HomeMy WebLinkAbout#13 Ski Run Tank Replacement Project AGENDA ITEM #13
Public Utility District m
MEETING DATE: May 1, 2024
TO: Board of Directors
FROM: Neil Kaufman, System Engineer
Chad Reed, Water Utility Director
SUBJECT: Consider Approval of a Contract with Resource Development
Company for the District's Ski Run Tank Replacement Project for an
Amount not to Exceed $1,317,600.
APPROVED BY:
Brian C. Wright, General Manager
RECOMMENDATION:
Authorize the General Manager to execute a construction contract with Resource
Development Company for the District's Ski Run Tank Replacement project in the
amount of $1,197,800, plus a ten percent change order allowance of $119,800 for a
total authorization not to exceed $1,317,600.
BACKGROUND:
The District currently operates 34 water storage tanks throughout the water distribution
system:
• 30 ground level welded steel tanks
• Two ground level bolted steel tanks
• One partially buried pre-stressed concrete tank
• One elevated welded steel tank
The tanks range in volume from 100,000 gallons to 1.5 million gallons, with the oldest
tank constructed in 1963 and the newest tank constructed in 2021.
District staff evaluated adjustments in capital maintenance required to extend the useful
life of the inventory of water utility storage tanks during the preparation of the 2020
Water System Capital Improvement Plan update. Through this process, staff
determined the need to increase funding allocated to a more comprehensive tank
maintenance program, and subsequently adjusted budgets to fund this
maintenance. Many of these tanks still use their original interior coating systems, which
are approaching 50 years old. The design standards and seismic engineering
requirements have also changed significantly, and many tanks do not meet current
Page 1 of 4
Page 55 of 215
standards.
ANALYSIS AND BODY:
In order to efficiently spend these maintenance funds, the need for an outside
engineering consultant was identified. Valuable experiences were gained during the
Roundhill Tank rehabilitation project. During this project, it was found that the tank
infrastructure exhibited more advanced stages of corrosion than originally anticipated,
requiring significant change orders to cover additional repairs to address this
issue. The additional costs and efforts required to address the advanced stages of
metal degradation were approaching the cost of completely replacing the tank. The
experience gained in the Roundhill Tank rehabilitation project prompted staff to do a
more comprehensive study on rehabilitation versus replacement of existing tanks.
In September 2022, the Board of Directors approved a contract with Carollo to conduct
engineering evaluations and prepare bid documents for the rehabilitation of the Ski Run
and Prosser Lakeview Tanks. During the course of this work, it was determined that the
District should not proceed with rehabilitation of the Prosser Lakeview Tank. Detailed
inspections revealed that the interior of the tank exhibited advanced stages of metal
degradation, exceeding industry standards for rehabilitation. An overall review of water
system hydraulics and water storage capacities determined that the water system could
function efficiently without the utility of the Prosser Lakeview Tank. Abandonment and
demolition of the tank within a 5-7 year time frame is currently planned.
Based upon the field inspections, it is believed the Ski Run tank is in better condition
than the Prosser Lakeview Tank. However, it should be noted that the Ski Run Tank is
experiencing some leakage in the proximity of floor construction and subterranean
infrastructure (inlet piping and weld seams). The current configuration of the water
system prevents the tank from being removed completely from service to perform a
thorough interior inspection. Since the tank cannot be drained for a comprehensive
review, the engineers' report denotes some uncertainties regarding the level of
rehabilitation required to bring the existing Ski Run Tank to current engineering
standards. It should also be noted that the Ski Run Tank was built by the same
contractor in the same time frame as the Roundhill tank. For this reason, staff believes
similar change orders will be associated with the rehabilitation of Ski Run tank, and that
replacement is more fiscally responsible than rehabilitation.
A set of bid documents for rehabilitation of the Ski Run tank was prepared, and bidding
began in early February 2023. The bid opening was held on March 2, 2023. Five bids
were received. The low bid for this work was $395,000. Additional costs would be
incurred for inspection and administration of the contract. It was determined that
expenditure of $450,000 - $500,000 for rehabilitation of the existing tank would not be
advisable, and on staff recommendation, the Board rejected all bids on April 5, 2023.
In May 2023, an RFP was issued to secure a consultant to design a new storage tank
to replace the existing Ski Run Tank. The consultant would also consider replacing the
existing Ski Run pump station, which has been in operation for about 50 years, and is
Page 2 of 4
Page 56 of 215
at the end of its useful life. Four proposals were received in response to the RFP. As a
result of this RFP process, a contract for design of the new tank was awarded to
Sauers Engineering at the August 2, 2023 Board meeting.
Construction bid documents were completed in early March 2024, and the District
began advertising for bids from construction contractors.
The bid opening was held on April 17, 2024. Three responsive bids were received:
SUMMARY OF BIDS
Bidder Location Bid Amount Responsive
Resource Sparks, NV $1,197,800 Yes
Development
Crosno Arroya Grande, CA $1,408,473.00 Yes
Construction
Paso Robles Tank Hemet, CA $1,741,700.00 Yes
In addition to the construction contract, the District will retain outside consultants to
perform construction inspection, environmental services and geotechnical testing for
this project. The estimated costs for this work are:
• Construction Inspection — CME — Estimated at $25,000
• Environmental Services — Inland Ecosystems — Estimated at $1,000
• Geotechnical Testing — NV5 — Estimated at $10,000
The Board of Directors approved the NV5 contract on December 6, 2023, as part of the
annual procurement process. The CME contract was approved by the Board at the
February 7, 2024, meeting.
GOALS AND OBJECTIVES:
District Code 1 .05.020 Objectives:
3. Provide reliable and high quality water supply and distribution system to meet
current and future needs.
6. Manage the District in an effective, efficient and fiscally responsible manner.
District Code 1 .05.030 Goals:
1. Manage for Financial Stability and Resiliency
4. Take the best of private sector thinking to modernize the utility and add value to our
communities.
FISCAL IMPACT:
The bid price from Resource Development is $1,197,800. It is recommended that a ten
percent change order allowance of $119,800 be established, for a total authorization of
Page 3 of 4
Page 57 of 215
$1,317,600. The rehabilitation of the Ski-Run tank was included in the water utility's 10-
year capital improvement plan. However, after the significant change orders associated
with a similarly aged tank, engineering services were consulted, and it was determined
that replacement would be the best path forward for this asset. Since the replacement
cost is higher than the anticipated rehabilitation cost, additional funding from the
District's capital budget will be required, pushing other tank rehabilitation projects back
in the CIP scheduled for FY2024. The water utility has sufficient funds for this capital
expenditure in 2024.
ATTACHMENTS:
None
Page 4 of 4
Page 58 of 215