HomeMy WebLinkAbout7 Falcon Point Change Order TDPUD MEMORANDUM
June 28, 2002
TO: Board of Directors
FROM: Ed Taylor, Water Utility Manager
SUBJECT: FALCON POINT CHANGE ORDER #1
AGENDA # 7
BACKGROUND:
The Board of Directors at the May 1, 2002 meeting awarded the Falcon Point Booster
Station Project contract to Longo Construction, Inc. We are requesting a change order
to the contract.
The design for the Falcon Point Booster Station was based off of the as built drawings
provided by Dart. The as built drawings were for the construction of the Falcon Point
Tank. The design was completed during the winter months when snow prevented the
site from being surveyed to determine the tank location. The site was surveyed and the
tank location was 3 feet different than the as built drawings had indicated.
The redesigned pump station will require additional excavation and additional concrete
wall construction. Staff and Longo Construction Inc. are reviewing the changes and will
have the results completed Tuesday, July 2, 2002.
RECOMMENDATION:
I recommend that the Board approve Contract Change Order#1.
Attachment-none at this time. Proposal to be distributed at meeting July 3, 2002.