HomeMy WebLinkAbout5 Falcon Point Change Order Agenda #
. .
Memorandum
To: Board of Directors
From: Ed Taylor, Water Utility Manager
Date: October 11, 2002
Subject: Change Order Falcon Point#1
Date of Board Meeting: October 16, 2002
BACKGROUND:
The Board of Directors at the May 1, 2002 meeting awarded the Falcon Point Booster
Station Project contract to Longo Construction, Inc. The contract for the construction of the
Falcon Point Booster Station was $155,475.
The design for the Falcon Point Booster Station was based off of the as built drawings provided
by Dart. The as built drawings were for the construction of the Falcon Point Tank. The design
was completed during the winter months when snow prevented the site from being surveyed to
determine the tank location.
The site was surveyed after the bid award but prior to the start of construction. The tank location
was 3 feet different than the as built drawings had indicated.The building and pump station
design did not change, but the elevation and the orientation were changed. The station had to be
lower four feet into the embankment which required additional excavation and additional concrete
retaining wall construction.
ORIGINAL CONTRACT AMOUNT: $155,475.00
CHANGE ORDER#1 $14 475.39
TOTAL AFTER CHANGE ORDER= $ 169,950.39
RECOMMENDATION:
I recommend that the Board approve Contract Change Order#1.
Attachment: Memo from Sauers Engineering, Inc.
0 Page 1
SAUERS ENGINEERING S80 26S 6884 10/10/02 10o S0am P. 001
Sauers Engineering, Inc.
Civil & Environmental Engineers
October 9, 2002
Mr. Ed Taylor, Water Utility Director
Truckee Donner Public Utility District
P.O. Box 309
Truckee, CA 96160-0309
SUBJECT: FALCON POINT PUMP STATION - PROPOSED CHANGE ORDER
Dear Ed,
We have reviewed the proposed change order and backup information submitted by
project contractor Longo, Inc. The change order is intended to cover additional work
associated with the relocation of the purnp station on the site as compared to the original
project plans. The amount of the proposed change order is $40,475.39.
The proposed change order and backup information appear to reflect all of the material
and labor charges associated with the excavation of the building site and construction of
the building footings, slab, and concrete walls. The information does not appear to
reflect any work which would have had to have been done based on the original plans.
We looked at the charges invoiced by the contractor for various items of work and
compared them with our estimates of the work which would have been required by the
original plans. We have identified approximately $14,700 in legitimate additional
charges.
Some of the issues which came out of our analysis include the following:
1. The contractor appears to have charged all of the equipment and labor for the
excavation of the footing key-way and for the pouring of the footings and floor
slab. Although the key-way was added to the footing as a result of the building
acting as a retaining wall, the re-designed footing/key-way only resulted in an
increase in excavation and concrete of less than 20% as compared to the original
footings. Also, there should be no extra cost associated with the pouring of the
concrete slab as the slab was always part of the design.
2. The contractor appears to have charged all of the labor for forming and stripping
the concrete walls and for the labor and materials for pouring the walls. The
station re-design provided the option of masonry block or cast-in-place concrete
walls for the retaining wall portion of the building. Had the contractor opted for
the masonry block, there would have been a minimal increase over the original
design to cover the need for 12" deep rather than 8" deep block for the lower two
— - --- - ,,,.. r "I
SAUERS ENGINEERING Sao 2SS SSS4 10/10/02 10:50am P. 00Y
to three feet of the wall. The contractor informed us that he preferred cast-in-
place as it would be faster and more cost effective than the masonry block. We
do not see any reason why the cast-in-place walls would result in additional cost.
3. Having the building act as a retaining wall did require additional backfill and
drainage around the building and waterproofing of the retaining walls. We would
agree that this is extra work.
4. Much of the contractor's extra charges are associated with excavation and rock
removal. The original plans indicated there would be excavation for the pump
station building as well as excavation and construction of a driveway between the
new building and the existing tank access. This included any rock encountered
during excavation. As a result of the building relocation, the driveway was
eliminated. From the original plans, we estimated the amount of excavation for
the building and driveway and compared it to our estimate of the actual volume of
excavation. We determined that as a result of the new building location, the
amount of excavation increased by approximately 30%. We would agree that
30% of the cost of excavation and rock removal would be extra work.
5. Other items in the proposed change order included additional ductile iron spools
and the relocation of dumpsters (garbage can enclosures). The pipe spools were
needed to accommodate the discharge manifold being deeper under the station
floor as a result of the new building and meter vault locations. We would agree
that pipe spools and dumpster relocation are extra work.
I am waiting for the contractor's certified payroll reports to verify the hours and wages
shown on the proposed change order invoices. At this point, I would not recommend
approval of the proposed change order as submitted by the contractor. I would
recommend approval of extra work not to exceed $14,700.
Your ruly,
0
Keith Knibb, Project Engineer