HomeMy WebLinkAbout5 Glenshire pipeline Project ER
. ,I,R�lic Utility�a! • ��
Memorandum
To: Board of Directors
From: Ed Taylor, Water Utility Manager
Date: 6-23-2002
Subject: Authorization to bid for the Glenshire Pipeline Project.
BACKGROUND:
The design and all planning for the Glenshire Pipeline Project are complete. The project
plans, specifications, and contract documents are complete for the Glenshire Pipeline
Project.
We are now asking authorization to advertise for, accept and open bids for the Glenshire
Pipeline Project with a bid opening date of August 1, 2002.
RECOMMENDATION:
1 recommend that the Board authorize staff to advertise for, accept and open bids for the
Glenshire Pipeline Project with a bid opening date of August 1, 2002.
0 Page 1