HomeMy WebLinkAbout8 Glenshire Pipeline TDPUD MEMORANDUM November 27, 2002 TO: Board of Directors FROM: Neil Kaufman, Water System Engineer SUBJECT: GLENSHIRE TRANSMISSION PIPELINE CHANGE ORDER #1 AGENDA # BACKGROUND: The Board of Directors previously awarded the Contract for construction of the GLENSHIRE TRANSMISSION PIPELINE project to Vulcan Construction. The project has been completed. I am requesting a Change Order to the Contract for issues covered under nine general items. Item 1: The contract was based on a unit price bid. Table 1 shows the differences between bid totals and the amounts actually constructed. This analysis results in a credit of $1,174.10 owed by Vulcan to the District. Item 2: The Bid Documents called for open cut construction across the Environmentally Sensitive Area located from Station 20+85 to Station 21+85 of the pipeline alignment. However, the final permit issued by the Lahontan RWQCB required that the pipeline be installed using trenchless construction methods. Discussions with Vulcan Construction indicated that bore & jack installation of a casing and then installation of the 16-inch pipe inside the casing would be the least expensive option. This additional work totaled $39,301. Item 3: The Bid Documents assumed that the developer for Old Greenwood would install a cross and butterfly valve to serve as the point of connection for the west end of the pipeline. However, the Developer's construction schedule postponed the construction of all water facilities until the Summer of 2003. Therefore, it was necessary for the District's contractor to install the cross. This work involved the purchase and installation of a 16-inch cross, four butterfly valves and some associated fittings. A price of$23,459 was agreed to with Vulcan Construction. Item 4: During excavation to install the pipeline through the Glenshire Drive Bridge, existing 18-inch, 20-foot long casing pipe were discovered at either end of the bridge outside of the bridge abutments. These casings interfered with Page 1 the pipeline construction and were removed by the Contractor and delivered to the District's storage yard on Coldstream Road. Vulcan Construction incurred costs of $3,526.70 in performing this work. Item 5: The Bid Schedule requires the Contractor to provide a unit price for pavement restoration. The unit price is based on a pavement thickness up to 4-inches. The pavement thickness of Glenshire Drive is between 10 and 12 inches in most of the area where the pipeline was constructed. Town of Truckee requirements call for pavement repairs to match the existing pavement thickness, with a maximum of 9-inches. Therefore, it was necessary to install an additional 5 inches of asphalt for most of the project, with an additional 2 inches of asphalt in other areas. A unit price of $1 .00 per inch per square foot was agreed to and Vulcan is due $ 44,784.50 for this additional asphalt work. A breakdown of this amount is shown in Table 2. Item 6: Along Glenshire Drive, it was necessary to perform some rock excavation at some locations in order to excavate the pipeline trench. Rock excavation is considered Extra Work under the Contract. Vulcan performed rock excavation for a total of 49 hours and is due $19,600 at an hourly rate of $400/hour. Item 7: The Contract Documents called for a connection between the new 16-inch pipeline and an existing 8-inch pipeline at the Glenshire Mutual Office. District crews placed USA marks at the proposed location of the tie-in. Upon performing some exploratory excavations, these marks proved incorrect. It was then necessary for Vulcan to perform additional exploratory excavation in order to locate the proper pipeline for the connection. It appears that the District's pipe locating equipment was registering on an abandoned steel water service lateral instead of the 8-inch asbestos-cement main. The additional exploratory excavations involved a backhoe, one operator and a laborer for one day. The cost of this work was $1,404.32. Item 8: At the west end of the Glenshire Drive Bridge, there is an existing duct bank consisting of six 6-inch conduits that crosses the pipeline alignment at an angle of about 20 degrees. The Drawings had indicated that there was only two conduits and not six. As a result, it was necessary to excavate the trench deeper and to install an additional elbow in order to avoid a conflict with the duct bank. Vulcan is due $5,433.54 for this work. Item 9: The Contractor was issued a Notice to Award on August 8, 2002 and mobilized to the site with the intent of commencing work on Monday, August 26, 2002. However, due to delays associated with some permitting and easement issues, the Contractor was unable to function at 100 percent efficiency for a couple of weeks after commencing the project on August 26. The Contractor submitted a claim for reimbursement of equipment rental Page 2 costs for equipment that was idled during this time period. I have reviewed the claim and based on discussions with the Vulcan, an amount of $17,202.04 was agreed upon. RECOMMENDATION: I recommend that the Board authorize Contract Change Order #1, in the amount of a $163,331.88 payment to Vulcan Construction from the District. Attachments —Table 1, Table 2, Contract Change Order #1 Page 3 Table 1 -Analysis of Bid Quantities vs.Actual Quantities Constructed Glenshire Transmission Pipeline Contractor: Vulcan Construction Bid Quantities Actual Quantities Bid Item Description Quantity Units Unit Price Subtotal Quantity Units Unit Price Subtotal 1 Mobilization 1 LS $ 25,000,00 $ 25,000.00 1 LS $ 25,000.00 $ 25,000.00 2 16"Class 250 DI Water Main from Station 0+00 to 59+58 5,958 FT $ 90,00 $ 536,220.00 5,972 FT $ 90.00 $ 537,480.00 3 16"Class 300 DI Water Main from Station 59+58 to 66+40 682 FT $ 73.00 $ 49,786.00 690 FT $ 73.00 $ 50,370.00 4 Glenshire Bridge Pipe Installation 1 LS $ 200,000.00 $ 200,000,00 1 LS $ 200,000.00 $ 200,000.00 5 16"Class 300 DI Water Main from Station 71+90 to 91+98 2,008 FT $ 84.00 $ 168,672.00 2,018 FT $ 84.00 $ 169,512.00 6 16"Class 250 DI Water Main from Station 91+98 to 106+25 1,427 FT $ 104.00 $ 148,408.00 1,439 FT $ 104.00 $ 149,656.00 7 16"Class 250 DI Water Main from Station 106+25 to 124+52.80 1,828 FT $ 79.00 $ 144,412,00 1,829 FT $ 79.00 $ 144,491.00 8 8"DI Water Main at Station 106+25 45 F' $ 11200 $ 5,040.00 33 FT $ 112,00 $ 3,696,00 9 10"DI Water Main at Station 124+52.80 20 FT $ 227.00 $ 4,540.00 44 Fr $ 227.00 $ 9,988.00 10 Connection to 16"Butterfly Valve by Others at Station 0+00 1 LS $ 1,000.00 $ 1,000.00 1 LS $ 1,000.00 $ 1,000.00 11 Connection to Existing 8"Piping at Station 106+25 1 LS $ 2,500.00 $ 2,500.00 1 LS $ 2,500,00 $ 2,500.00 12 Connection to Existing 10"Piping at Station 124+52.80 1 LS $ 3,800.00 $ 3,800.00 1 LS $ 3,800.00 $ 3,800.00 13 2"Blow-Off Assemblies 2 EA $ 2,500.00 $ 5,000.00 2 EA $ 2,500.00 $ 5,000.00 14 T'Air Valve Assemblies 3 EA $ 2,300.00 $ 6,900.00 3 EA $ 2,300,00 $ 6,900.00 15 14"Butterfly Valve Assemblies 2 EA $ 5,000.00 $ 10,000.00 2 EA $ 5,000.00 $ 10,000.00 16 16"Butterfly Valve Assemblies 2 EA $ 5,000.00 $ 10,000.00 2 EA $ 5,000.00 $ 10,000.00 17 Fire Hydrant Assemblies 2 EA $ 3,700.00 $ 7,400.00 2 EA $ 3,700.00 $ 7,400.00 18 AC Pavement Trench Restoration 15,000 SO Fr $ 4.50 $ 67,500.00 13,122 SO FT $ 4.50 $ 59,049.00 19 Perform AC Pavement Lane Restoration 31,200 SO FT $ 1.70 $ 53,040.00 30,707 SO FT $ 1.70 $ 52,201.90 20 All Other Work Required by the Contract Documents i LS 1 $ 48,000,00 1 $ 48,000.00 1 LS $ 48,000.00 $ 48,000.00 $ 1,497,218.03 $ 1,496,043.90 Difference Owed to District $ (1,174,10) Table 2-Calculation of Extra Depth of AC Pavement Glenshire Transmission Pipeline Contractor: Vulcan Construction Bid Price= $4.50 for up to 4-inch thick AC Additional Cost= $1.00 for each additional inch of AC Length, Width, Area, Depth, Bid Item Extra Depth, Extra Item Description feet feet square feet inches Total inches Total 1A West of Glenshire Bridge-Lateral w/T-cut 25 7 175,00 3 $787.50 0 $0.00 1 B West of Glenshire Bridge-Lateral w/T-cut-Extra Depth 25 4 100.00 9 $450,00 5 $500,00 1C West of Glenshire Bridge-Shoulder 32 8 256,00 6 $1,152,00 2 $512,00 1 D West of Glenshire Bridge-Shoulder 20 7 140,00 6 $630,00 2 $280,00 1E West of Glenshire Bridge-Shoulder 50 5 250.00 6 $1,125,00 2 $500.00 1F West of Glenshire Bridge-Shoulder 7 4 30,10 6 $135,45 2 $60,20 1G West of Glenshire Bridge-Lateral w/T-cut 40 7 280,00 3 $1,260,00 0 $0,00 1 H West of Glenshire Bridge-Lateral wIT-cut-Extra Depth 40 4 160.00 6 MOM 2 $320,00 2A East of Glenshire Bridge-Trench Patch 6 7 40,95 6 $184,28 2 $81.90 2B East of Glenshire Bridge-Trench Patch 545 4 2,180.00 6 $9,810,00 2 $4,360.00 2C East of Glenshire Bridge-Trench Patch 6 3 18,00 6 $81,00 2 $36,00 2D East of Glenshire Bridge-Trench Patch 13 1 14,30 6 $64.35 2 $28,60 2E East of Glenshire Bridge-Trench Patch 17 2 37,40 6 $168,30 2 $74,80 2F East of Glenshire Bridge-Trench Patch 3 2 6.00 6 $2T00 2 $12,00 3A East of Glenshire Bridge-Lateral 36 7 252,00 3 $1,134,00 0 $0.00 36 East of Glenshire Bridge-Lateral-Extra Depth 36 4 144.00 6 $648.00 2 $288.00 4 Old Highway 40 Crossing 45 12 540,00 4 $2,430,00 0 $0,00 5A East of Glenshire Bridge-Shoulder Patch 23 4 92,00 4 $414,00 0 $0.00 5B East of Glenshire Bridge-Shoulder Patch 11 4 38,50 4 $173,25 0 $0,00 5C East of Glenshire Bridge-Shoulder Patch 22 4 77.00 4 $346,50 0 $0,00 6A At GMWC Office-Lateral wfr-cut 23 7 149,50 3 $672.75 0 $0,00 6B At GMWC Office-Lateral w/T-cut-Extra Depth 23 4 92,00 6 $414,00 2 $184,00 7A Glenshire&Dorchester-Lateral w/T-cut 32 7 224.00 3 $1,006.00 0 $0.00 7B Glenshire&Dorchester-Lateral w/T-cut-Extra Depth 32 4 128.00 6 $576.00 2 $256,00 7C Glenshire&Dorchester-Pothole Excavation 7 7 45.50 6 $204,75 2 $91.00 8 Lateral at 14956 Glenshire Drive 13 4 52,00 3 $234,00 0 $0.00 9A GMWC Office Driveway 11 5 59.36 3 $267,12 0 $0.00 96 GMWC Office Driveway 25 4 100,00 3 $450,00 0 $0,00 10 Glenshire Drive from GMWC Office to Dorchester 1,860 4 7,440,00 9 $33,480.00 5 $37,200.00 Total 13,121,61 $59,047,25 $44,784,50 V Round Off to 13,122 I Cost of Extra Depth= $ 44,784.50 NOV-27-2002 11:37 P.02i02 Ray-V-[uut I:acam num-,,,�.,» •-,•,••• -- ��_ TRUCKFE DONNER Change Order Contract Name: G4ENSHIRETRANSMISSION PIPELINE Contract Change Order No, 1 Ong. Contract Amt.$ 1,497,218.00 Days NA Date: _ November 27,2002 _ Prev.Apprd Changes$ 0 Days NA Contractor. yuican Construction This Change S 163,331.88 Days NA Revised Contract Amt S 1.660,649.88_ Days NA This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items for a lump sum price agreed upon between the Contractor and District. Increase in (Decrease) Contract Time Contract in Contract Extension Description of Changes Amount $ Amount da s 11 Adjustment of Bid Unite vs.Actual Construction 31,174.10 NA 2) Bore&Jack of Environmentally Sensitive Area $39,301.00 NA 3} Installation of Cross at Old Greenwood $23,459,00 NA 4) Removal of Existing Casings $3,626.70 NA 5} Additional Pavement Thickness $44,784.50 NA 6) Rock Excavation $29,400.00 NA 7) Locate Pipe at GMWC Office $1.404.32 NA 8) Additional Depth at West End of G{enshire Drive Bridge $6,428.42 NA 9) Start-up Delays caused by Late Issuance of Lahontan $17,202,04 NA RWQCS Permit Totals $164,505.98 $1,174.10 Net change in contract amount(increase or decrease) $163,331.88 The amount of the Contract will be increased by the sum of $163,331 88 and the to Contract the changes, any.all not'in the be extended. The undersigned Contractor approves the foregoing Chang Ord a contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any,for completion of the entire work on account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of the directly or Indirectly related to the approved time extension, required ens will apply hereto Change order hems. This document will become a supplement of the contract and all p pp Y understood that the Change Order shall be effective when approved by the District. / L, Accepted: (Contractor Date: (Signwure) Approved: /District Date: (Signature) TnTRI P.P7 Agenda Item # Resolution No . 2002 - _ AUTHORIZING THE ACCEPTANCE OF THE GLEN SHIRE TRANSMISSION PIPELINE PROJECT AND DIRECTING FILING OF THE NOTICE OF COMPLETION WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the determination to undertake the Glenshire Transmission Pipeline Project; and WHEREAS, Vulcan Construction, was selected by the District to perform the work; and WHEREAS, the District's Water Utility Manager, Ed Taylor, has recommended that the work be accepted by the District; NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows: 1. That the District hereby accepts Glenshire Transmission Pipeline Project as complete. 2. That the Clerk of the District be directed to file with the County of Nevada the Notice of Completion, a copy of which is attached hereto. 3. That 35 days following the filing of the Notice of Completion, the 10% retained from the contractor payments be released to the contractor if no claims have been made to the District by material suppliers or laborers. PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the District on the 41h day of December 2002 by the following roll call vote: AYES: NOES: ABSTAIN: ABSENT: TRUCKEE DONNER PUBLIC UTILITY DISTRICT By Nelson Van Gundy, President of the Board ATTEST: Peter L. Holzmeister, Clerk of the Board bhc RECORDING REQUESTED BY: Truckee Donner Public Utility District WHEN RECORDED, RETURN TO: TRUCKEE DONNER PUBLIC UTILITY DISTRICT Post Office Box 309 Truckee, CA 96160 NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN: 1. That the name and address of the public entity for whom the improvement project was done, as owner thereof, is the Truckee Donner Public Utility District, Post Office Box 309, Truckee, CA 96160. 2. That on November 20, 2002 the hereinafter described improvements were accepted as complete pursuant to a resolution of the Truckee Donner Public Utility District, the awarding authority. 3. That the subject improvements of the Notice are generally described and identified as follows: Glenshire Transmission Pipeline Project. 4. That the name and address of the contractor for such project was: Vulcan Construction, 1010 West Whitesbridge Avenue, Fresno, Ca. 93706-1328 1 certify under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Dated: TRUCKEE DONNER PUBLIC UTILITY DISTRICT By Peter L. Holzmeister, General Manager