HomeMy WebLinkAbout5 6160 Bridge Street Tank Change Order TDPUD MEMORANDUM August 16, 2002 TO: Board of Directors FROM: Neil Kaufman, Water System Engineer SUBJECT: BRIDGE STREET 6160 TANK CHANGE ORDER #1 AGENDA # BACKGROUND: The Board of Directors previously awarded the Contract for construction of the Bridge Street 6160 Tank to CB&I Water(CBI). CBI commenced work at the site on July 15, 2002. At that time, CBI began tree removal and processing and screening of the spoils materials located in the old Quarry site. After removal of the trees, CBI was unable to begin excavation of the storage tank pad since the Lahontan Regional Water Quality Control Board had not yet issued a Waiver of Waste Discharge. Upon completion of the tree removal and spoils processing, they began construction of the detention basin. Construction of the detention basin was not a critical path item, but it was the only remaining work that could be performed without the Waiver. The detention basin was completed on August 1 and CBI stopped work at that time since the Waiver of Waste Discharge still had not received by the District and there was no other work that could be performed without the Waiver. The Waiver of Waste Discharge was received on Friday, August 9 and CBI recommenced work on Monday, August 12. The critical path task for completion of the storage tank is the coating of the tank interior. Application of the coating is temperature sensitive and CBI had originally planned to begin coating the tank on September 18 as shown on the attached baseline schedule. In order to recover the lost time and ensure that the tank can be coated in September, CBI has developed a revised schedule based on working 12 hour days for 7 days a week. This revised schedule is also attached. This schedule will incur significant amounts of overtime charged for project labor. CBI has determined this additional cost to be $142,887.00. RECOMMENDATION: I recommend that the Board authorize Contract Change Order #1 in the amount of $142,887.00. Attachments - Contract Change Order#1 CBI Memo CBI Letter Baseline Schedule Revised Schedule FILE No.084 08/16 '02 14:06 ID:CBMTrusco FAX: PAGE 4i 4 ua 16-8002 10:46aa From-TRUCKEE DONNER PUD +53D5871188 T-868 P.00Z/DOZ F-353 - Change Order Contmat Name: BRIDGE STREET 616D TANK Contract Change Order NO: 1 Ong.Contract Amt. $ 1126 0000.00 Days NA Date: August 16,2002 _ Prev. Apprd Changes$ 0.00 Days NA Contractor CEt&I Water This Change$ 142,887.00 Days NA Revised Contract Amt.$ 1,405,887.00 Days NA This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct, furnish equipment a lump sum Price agreed upon between the Contractor and Distrire�quirad to complete the Change Order Items Increase in (Decrease) Contract Time Contract In Contract Extension Description of Changes Amount Amount $ da Additional ovenima labor charges to be incurred In order to $142,887.00 NA recover the project schedule due to delays in receiving the necessary permits. Total $142,887.00 Not change in contract amount (increase or decrease) $142,687.00 The amount of the Contract will be increased by the sum of $142,887.00 and the Contract Time shall not be extended, The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each clam including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, If any,for completion of the entire work on account of sold Change Order, The Contractor agrees to furnish a materials and requiredor complete the other ceChangeary work inclusive of the directly or Indirectly related to the approved time extension, order items. This document will become effective supplement e when aggro ed contract the d all licptrovisions will apply hereto. it is understood that the Change Accepted: —�� /Contractor Date: �✓ (Signature) Approved: /Distrlet Date: (Signature) FILE No.082 08/15 '02 17:07 ID:CKITrusoo FAX PAGE Si 1 a a IS Water a DIYWQB of Ca&I CGROMtOrs Inr. 4388 Santa Fa Road Fax San Luis Obispo,CA.93401 ( 5 4-iios 9155 Fax(805)5464105 To: Truckee Donner PUD Awu Neil Coffman From: Wade Crosno Fax: 630 5875056 Pages Including Cover. 1 phones 530-587-3896 Date: 8t16102 Res Add cost Accelerated Schedule based on permit delay E7 urgent x For Review ❑Please Comment ❑ Please Reply E] Plsase Recycle This is a change request for an accelerated schedule to make up days for the delay of the permit. Means to make up time from the delay are as follows: We have based our overtime premiums on the site work on working 7-12 hour days, Sundays will be with a partial crew cutting slopes to minimize the double time required on Sundays and Holidays. We have included working 10 hours per day 5 days per week and have only included for time outside this time. We have based our overtime on piping on working 6-12 hour days,Monday to Saturday. We had based our original bid on working a 40-hour work week for the piping. We have based our overtime on the ring wall on working 7-12 hour days. We had based our original bid on working a 50-hour work week on the ring wall. We have not addressed the final grading and paving as it will depend on the availability of AC Concrete at the time work will be done. We have not allowed working on tabor Day as by Law we can only work this day in the case of an-targency. We will perform the tank erection with two crews and two superintendents working 4 days on 4days off alternating crews. We will be working 10 hour days. Overtime rates will be accounted for on Saturday and Sunday. Painting will be staffed in the same manner as the tank erection. It will be necessary for the tank and paint crews to be increase in size be 1 man each. Additional coordination will be required between RSH and CB✓?<I due to access and working in the same areas on the shortened schedule. The added cost to accelerate the schedule will be $142,887.00 Please give me a call if you have any questions. FILE No.085 08/16 '02 14:45 ID:CKITrusco FAH: PAGE li l CB&I Trusco Tank a division of CB&7 Constructors./no. 4388 Santa Fe Road(9 34 01-81 58) P.O.Box 12210 San Luis Obispo.CA 93406-2210 August 16, 2002 $055449155 FAX: 805 546 8105 Website: www,chicagabridge.com Mr. Neil Kaufman Truckee Donner Public Utility District Re: Change order number 1, Schedule acceleration Neil: With the acceptance of change order number one, approving the accelerated schedule (permit delayed schedule) to finish Contracted Work at the site by October 31, 2002 plus 5 days cure time for the tank paint and 1 day for disinfection of the tank. This schedule does not take into consideration any unforeseen acts of nature such as rain, snow, or severe amounts of rock. The only additional costs that have not been addressed would be the additional trucking of AC if the AC: plant closes early. If for any reason the contract is pushed into next year, the cost of change order I will be deducted from the $200,000 associated with the accelerated bid schedule. The only additional money that would be expected is a negotiated portion of the difference of the $200,000 and change order No.1, approximately $ 57,000. Sincerely, Wade Crosno Project Manager Truckee 1.5 MG Water Tank&Site Work Truckee Donner PUD gASE�IRIE SCHEDULE Trusco Tank i a Jul Aug Sep Oct ID Task Name/Description Start Finish Duration 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 1 Customer Tasks Tue 1/9/02 1 Thu 10131102 83 days 9 I 2 Award Contract Tue 719102 Tue 7/9/02 0 days # 719 3 Provide Vital Information Tue 719102 Wed 7/10/02 2 days 19 137110 4 Approve Drawings Mon 7/15102 Tue 7123102 7 days 71 15= 712.3 5 Tumover Site Tue 719/02 Tue 7/9102 0 days 1719 6 Supply Test Water Tue 10129102 Wed 10130102 2 days i 1 7 Accept Job Thu t0/31/02 Thu 10131102 0days E 8 Engineering Tasks Tue 719102 Fri 7112102 4 days 9 # 7/12 11 Material Procurement Wed 7110/02 Fri 819102 23 days 0 8/9 16 Shop Fabrication Fri 7126/02 Mon 8119102 16 days 7/26 ^ 8t19 I 23 Shop Paint Mon 7129102 Mon 9/2102 26 days .7129 1912 i 33 Ship Components 8 Tools Mon 815102 Tue 913IO2 22 days ,, 8f5 913 41 Subcontracts Mon 7/16/02 Fri 819/02 20 days 115 819 43 Tank Erection Mon 8/12/02 Tue 9I17IO2 27 days 8112 9117 1 50 Field Paint Wed 9118/02 Wed 10/23/02 26 days 9/18 55 Cure Interior Thu 10/24/02 Wed 10/30/02 5 days 1012 56 DisinfectJTest Thu 10/31/02 Thu 10/31/02 1 day I 1 V Task Rolled Up Progress - Project:draft template Milestone Project Summary Date:Fri 7112102 Summary ^ External Milestone Rolled Up Task Deadline Page 1 I.5 MG Core roof Tank --------------------------------------- Truckee Donner PUD REVISED SCHEDULE ®Trusco Tank Jul Aug Sep Oct No 10 Task NameMescriPliOn Start Finish Predecessor Success Duration 30 T 1421 28 4 11 18 25 1 a 15 2229 6 132027 3 Thu ,I"U. 111 2 85 days it I customer Tasks AWaTU COnbact Thu 7111/02 Thu 1/1 IM2 +3 days 0 days 71 1 3 Provide VBaf lnlormation ---TFu—7/ffA2 Ffi 7/12h72 2 10 2 days (II'!71.2 10 15 10 days 7118 7131 4 APPIRM OfflWrIgS aw Wed 7YWA2 5 Turnarinorlilte u 7JI1102 717111102 2 51 0 days wit 101,111 lorl 'rue ICVIA* Tue laVIIIAMM2 56 6 Supply, lost Water 4 Pip Accept Job fNon 1114)02 won 1114102 63 1 8 Engineering Tasks u 7111102 Wed 7117102 6 71117 tT— Material Procurement Fr17N2r02, Fri 11116102 27daya 12tl a(I i IS Shop Fabrication Tue V30102 Man f 20 days i30 Shop—Paint 02 30 days I d 7131102 Mon LL 23 33 Shfp CompaneMs&Taola Wedar7l02 Tue 91I0ID2 Tue 7116d102 U 41 Subcontracts 42 Holding POrtdiNon Critical path work Tue 7/16102 Wed 713 W2 43 Waiting for permit rue 7116102 Fri BOOM-'I 44 Demobilization due to no permit 45 Rennobilizatiori�Ulpmefft t wwo 4 days it 811010 8126. S; —Mon 91 Excavation Wed Oil III o 46 13 days 0 2 ys- 91 In • Too W7102 Marr9002. 41-bi�3 Us 7 days ZY; 47 Foundation Wed 6f02 Tue WIS102 36 days 1018 48 Pipeline16125 Aw al 10rhM2 Thu 101`31102 5 days Paving t Tue 913102 Man W10102 28 days gw/3 Tank Erection Sal l0i26,102 26 days 57 Field Paint Tue 1011102 co 6-2 cure interior Moll 1012=2 Fri 111V02 59,61 63 5 days Man 11/4102 Moll 1114102 -9,62 I day, 7 1 Distrifect/Test Project Summary C\j Task Rolled Up Task External Milestone Split ............ Rolled Up Split ...... Prc)ect. Prog draft template Rolled Up Milestone 0 Deadline ress 00 Dow.Fri 8116102 CD Milestone Rolled Up Progress nommon� It CD 00 Summary external Tasks Page I LOU -j LL