HomeMy WebLinkAbout11 West End Donner Lake TDPUD MEMORANDUM December 12, 2002 TO: Board of Directors FROM: Neil Kaufman, Water System Engineer SUBJECT: INSTALLATION OF SERVICES FOR THE WEST END OF DONNER LAKE — CHANGE ORDER #3 AGENDA # BACKGROUND: At the Board Meeting on November 20, 2002, 1 presented, and the Board approved Change Order No. 2 for the INSTALLATION OF SERVICES FOR THE WEST END OF DONNER LAKE project. That change order covered issues under thirteen general items. Just prior to Thanksgiving, I received a call from Jaeger Construction indicating that four of the final quantities they had presented in the analysis of Bid vs. Actual quantities were in question. Jaeger indicated that they had purchased 31 fire hydrants from Western Nevada Supply but had not received a credit from Western for returned hydrants. Therefore, their office staff believed that 31 hydrants had been installed. They also indicated that a total of 49 gate valves and 11 fire hydrants had been abandoned, as opposed to the quantities of 38 and 6 originally presented. I directed the projected inspector (Paul Rose) to review his field reports and then perform another site inspection to verify the quantities in question. It was determined that only 27 fire hydrants were installed and that it was Jaeger's responsibility to straighten out the issue with Western Nevada Supply. It was also determined that the revised quantities for abandonment of gate valves and fire hydrants were correct. Therefore, I am presenting Change Order No. 3. This Change Order is for a total of $6,248, representing the cost of the additional nine gate valve abandonments and the five fire hydrant abandonments. RECOMMENDATION: I recommend that the Board authorize Contract Change Order No. 3, in the amount of $6,248.00 owed by the District to Jaeger Construction. Attachment-Contract Change Order No. 3 Page 1 12Acis-ac0utFWZURm'S rFom irtuur=vuitK uuJAEGER CONSTRUCTION 1-tbi P 001l001 (�j0Agli0al �!CKEE Utility 111 II t Public . Change Order Contract Name: INSTALLATION OF SERVICES FOR THE WEST END OF DONNER LAKE Contract Change Order No: 3 Ong. Contract Amt.$ 1,052,014.00 Days NA Date: December 11, 2002 Prev. Apprd Changes S - 1,510.10 Days NA Contractor: Jaeger Construction This Change$ 6,248.00 Days NA Revised Contract Amt.$ 1 056.751.90 Days NA This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items for a lump sum price agreed upon between the Contractor and District increase in (Decrease) Contract Time Description of Changes Contract in Contract Extension Amount $ Amount $ (days) 1) Gate Valve Abandonments (11 0 $278 each) $3,058.00 NA 2) Fire Hydrant Abandonments (5 @ $638 each) $3,190.00 NA Totals 66.248.00 Net change in contract amount (increase or decrease) $6,248.00 The amount of the Contract will be decreased by the sum of $6,248.00 and the Contract Time shall not be extended. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other necessary work. Inclusive of the directly or indirectly related to the approved time extension, required to complete the Change order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the rder shall be effective when approved by the District, Accepted: /Contractor Date: (Signature) Approved: /District Date: (Signature) Page 1 of 1