITPAVERSHANDTIGHT
O O• AROUND EDGE OE FENCE
• \ QO°` / _ POST
71 (P) II u
DRIVEWAY/. .u n a `.'• I _ Lr
+,I• \ / / - i1. I'I _ }FENCE POST FOOTING,
E 14"SONOTU6E,FILL
WITH 4ONGRETE,
• .•Y " 3300 P51
A
ELEVATION'
(P)DECK: (E)BUILDING
RETAINING WALL w/ RAILING DETAIL
sp RT32.o•
APN
\ 046-250-009
,\,,\• (P)BUILDING
(E)SKI LIFT \: 6
ir
\ •�• R700.0'
' k k
APN
046-250-013
APN o
046-250-013
11 23
kk _
k
11
GRAPHIC SCALE
40 0 20 40
C4 CIVIL SITE PLAN
1 INCH = 40 FEET
IAHOE DONNER DOWNHILL SKI RESORT 28 AUERBACH ENGINEERING bull stuc;KWell alien
JULY 25, 2022 CORP ARCHITECTURE+PLANN%+INT`5�l F 215
or_-
gift
r J
ATAHOLDONNEP, - -
AII_ �► AG r
I 4Ci
A,
*A I s
EXTERIOR VIEW/ELEVATION - STREET (WEST) SIDE
TAHOE DONNER DOWNHILL SKI RESOH 1 12 bull stockWell allen
J U LY 25, 2022
ARCHITECTURE+RLANN%geT �l 0 15
AUERBACH
ENGINEERING
UTILITY KEYNOTES CORP
CIVIL ENGINEERING*LAND SURVEYING-ENVIRONMENTAL PLANNING
REUSE OF DOCUMENTS
1. INSTALL MANHOLE OVER (E) SEWER & CONNECT TO NEW 1-5 THIS DOCUMENT&THE I DEAS&DESIGN INCORPORATED HEREIN,AS AN
ss E D U M PSTER D3 INSTRUMENT OF PROFESSIONAL SERVICE,IS THE PROPERTY OF AEC&IS
o (E) 6" SS LATERAL, SEE SEWER PLAN AND PROFILE. NOT TO BE USED,IN WHOLE OR IN PART,FOR ANY OTHER PROJECT
WITHOUT THE WRITTEN AUTHORIZATION OF AEC.
(E)
(E) CONDOMINIUMS BUILDING 2. INSTALL SEWER SERVICE TO BUILDING, SEE SEWER PLAN
AND PROFILE. oQROFESS/pNq�
(E) I 3. CONSTRUCT SEWER CLEANOUT, SEE SEWER PLAN AND
D3. v
GARAGE ss PROFILE. *� ENo. C34303
xp. 9/0/23
----------------------- \ 4. CONNECTION TO (E)WATER PER TCPUD STANDARDS.
- sT CIV\\
5. INSTALL 2.5" DOMESTIC WATER AND 8" FIRE SERVICE TO 1-5 gTFpFCAUF��
�''------------- \I \
28 1 16 BUILDING.
- ' 6. CONNECT TO (E) ELECTRIC PER TCPUD STANDARDS.
g
G� 13 \� W W 15
E m 7. CONNECT TO (E) COMMUNICATIONS, SEE MECHANICAL
! 10 PLANS.
SS NN
8. JOINT TRENCH ELECTRIC AND COMMUNICATIONS. D3.7
W= -P(E) LIFT �
® m - � ��- W� � 3Jn nl 3J � SLALOM WAY g• ELECTRIC PANELS, SEE ELECTRICAL PLANS.
MAINTENANCE ;"
/ BUILDING /
10. RE-ROUTE ELECTRIC SERVICE TO SKI LIFT 300 MONTGOMERY STREET, SUITE 600
co
/ 6 ... ......... N roCO AVOID DRIPLINE OF 34" PINE TREE. COORDINATE AND SAN FRANCISCO CA 94104
6 INSTALL PER TCPUD STANDARDS.
/ =--------- =--------- �\ (C) 2011 BSA ARCHITECTS INC "All
7 ` 8 drawings and written material appearing
11. CONNECT TO ( ) A SEE MECHANICAL PLANS. herein constitute the original and
Is......... 29
i
I........... :..... / unpublished work of the architect and the
-- 12 GAS SERVICE TO BUILDING, SEE MECHANICAL PLANS b duplicated, d G, S D3 7 same may not e used, or
co
disclosed without the written consent of the
13 13. CONSTRUCT TRENCH DRAIN. SEE STORM PLAN AND 3 architect"
C� PROFILE. D3.
\I/
14. ELECTRIC SERVICE FROM BUILDING TO FUTURE
co�9ZN GENERATOR, SEE MECHANICAL PLANS.
28 15. SEWER LATERAL. SEE SEWER PLAN AND PROFILE.
w (P) DRIVEWAY
16. (E) SEWER MANHOLE, PROTECT IN PLACE.
U)i APPROXIMATE IE = 6752.16 W
U)
-,-'
_--- ---- 14 C/) 17. INSTALL 2000 GAL SEWER INTERCEPTOR PER v
w , I � MECHANICAL PLANS, SEE SEWER PLAN AND PROFILE. Q
(P) PATIO (P) STAIRS D O
Cn 18. ELECTRIC TRANSFORMER(S), SEE ELECTRICAL PLANS.
\ J
(P) DECK I 18 22 19. GAS METERS WITH SHED, PER MECHANICAL PLANS.
27 (E) BUILDING
W
w , I 3 r r v � 20. CATV SERVICE TO BUILDING, SEE MECHANICAL PLANS.
1 1 1 1 �� z Q
2 U)
' L J J 17 25 21. ELECTRIC SERVICE TO BUILDING, SEE ELECTRICAL PLANS. z �
(P) BUILDING 20 r - - , Q S J � �
P 22 L - r 22. INSTALL & STUB 2' GAS SERVICE FOR FUTURE O LJJ �
{ ° m o SS SS // D CONNECTION GENERATOR, SEE MECHANICAL PLANS. Q
24
g TV- 11 I�_�� 23. CONSTRUCT STORM DRAIN INLET(S). SEE STORM PLAN 1 = U
23 I 19 G � G) W AND PROFILE. D3. 7 Q L
II _ Q L z w
21 p o II 24. CONSTRUCT DRAINAGE SWALE. SEE GRADING AND 5 (n
II 9 I DRAINAGE PLAN.
D3.
% C`7
12 23 1 O
25. CONSTRUCT SEWER MANHOLE, SEE SEWER PLAN AN O
D 1-3
PROFILE, SHEET C2.6. D3. Q
(E) SKI LIFT \\IY\ W W �s
26. INSTALL STORM DRAIN OUTFALL. 1
D3.
5 4 -
27. ELECTRICAL CONDUIT, SEE ELECTRICAL PLANS FOR ISSUE
I TERMINATION TO EQUIPMENT AND CONDUIT SCHEDULE. 90% CORE & SHELL BID SET
23
I 28. INSTALL 8"WATER MAIN PER TDPUD STANDARDS. RELEASE DATE Z
PLANTER I 29. RE-CONNECT EXISTING SERVICE TO NEW WATER MAIN 2/24/2023 O
\ \ k k k 29 PER TDPUD STANDARDS.
23
• ,/ � � � o� � � � z �
� I REVISIONS U
26
Q o
� z
o
CD
N
PROJECT NO. 450.32
co
i MADE BY JF 0
7� REVIEWED BY CA/WA U.
J
\ (E) BUILDING / /
�� / UTILITY PLAN p
z
Q
GRAPHIC SCALE
20 0 0
0 20o
Mo 1 INCH = 20 FEET O
Ln
Page 35 of 215
ELECTRIC AND WATER DEVELOPMENT AGREEMENT
BETWEEN THE
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
AND
OWNER/DEVELOPER
046-250-009
Tahoe Donner Downhill Ski Lodge
This Agreement is entered into between the TRUCKEE DONNER PUBLIC UTILITY DISTRICT, a
local public agency of the State of California, hereafter referred to as "the District," and Tahoe
Donner Association, hereafter referred to as "Developer," with respect to the following facts:
RECITALS
A. Developer is the owner of that certain real property located within Nevada County, California,
bearing Assessor's Parcel Number 046-250-009 on which Developer intends to construct a
"Replacement of Downhill Ski Lodge with facilities for rentals, food and beverage dining,
commercial kitchen, offices and support spaces", hereafter referred to as the "Project."
B. Developer intends to construct a complete electric distribution system for the Project in
accordance with the approved plans and specifications. Such system shall hereafter be referred
to as the "electric distribution system."
C. Developer intends to construct a complete water distribution system for the Project for domestic
and fire protection use, including pipes, valves, service laterals, and related equipment, in
accordance with the approved plans and specifications. Such system shall hereafter be referred
to as the "water distribution system."
D. The electric and water distribution systems is a necessary part of the Project, and Developer
has requested that the District accept the system by including it within the District's existing
integrated system. Developer has further requested that, upon completion,the District thereafter
own, operate, maintain, repair, and replace the electric and water distribution systems as
necessary. If the total value of the projects on-site improvements being installed by the
Developer to be conveyed to the District for ownership, operation and maintenance exceeds
$400,000, the Development Agreement will be brought to District's Board of Directors for
review. The total value will be calculated by the engineer of record.
E. The District is willing to accept the electric and water distribution systems providing it is properly
constructed in accordance with the approved plans, specifications and terms of this Agreement.
F. Complete plans and specifications for the construction of the electric and water distribution
systems have been prepared in accordance with the District's Rules and Regulations and with
the requirements and specifications as hereafter set forth. Copies of the approved plans and
specifications are on file in the District's Department.
G. Developer has selected contractors for construction of the electric and water portions of this
Project. The names of the contracting firms, contact persons, mailing addresses, telephone
numbers, California Contractor License, insurance coverage verification and a schedule of
Page 1 of 14
Page 36 of 215
construction dates have been included on data sheets entitled Contractor Firm Data Sheets,
and are on file in the District's Electric and Water Departments.
H. The following items are on file in the District office and incorporated herein by reference:
• Development agreement application
• Contracting firm data sheet— electric
• Contracting firm data sheet—water
• Temporary Blanket Public Utility Easement
• Proof of Insurance
• Project parcel map
• Site and Improvement plans - electric
• Site and Improvement plans -water
• Estimated costs and calculation of fees — electric
• Estimated costs and calculation of fees —water
• Improvements by and Responsibilities of Developer— electric
• Improvements by and Responsibilities of Developer- water
• Improvements by and Responsibilities of District— electric
• Improvements by and Responsibilities of District -water
• Project documentation policy
• TDPUD Electric Construction Standards
• TDPUD Water Construction Standards
The parties agree as follows:
1. Payment of Costs and Fees. The District has prepared an estimate of its costs for materials,
labor, consultants, and legal expenses that the District expects to expend for administrative,
design, inspection, and actual construction (hereafter collectively referred to as the
"construction costs"). Upon start of construction, Developer shall deposit with the District
amounts that shall be applied to the actual construction costs incurred by the District. If the
actual cost exceeds the amount deposited, Developer shall pay such excess within thirty(30)
days of receipt of the District's invoice. If the actual cost is less than the amount deposited,
the District shall refund the difference within sixty (60) days of the date of unconditional
acceptance of the electric and water distribution systems. Upon execution of this Agreement,
Developer shall also pay to the District the fees set forth in the estimated construction costs
and calculation of fees.
2. N/A
3. N/A
4. Provision of Easements - Permission to Enter Land. Developer will execute a temporary
blanket easement granting the right to do all things necessary for the construction of the
electric and water facilities including, but not limited to, a right to ingress and egress, a right
to temporarily store equipment and materials, to excavate, to drive vehicles over, to place
markers on, to survey, to inspect and repair, and to remove rocks, boulders, trees and plant
life in the course of excavation or re-excavation. The temporary easement will be abandoned
upon receipt by the District of a permanent easement for the maintenance and repair of the
electric and water distribution systems.
Page 2 of 14
Page 37 of 215
5. Provision of Insurance - Upon execution of this agreement, Developer shall provide the
District with satisfactory evidence of an insurance policy written upon a form and by a
company which meets with the approval of the District, insuring the District, its officers,
agents and employees against loss or liability which may arise during the construction, or
which may result from any of the work or construction herein required to be done, including
all costs of defending any claims arising as a result thereof. The minimum limits of such
policy shall be in the amount of$1,000,000 for the death of or injury to any person in any one
accident and $2,000,000 for the death of or injury to more than one person in any one
accident and $1,000,000 for property damage in any one accident. Such policy shall be
written in favor of Developer or its general contractor and subcontractors and also in favor of
the District, its officers, agents and employees and shall be maintained in full force and effect
until the electric and water distribution systems are unconditionally accepted by the District.
Such insurance policy shall state by its terms or by an endorsement that it shall not be
canceled without thirty (30) days prior written notice to the District that the right of
subrogation is waived and that the coverage is provided on a primary and non-contributory
basis.
6. Indemnification by Developer. Developer shall indemnify, defend and save harmless the
District, its officers, agents and employees, and each of them, of and from any and all claims,
demands, causes of action, damages, costs, expenses, losses, or liabilities, in law or in
equity, of every kind and nature whatsoever, for, but not limited to, injury to or death of
Developer, any subcontractor of Developer, or any officers, agents or employees of the
District, of Developer, or of any subcontractor, or any other person, and damages to or
destruction of property of the District or any other person, arising out of or in any manner
directly or indirectly connected with the work to be performed underthis Agreement,however
caused, regardless of any negligence of the District or its officers, agents or employees,
except for the active negligence or willful misconduct of the District.
7. Improvements by and Responsibilities of Developer- Electric. Developer shall perform and
be responsible for all labor and material expenses involved in performing the distribution
system improvements described in the design drawings and outlined under the general
construction notes entitled Customer to Supply and Install.
8. Improvements by and Responsibilities of Developer-Water. Developer shall perform and be
responsible for all labor and material expenses involved in performing the water distribution
system improvements described in the attachment entitled Improvements by and
Responsibilities of Developer (Exhibit A).
9. Improvements by and Responsibilities of District- Electric. The District shall assign a Project
Administrator to oversee the Project. The District shall perform electric distribution system
improvements at Developer's expense as described in the design drawings and outlined
under the general construction notes entitled TDPUD to Supply to the Customer, for
Installation by the Customer and TDPUD to Supply and Install at Customers Expense. The
construction costs deposited with the District shall be applied to the actual construction costs
unless otherwise indicated. If the actual construction costs exceed such deposit, Developer
shall pay such excess within thirty (30) days of receipt of the District's invoice.
10. Improvements by and Responsibilities of District—Water. The District shall assign a Project
Administrator to oversee the Project. The District shall perform water distribution system
improvements at Developer's expense as described in the attachment entitled Improvements
by and Responsibilities of District (Exhibit B). The construction costs deposited with the
Page 3of14
Page 38 of 215
District shall be applied to the actual construction costs unless otherwise indicated. If the
actual construction costs exceed such deposit, Developer shall pay such excess within thirty
(30) days of receipt of the District's invoice.
11. Construction Inspection. The District shall inspect the construction from time to time, in order
to determine that the electric and water distribution systems are installed in accordance with
the approved improvement plans, construction specifications and the terms of this
agreement.
a. The District shall notify the Developer and/or the Developer's representatives in writing
as to any deviation from the approved improvement plans, construction specifications
and the terms of this agreement. The Developer and/or the Developer's representatives
shall correct such deviation or failure as soon as is reasonably practicable.
12. Timely Construction Required. Construction of the electric and water distribution systems
shall be completed, as defined herein, within twenty-four (24) months from the date of
execution of this agreement. In the event Developer fails to complete the electric and water
distribution systems within that time, the District may in its discretion (1)increase any and all
fees and costs to equal the District's current charges, (2) require Developer's plans and
specifications to be updated and redrawn to comply with the District's current standards,and
(3) terminate this Agreement and recover from Developer the full cost of all expenses and
charges incurred by the District, including but not limited to material, labor, backfill, paving
and outside services.
13. Developer's Warranty. Developer warrants and guarantees that all labor and materials
supplied by Developer are of a good and workmanlike quality, free of any defects of any type
whatsoever for a period of one(1)year after unconditional acceptance by the District.Within
the period of this warranty, Developer shall repair or replace, at Developer's expense, any
defective material or workmanship. The District shall notify Developer of any malfunction or
nonconformity promptly upon discovery. Within fifteen (15) business days after receiving
notice from the District, Developer shall commence to repair or replace the defective part and
will expeditiously pursue such work to completion and acceptance by the District. Emergency
repairs will be coordinated by District and charged to the Developer.
14. No Early Use of Project. Developer shall not request or obtain a temporary occupancy
permit, final inspection approval, nor shall Developer use, or permit anyone else to use, any
portion of the electric and water distribution systems on the Project, nor shall Developer use
or permit anyone else to use any electric and water service supplied by the District, until the
District has granted Conditional Acceptance in writing. Developer may, however, with the
District's written permission and prior to conditional acceptance, use electricity or water for
metered construction purposes. The District shall be entitled to terminate,without notice,any
electric and water usage by Developer or any other person, other than that required for
construction purposes, occurring prior to unconditional acceptance by the District of the
entire electric and water distribution systems.
15. Completion of the System. Construction shall be deemed complete when the District
determines that the electric and water distribution systems have been entirely finished,
properly tested, and ready to service the Project in accordance with the District's Rules and
Regulations and qualifies for Unconditional Acceptance.
16. Conditional Acceptance. When the District has determined that the electric and water
Page 4 of 14
Page 39 of 215
distribution systems have been completed, the District may conditionally accept the system
and may provide electric and water service, on a conditional basis, to the Project.
Conditional service shall be provided to enable Developer to use the Project while Developer
is in the process of providing to the District those items specified in the paragraph entitled
"Requirements for Unconditional Acceptance." Any conditional acceptance shall be in
writing from the District General Manager. If at any time the District, in its sole discretion,
determines that Developer is not making adequate progress toward providing the District
with the required items or is delinquent in not paying for metered electric and water services,
then the District may, after providing thirty (30) days prior written notice, discontinue
conditional electric and water service to the Project. Any electric and water service provided
by the District prior to unconditional acceptance of the electric and water distribution systems
shall be deemed conditional service.
17. Requirements for Unconditional Acceptance. Within thirty (30) days after completion as
determined by the District, Developer shall fully comply with all steps set forth below, and
upon such full compliance, the District shall unconditionally accept the electric and water
distribution systems.
a. Developer shall execute an offer of dedication for the electric and water distribution
systems to the District in a form satisfactory to the District, without cost, free, and clear
of all liens and encumbrances.
b. Developer shall certify that the Project was constructed with approved materials and in
compliance with the development agreement and the approved plans, except as noted
on the Project documentation drawings.
C. Developer shall provide the District with Project documentation drawings in compliance
with District policy.
d. Developer shall provide the District with the appropriate permanent easements.
e. Developer shall provide the District with a maintenance bond in a form satisfactory to
the District in a sum equal to fifteen percent(15%) of the ultimate construction costs of
the water distribution system. This bond shall remain in effect for a period of one (1)
year after unconditional acceptance of the water distribution system and protect against
any defects or failures in the system that may develop during that time.
f. Developer shall provide the District with a statement of the "as-built" dollar value of the
installed electric and water distribution systems with documentation to substantiate the
stated value.
g. Developer shall pay any outstanding costs and fees.
18. Responsibilities After Unconditional Acceptance. Prior to unconditional acceptance of the
electric and water distribution systems by the District, Developer shall be responsible for all
maintenance and repair of the electric and water distribution systems. Upon unconditional
acceptance of the electric and water distribution systems by the District, the District shall
thereafter own, operate, maintain, repair and replace the electric and water distribution
systems, unless such repairs or replacements are covered by Developer's warranty.
Thereafter, the District shall use its best efforts to provide adequate electric and water
service to the Project upon request, completion of any permit requirements and payment of
Page 5 of 14
Page 40 of 215
all appropriate fees and charges, in accordance with California law Town of Truckee, County
of Nevada requirements and District Rules and Regulations.
19. Notices. Notices or requests from either party to the other shall be in writing and delivered or
mailed, postage prepaid, to the following addresses:
Tahoe Donner Association
John Mitchel
11509 Northwoods Blvd
Truckee, CA 96161
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
Attention: Contract Administrator
11570 Donner Pass Road
Truckee, California 96161
20. Successors and Assigns. This Agreement shall be binding upon and inure to the benefit of
the successors and assigns of all parties; however, Developer shall not assign any of its
rights, duties or obligations under this Agreement without the prior written consent of the
District.
19. District Powers. Nothing contained herein shall be deemed to limit, restrict, or modify any
right, duty, or obligation given, granted, or imposed upon the District by the laws of the State
of California now in effect, or hereafter adopted, nor to limit or restrict the power or authority
of the District. The District may enact rules, regulations, resolutions, or ordinances,
including, without limitation, creation of service zones and rate differentials applicable within
the Project area that may not be applicable elsewhere, at its discretion.
20. Severability. In the event that any part or provision of this Agreement is found to be illegal or
unconstitutional by a court of competent jurisdiction, such findings shall not affect the
remaining parts, portions, or provisions of this Agreement.
21. Attorneys' Fees. In the event of any litigation concerning any controversy, claim or dispute
between the parties hereto, arising out of or relating to this Agreement or the breach hereof,
or the interpretation hereof, the prevailing party shall be entitled to recover from the other
party reasonable attorneys' fees and costs incurred therein or in the enforcement or
collection of any judgment or award rendered therein.
22. Entire Agreement. This Agreement contains the entire agreement of the parties and
supersedes any prior written or oral agreements between them concerning the subject
matter contained herein. There are no representations, agreements, arrangements, or
understandings, oral or written, between the parties relating to the subject matter contained
in this Agreement which are not fully expressed herein. The provisions of this Agreement
may be waived, altered, amended or repealed in whole or in part only upon the written
consent of all parties to this Agreement.
23. Dispute Resolution. If at any time during the Development Agreement process issues arise
that need resolution, the Developer should submit a written request to the Project
Administrator responsible for the Project in question. Such request shall state all of the
Page 6 of 14
Page 41 of 215
items of concern. The Developer can expect a response within 10 business days from
receipt of request. If no resolution is reached, the Developer can request a meeting with the
District's General Manager. If still no resolution is reached, the Developer can request a
meeting before the Board to resolve the issue. The item shall be agendized before the
Board for the next scheduled regular Board meeting. Scheduling shall be consistent with the
Brown Act and must occur with at least 72 hours prior notice. Only after this process is
exhausted without resolution of the dispute may the parties proceed to litigation. If either
party commences a court action against the other based on a dispute or claim to which this
paragraph applies without first complying with the provisions of this paragraph, the party
commencing the court action shall not be entitled to recover attorney's fees or costs, even if
they would otherwise be available in such court action.
24. Forum. Any litigation to enforce or interpret the provisions of this Agreement or the parties'
rights and liabilities arising out of this Agreement or the performance hereunder shall be
maintained only in the courts in the Superior Court in and for the County of Nevada,
California, if in state court, or the Federal Court for the Eastern District of California, if in
federal court.
25. Captions. The captions and headings of the different paragraphs of this Agreement are
inserted for convenience of reference only, and are not to be taken as part of this Agreement
or to control or affect the meaning, construction, or effect of the same.
26. Necessary Acts. Each party to this Agreement agrees to perform any further acts and
execute and deliver any further documents that may be reasonably necessary to carry out
the provisions of this Agreement.
27. No Waiver. The waiver by one party of the performance of any covenant, condition or
promise shall not invalidate this Agreement, nor shall it be considered as a waiver by such
party of any other covenant, condition or promise. The delay in pursuing any remedy or
insisting upon full performance for any breach or failure of any covenant, condition or
promise shall not prevent a party from later pursuing remedies or insisting upon full
performance for the same or any similar breach or failure.
28. Governing Law. This Agreement shall be governed by and construed in accordance with
the laws of the State of California.
29. Water Pipeline Construction and Reimbursement. The DISTRICT has identified the
need to replace the existing water distribution system piping throughout the Tahoe
Donner Ski Bowl Condominium complex. This includes piping in the immediate vicinity of
the Project. The DISTRICT has delayed this pipeline replacement work to avoid conflicts
with construction of the Project. The DISTRICT intends to undertake this pipeline
replacement work within three years of completion of the Project.
The scope of the Project includes placing new asphalt pavement in the immediate vicinity of
the new base lodge structure. It is planned to install replacement water pipelines in this
area. In order to avoid disturbing any newly placed asphalt, the Developer agrees to install
approximately 455 feet of new water distribution piping and appurtenances as depicted on
the approved Project drawings.
Page 7 of 14
Page 42 of 215
The DISTRICT agrees to reimburse the Developer for the cost of installing this piping in
accordance with the attached cost estimate. Final payment for this work shall be based
upon the unit prices given in the cost estimate and the actual quantities installed in the field
as measured by the DISTRICT.
Reimbursement to the Developer shall not be made until Unconditional Acceptance of the
Project is achieved. The conditions for Unconditional Acceptance are described in this
Development Agreement. Upon Unconditional Acceptance, the Developer shall submit an
invoice or letter to the DISTRICT requesting reimbursement for the pipeline installation
work.
This Agreement shall be binding upon the parties only when signed by all parties. The District
representative shall not sign this Agreement until Developer has provided all costs, fees and items
required to be provided by Developer"upon execution of this Agreement."
Dated:
Annie Rosenfeld, General Manager
Tahoe Donner Association
Dated:
Brian C. Wright, General Manager
Truckee Donner Public Utility District
Page 8 of 14
Page 43 of 215
ESTIMATED ELECTRIC FEES
FACILITIES, CONNECTION,AND METERING
TD DOWNHILL SKI LODGE
WO#22-644470
Date: 4/17/2024
1.FACILITIES FEES
Qty Charge Total
30 1200A 277/480V 1 $26,975.00 $26,975.00
Total Facilities Fees $26,975.00
2.CONNECTION FEES
esign, installation and inspection of primary an Material cost $ 29,152.01
econdary cables,transformer and electric mete Labor cost $46,295.82
Total Connection Fees $ 75,447.84
3.METERING FEES
(1)9S CL20 meter and CTs
Material cost $2,248.00
Labor cost $1,334.84
Setup&Admin Fee $115.00
Total Metering Fees $3,697.85
TOTAL $106,120.69
Project Documentation Deposit (see note 1.) 5.0% $3,957.28
$1000 minimum deposit
GRAND TOTAL $110,077.97
Deposit received 12/15/22 Deposit Received ($1,000.00)
BALANCE DUE $109,077.97
Note:
1.The Project Documentation Deposit will be refunded to the developer when the project
as-built drawings have been submitted to and accepted bythe District in accordance
with District policy, See Development Agreement for As-Built policy.
2. Long lead times exist for required project materials. Project materials will not
be ordered until fees are paid in full to the District.
Page 10 of 14
Page 44 of 215
General Construction Notes:
TRUCKEE DONNER PUD-ELECTRICAL DESCRIPTION OF WORK PROJECT NOTES
CUSTOMER TO SUPPLY AND INSTALL,AS INDICATED ON THESE DOCUMENTS: Site Work Electric Work
O - Primary Overhead TRUCKEE DONNE
Poles
•
•�' Secondary Overhead CD
CV
Vaults&Boxes N
Primary Underground
❑
El
MSecondary Underground
Switching Facility ■ ■
F-1 Transformers
d
d
d
Vicinity Map c
Transformer Pads �
❑ m
m
a� m
Barrier Posts
x
M
. Trench Work
• �� � Meter Panels
TDPUD TO SUPPLY TO THE CUSTOMER,FOR INSTALLATION BY THE CUSTOMER:
1
■
TDPUD TO SUPPLY AND INSTALL AT CUSTOMER EXPENSE
Sheet Index:
(NOT A COMPLETE LIST):
■
•
Truckee, California
�5 ]
RUCKEE DONNE
UBLIC UTILITY DISTRIC
Private Access Rd 1/5/2023
0 ` - 30
co
- W
Retire 'A O U
Q� 113 KVA J
Qy� — cn
CIO
0 J F-.F-
1A85 J J
❑ �U
z
O
Q � (n
wo-
Z �
00
0
Z 0o
ti
�_ wLr)
0
w�
w Y
W
U
0
u_ �
> F-
0
2
w
U
0'
H
U
w
J
LL'
Page 46 of 215�
11509
RUCKEE DONNE
UBLIC UTILITY DISTRIC
1/5/2023
4 �
0 0
P r i v a t ess Rd 1 ' = K
1 3
W C)
CD U)
�
0
60 p o(0
04
J
Lot #RrF
— c
Jo
v) Z)U
11585 J U a
U
16363 3 Phase Pad/Vault
0 z
577TD
Traffic Cover �, 11507 Z L-
ZC
00
Do
3 � wLO
0
L
0
a
J
Y
O
w
11631
Page 47 of 215�
11509
RUCKEE DONNE
UBLIC UTILITY DISTRIC
1/5/2023
4 �
0 0
Private Access Rd 1 ' =T 30 '
G.
W v
O
0
Lot #R N
O o�
J ��
� M
11585 J o
C/)
0 ^ JID
16363
0 J �
11507 z
lot '
O wo-
Z
� o
0 Do
� wr--
oLL
Y�
U
o
J
Z
O
FNote
---- 11631 :
Conduit lengths are approximate.
Page 48 of 215�
11509
RUCKEE DONNE
UBLIC UTILITY DISTRIC
1/5/2023
4 �
0 0
Private Access Rd 1 ' = 30
UJ
,�9V gal
■ M
p
_ 0(0
v
Lot #R m ��
JL
. N v) �—
O �U
11585 J U
577TD
J U
Vault
16363 ` z ��
0
C �
ABC Phase 11507 wo-
�` 500 KVA o z aD
ir` 480Y/277 Volts Q O C
0
qec�A, Q p o
3 'so w
w�
Y
U
o
u_
0
a
J
U
H
U
w
J
LL'
11631
Page 49 of 215�
Estimated Water Fees
TD Downhill Ski Area Base Lodge WO # - 22-744470
The Estimated Costs are as follows:
Administrative and design $ 1,000.00
Engineering & modeling 0.00
Construction and inspection 1,500.00
Project documentation deposit 5,000.00
Total Estimated Costs $ 7,500.00
The Fees as follows:
Total Fees $ 0.00
Total Estimated Costs & Fees $ 7,500.00
Less Deposit Paid in Advance ( 1,000.00)
BALANCE DUE $ 6,500M
Page 11 of 14
Page 50 of 215
Exhibit A
Improvements by and Responsibilities of Developer
1. Schedule a pre-construction meeting with District staff and the pipeline contractor.
2. Provide all permits required.
3. Provide all traffic control and trench protection as required per applicable laws and
TDPUD field supervisor's requirements.
4. Construct water system improvements per approved plans/construction drawing.
5. Water facilities constructed under this "Development Agreement/Estimate of Water
Construction"shall be constructed by appropriately licensed contractors. Contractors
shall have current and active licenses issued by the California Department of
Consumer Affairs, Contractors License Board. The appropriate licenses for water
system construction are typically "A — General Engineering Contractor", or "C34 —
Pipeline Contractor".
6. All construction to meet or exceed requirements of the current District WATER
SYSTEM CONSTRUCTION STANDARDS.
7. Perform all water pipeline testing and disinfection per requirements of WATER
SYSTEM CONSTRUCTION STANDARDS.
8. Provide compaction test results by a licensed professional.
9. Schedule main taps and meter installations with the Water Superintendent(Earl Smith
582-3955). A minimum of five working days notification is required for District crew
scheduling.
10. Contact Clay Walker(582-3926)to confirm cross connection installation requirements
(equipment, location, testing, etc.).
11. Compile and submit project documentation drawings in accordance with District
requirements.
12. Certify that the project was constructed with approved materials and in compliance
with the development agreement and the approved plans, except as noted on the
project documentation drawings.
Page 12 of 14
Page 51 of 215
13. Schedule and attend final walk through inspection with contractor and District
representatives.
Page 13 of 14
Page 52 of 215
Exhibit B
Improvements by and Responsibilities of District
1. Operate water system as required including customer notification (outages),
system shut-down and system flushing.
2. Attend pre-construction meeting.
3. Inspect installation and construction of Project.
4. Relocate the existing 1.5" water meter to the new point of service
5. Observe pressure testing & disinfection activities.
6. Take bacteriological samples.
7. Review, approve and inspect installation of all required backflow prevention
equipment.
8. Attend final walk thru inspection and prepare punch list if necessary.
Page 14 of 14
Page 53 of 215
Tahoe Donner Downhill Ski Lodge Project - TDPUD Water Line Costs
Bid Item Description Quantity Uni Unit Price** Total
t
1 Mobilization / Demobilization / BMPs 1 LS 1,209.65 1,209.65
2 Surveying 1 LS 1,907.93 1,907.93
3 Slalom Way Temporary Connection (8x8x6 'T') 1 LS 1,813.00 1,813.00
4 FL Tee with RFCA 1
6" FL GV 1
FL x MJ bend 1
5 8-Inch Water Main incl. Trenching and Backfill 455 LF 234.00 106,470.00
6 8-Inch Gate Valves 3 EA 2,881.00 8,643.00
7 6-Inch Gate Valve 1 EA 2,637.00 2,637.00
8 8" Mechanical Joint Cap Fittings 3 EA 799.00 2,397.00
9 ARV Assembly 1 EA 7,428.00 7,428.00
10 New Fire Hydrant 1 EA 16,075.00 16,075.00
11 Reconnect Water Services to Condos 1 LS 11,512.00 11,512.00
2" HDPE Service Line 2
1" WM Assembly 2
Abandon Each (E) Service at Corp Stop 2
12 Compaction testing for water lines 1 LS 1,936.00 1,936.00
13 Pressure testing 1 LS 4,235.00 4,235.00
14 Disinfection and flushing 1 LS 4,235.00 4,235.00
GC Subtotal $170,498.58
15 General Conditions 1 % 6.2% 10,541.68
16 GC Insurance 1 % 1.0% 1,704.99
17 GC Fee 1 % 4.0% 7,241.61
GC Total $189 986.85
18 Owner Rep. CM 1 % 1.3% 2,533.91
Grand Total $192,520.76
**Includes Prevailing Wage Rates
Page 54 of 215