HomeMy WebLinkAbout5 6160 Bridge Street Tank Change Order TDPUD MEMORANDUM
August 16, 2002
TO: Board of Directors
FROM: Neil Kaufman, Water System Engineer
SUBJECT: BRIDGE STREET 6160 TANK
CHANGE ORDER #1
AGENDA #
BACKGROUND:
The Board of Directors previously awarded the Contract for construction of the Bridge
Street 6160 Tank to CB&I Water(CBI). CBI commenced work at the site on July 15, 2002.
At that time, CBI began tree removal and processing and screening of the spoils materials
located in the old Quarry site. After removal of the trees, CBI was unable to begin
excavation of the storage tank pad since the Lahontan Regional Water Quality Control
Board had not yet issued a Waiver of Waste Discharge.
Upon completion of the tree removal and spoils processing, they began construction of the
detention basin. Construction of the detention basin was not a critical path item, but it was
the only remaining work that could be performed without the Waiver. The detention basin
was completed on August 1 and CBI stopped work at that time since the Waiver of Waste
Discharge still had not received by the District and there was no other work that could be
performed without the Waiver. The Waiver of Waste Discharge was received on Friday,
August 9 and CBI recommenced work on Monday, August 12.
The critical path task for completion of the storage tank is the coating of the tank interior.
Application of the coating is temperature sensitive and CBI had originally planned to begin
coating the tank on September 18 as shown on the attached baseline schedule.
In order to recover the lost time and ensure that the tank can be coated in September, CBI
has developed a revised schedule based on working 12 hour days for 7 days a week. This
revised schedule is also attached. This schedule will incur significant amounts of overtime
charged for project labor. CBI has determined this additional cost to be $142,887.00.
RECOMMENDATION:
I recommend that the Board authorize Contract Change Order #1 in the amount of
$142,887.00.
Attachments - Contract Change Order#1
CBI Memo
CBI Letter
Baseline Schedule
Revised Schedule
FILE No.084 08/16 '02 14:06 ID:CBMTrusco FAX: PAGE 4i 4
ua 16-8002 10:46aa From-TRUCKEE DONNER PUD +53D5871188 T-868 P.00Z/DOZ F-353
- Change Order
Contmat Name: BRIDGE STREET 616D TANK
Contract Change Order NO: 1 Ong.Contract Amt. $ 1126 0000.00 Days NA
Date: August 16,2002 _ Prev. Apprd Changes$ 0.00 Days NA
Contractor CEt&I Water This Change$ 142,887.00 Days NA
Revised Contract Amt.$ 1,405,887.00 Days NA
This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct,
furnish equipment a lump sum Price agreed upon between the Contractor and Distrire�quirad to complete the Change Order
Items
Increase in (Decrease) Contract Time
Contract In Contract Extension
Description of Changes Amount Amount $ da
Additional ovenima labor charges to be incurred In order to $142,887.00 NA
recover the project schedule due to delays in receiving the
necessary permits.
Total $142,887.00
Not change in contract amount (increase or decrease) $142,687.00
The amount of the Contract will be increased by the sum of $142,887.00 and the Contract Time shall not be
extended, The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the
contract price specified for each clam including any and all supervision costs and other miscellaneous costs relating
to the change in work, and as to the extension of time allowed, If any,for completion of the entire work on account
of sold Change Order, The Contractor agrees to furnish a materials
and requiredor complete the other ceChangeary
work inclusive of the directly or Indirectly related to the approved time extension,
order items. This document will become effective supplement e when aggro ed contract
the d all
licptrovisions will apply hereto. it is
understood that the Change
Accepted: —�� /Contractor Date: �✓
(Signature)
Approved: /Distrlet Date:
(Signature)
FILE No.082 08/15 '02 17:07 ID:CKITrusoo FAX PAGE Si 1
a a
IS
Water
a DIYWQB of Ca&I CGROMtOrs Inr.
4388 Santa Fa Road Fax
San Luis Obispo,CA.93401
( 5 4-iios 9155 Fax(805)5464105
To: Truckee Donner PUD
Awu Neil Coffman From: Wade Crosno
Fax: 630 5875056 Pages Including Cover. 1
phones 530-587-3896 Date: 8t16102
Res Add cost Accelerated Schedule based on permit delay
E7 urgent x For Review ❑Please Comment ❑ Please Reply E] Plsase Recycle
This is a change request for an accelerated schedule to make up days for the delay of the permit.
Means to make up time from the delay are as follows:
We have based our overtime premiums on the site work on working 7-12 hour days, Sundays will be
with a partial crew cutting slopes to minimize the double time required on Sundays and Holidays. We
have included working 10 hours per day 5 days per week and have only included for time outside this
time.
We have based our overtime on piping on working 6-12 hour days,Monday to Saturday. We had
based our original bid on working a 40-hour work week for the piping.
We have based our overtime on the ring wall on working 7-12 hour days. We had based our original
bid on working a 50-hour work week on the ring wall.
We have not addressed the final grading and paving as it will depend on the availability of AC Concrete
at the time work will be done.
We have not allowed working on tabor Day as by Law we can only work this day in the case of
an-targency.
We will perform the tank erection with two crews and two superintendents working 4 days on 4days off
alternating crews. We will be working 10 hour days. Overtime rates will be accounted for on Saturday
and Sunday. Painting will be staffed in the same manner as the tank erection. It will be necessary for
the tank and paint crews to be increase in size be 1 man each.
Additional coordination will be required between RSH and CB✓?<I due to access and working in the same
areas on the shortened schedule.
The added cost to accelerate the schedule will be $142,887.00 Please give me a call if you have any
questions.
FILE No.085 08/16 '02 14:45 ID:CKITrusco FAH: PAGE li l
CB&I Trusco Tank
a division of CB&7 Constructors./no.
4388 Santa Fe Road(9 34 01-81 58)
P.O.Box 12210
San Luis Obispo.CA 93406-2210
August 16, 2002 $055449155
FAX: 805 546 8105
Website: www,chicagabridge.com
Mr. Neil Kaufman
Truckee Donner Public Utility District
Re: Change order number 1, Schedule acceleration
Neil:
With the acceptance of change order number one, approving the accelerated schedule
(permit delayed schedule) to finish Contracted Work at the site by October 31, 2002 plus
5 days cure time for the tank paint and 1 day for disinfection of the tank. This schedule
does not take into consideration any unforeseen acts of nature such as rain, snow, or
severe amounts of rock. The only additional costs that have not been addressed would be
the additional trucking of AC if the AC: plant closes early.
If for any reason the contract is pushed into next year, the cost of change order I will be
deducted from the $200,000 associated with the accelerated bid schedule. The only
additional money that would be expected is a negotiated portion of the difference of the
$200,000 and change order No.1, approximately $ 57,000.
Sincerely,
Wade Crosno
Project Manager
Truckee 1.5 MG Water Tank&Site Work
Truckee Donner PUD gASE�IRIE SCHEDULE
Trusco Tank i a
Jul Aug Sep Oct
ID Task Name/Description Start Finish Duration 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13
1 Customer Tasks Tue 1/9/02 1 Thu 10131102 83 days 9
I
2 Award Contract Tue 719102 Tue 7/9/02 0 days # 719
3 Provide Vital Information Tue 719102 Wed 7/10/02 2 days 19 137110
4 Approve Drawings Mon 7/15102 Tue 7123102 7 days 71
15= 712.3
5 Tumover Site Tue 719/02 Tue 7/9102 0 days 1719
6 Supply Test Water Tue 10129102 Wed 10130102 2 days i 1
7 Accept Job Thu t0/31/02 Thu 10131102 0days
E
8 Engineering Tasks Tue 719102 Fri 7112102 4 days 9 # 7/12
11 Material Procurement Wed 7110/02 Fri 819102 23 days 0 8/9
16 Shop Fabrication Fri 7126/02 Mon 8119102 16 days 7/26 ^ 8t19
I
23 Shop Paint Mon 7129102 Mon 9/2102 26 days .7129 1912
i
33 Ship Components 8 Tools Mon 815102 Tue 913IO2 22 days ,, 8f5 913
41 Subcontracts Mon 7/16/02 Fri 819/02 20 days 115 819
43 Tank Erection Mon 8/12/02 Tue 9I17IO2 27 days 8112 9117
1
50 Field Paint Wed 9118/02 Wed 10/23/02 26 days 9/18
55 Cure Interior Thu 10/24/02 Wed 10/30/02 5 days 1012
56 DisinfectJTest Thu 10/31/02 Thu 10/31/02 1 day I 1
V
Task Rolled Up Progress -
Project:draft template Milestone Project Summary
Date:Fri 7112102 Summary ^ External Milestone
Rolled Up Task Deadline
Page 1
I.5 MG Core roof Tank ---------------------------------------
Truckee Donner PUD REVISED SCHEDULE
®Trusco Tank
Jul Aug Sep Oct No
10 Task NameMescriPliOn Start Finish Predecessor Success Duration 30 T 1421 28 4 11 18 25 1 a 15 2229 6 132027 3
Thu ,I"U. 111 2 85 days it
I customer Tasks
AWaTU COnbact Thu 7111/02 Thu 1/1 IM2 +3 days 0 days 71 1
3 Provide VBaf lnlormation ---TFu—7/ffA2 Ffi 7/12h72 2 10 2 days (II'!71.2
10 15 10 days 7118 7131
4 APPIRM OfflWrIgS aw Wed 7YWA2
5 Turnarinorlilte u 7JI1102 717111102 2 51 0 days wit
101,111 lorl
'rue ICVIA* Tue laVIIIAMM2 56
6 Supply, lost Water 4 Pip
Accept Job fNon 1114)02 won 1114102
63
1
8 Engineering Tasks u 7111102 Wed 7117102 6 71117
tT— Material Procurement Fr17N2r02, Fri 11116102 27daya 12tl a(I
i
IS Shop Fabrication Tue V30102 Man f 20 days i30
Shop—Paint 02 30 days I
d 7131102 Mon LL 23
33 Shfp CompaneMs&Taola Wedar7l02 Tue 91I0ID2
Tue 7116d102 U
41 Subcontracts
42 Holding POrtdiNon Critical path work Tue 7/16102 Wed 713 W2
43 Waiting for permit rue 7116102 Fri BOOM-'I
44 Demobilization due to no permit
45 Rennobilizatiori�Ulpmefft t wwo 4 days
it 811010
8126.
S;
—Mon 91
Excavation Wed Oil III
o 46 13 days
0
2
ys- 91
In • Too W7102 Marr9002. 41-bi�3 Us 7 days ZY;
47 Foundation
Wed 6f02 Tue WIS102 36 days 1018
48 Pipeline16125 Aw
al 10rhM2 Thu 101`31102 5 days
Paving t
Tue 913102 Man W10102 28 days gw/3
Tank Erection
Sal l0i26,102 26 days
57 Field Paint Tue 1011102
co 6-2 cure interior
Moll 1012=2 Fri 111V02 59,61 63 5 days Man 11/4102 Moll 1114102 -9,62 I day, 7 1
Distrifect/Test
Project Summary
C\j Task Rolled Up Task
External Milestone
Split ............ Rolled Up Split ......
Prc)ect. Prog
draft template Rolled Up Milestone 0 Deadline
ress
00 Dow.Fri 8116102
CD Milestone Rolled Up Progress nommon�
It
CD
00 Summary external Tasks
Page I
LOU
-j
LL