HomeMy WebLinkAboutRES 1989-19 - Board RESOLUTION NO. 89/
OF THE
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
APPROVING SPECIFICATIONS AND CALLING FOR
BIDS ON GARAGE HEATERS
WHEREAS, the Board of Directors of the Truckee Donner Public
Utility District has determined the need to purchase and install
heaters in the garages; and
WHEREAS, funds have been set aside in the 1989 budget for this
purpose;
NOW, THEREFORE, BE IT RESOLVED that the Board of Directors of the
Truckee Donner Public Utility District does hereby authorize the
President to issue a call for bids based on the specifications
attached hereto, and that the date and time established for the bid
opening is Wednesday, August 16, 1989 at 2: 00 P.M.
PASSED AND ADOPTED by the Board of Directors of the Truckee Donner
Public Utility District at a regular meeting thereof duly called
and held in the District on the 1989 by the following
roll call vote:
AYES: .¢lydt.e.9 Co.L'��rT SvTTb^% �t/.s�i�-c- /yJA.9ss.
NOES: ivoivE
ABSENT:NGiv6.
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
By k-<3e� -
Jam&s A. Maass, President
ATTES /
4 L,
usan M. Craig, Deput District Clerk
smc
BID LIST
RADIANT HEATERS FOR GARAGES
Bid opening - 2:00 P.M. , August 16, 1989
Climate Control
5480 Highway 50 East
Carson City, NV 89706
Howard Kerr 882-8427
Paul 's Plumbing
1808 Frazer Avenue
Sparks, NV 89431
Brad or Shirley 359-8800
D & D Plumbing
P. O. Box 3257
Sparks, NV 89432
Bob Marshall 358-2378
Crane Plumbing
1555 Pittman Avenue
Sparks, NV 89431
Steve 355-8555
Gardner Plumbing
311 No. Park
Reno, NV 89512
Jeff 329-1017
Truckee Donner Public Utility District
Post Office Box 309 • 11570 Donner Pass Road • Truckee, California 95734
General Manager (916)587-3896 Board of Directors
Peter L. Holzmeister Joseph R.Aguera
John L. Corbett
James A. Maass
Patricia S. Sutton
Karen F.White
July 25, 1989
Prospective Bidders:
Notice is hereby given to prospective bidders that sealed bids will
be received by the Truckee Donner Public Utility District until
2 : 00 P.M. on Wednesday, August 16, 1989 for installing radiant
heating systems for the District's vehicle maintenance garages as
detailed in the attached plans and specifications. If you have any
questions about the specifications, please contact Tom Buckhouse,
Electrical Engineer, at the number above.
The Truckee Donner Public Utility District specifically reserves
the right to reject any and all bids, waive irregularities or
informalities in any or all bids, be the sole judge of the
�-� suitability of the items offered, and to accept any bid that it
determines to be in its best interest.
Very truly yours,
Peter L. Holzmeister
General Manager
smc
Enclosures
cc: T. Buckhouse, Electrical Engineer
FORM OF PROPOSAL
RADIANT HEATING SYSTEMS
FOR VEHICLE MAINTENANCE GARAGES
Bid opening - 2: 00 P.M. - Wednesday, August 16, 1989
The undersigned hereby certifies that he has read the plans,
specifications and contract documents and hereby submits a bid for
providing and installing radiant heating systems for the Truckee
Donner Public Utility District's vehicle maintenance garages in
accordance with those documents.
Bid amount $
Total bid (in words)
The bid price shall remain in effect for a period of 60 calendar
days from the date of the bid opening.
If the bid is awarded to me I agreed to complete the project within
three months from the date the notice to proceed is received.
LIST OF SUPPLIERS/SUB-CONTRACTORS (names and addresses)
Name, address and telephone number of bidder:
RADIANT HEATING SYSTEMS
FOR THE TDPUD VEHICLE MAINTENANCE GARAGES
This agreement is made this day of 1989,
at Truckee, Nevada County, California, by and between the TRUCKEE
DONNER PUBLIC UTILITY DISTRICT and
(Contractor) .
In consideration of the mutual covenants and conditions hereinafter
set forth, owner and contractor hereby agree as follows:
1) STATEMENT OF WORK
The project is fully described in the plans and specifications
attached hereto.
2) CONTRACT PRICE
The District shall pay contractor the amount of $ for
performance of this project.
3) PAYMENT
Payment will be made by the loth of the month following completion
of work and receipt of invoice by the District.
4) GUARANTEE
Contractor shall guarantee all work done under the contract for a
period of one year from the date of completion of the project.
Should the workmanship or materials prove defective in the opinion
of the District, the work shall be removed and replaced at the
Contractor's expense.
5) COMPENSATION INSURANCE
The Contractor shall procure and shall maintain during the life of
the contract, Workmen's Compensation Insurance for all of his
employees to be engaged in work. In case of any such work sublet,
the Contractor shall require the subcontractor similarly to provide
Workmen's Compensation Insurance for all of the latter's employees
to be engaged in such work unless such employees are covered by the
protection afforded by the Contractor's Workmen's Compensation
Insurance.
1
6) PUBLIC LIABILITY AND PROPERTY DAMAGE INSURANCE
Contractor shall furnish satisfactory proof, by certificate
presented to the District within ten days of the date of the
contract, that he has public liability and property damage
insurance. The insurance shall protect both the Contractor and the
District, its officers a/d/or agents against loss from all
liabilities imposed by law, and shall be maintained in full force
and effect during the performance of the contract and in the
following amounts:
a) Limit of liability for personal injury or accidental
death - one person, $500,000; aggregate liability per
accident, $1, 000, 000.
b) Limit of liability for property damage - one
occurrence, $50, 000; aggregate liability for loss per
accident, $100,000.
7) NOTICE TO PROCEED
Contractor shall complete the project within three months from the
date the notice to proceed is received.
8) ADJUSTMENT OF DISPUTE
All questions or controversies which may arise between the
Contractor and the District under or in reference to this contract
shall be subject to the decision of some competent person to be
agreed upon by the District and the Contractor who shall act as
referee, and his decisions shall be final and conclusive upon both
parties. Should the District and the Contractor be unable to agree
upon a referee, a board of three arbitrators shall be chosen, one
by the District, one by the Contractor, and the third by the two
so chosen, and the decision of any two of said arbitrators shall
be final and binding upon the parties. If either party to the
contract neglects or fails for a period of ten days after notice
from the other party to designate an arbitrator hereunder, the
arbitrator designated by the other party shall have full power to
decide the dispute in the same manner as though a board of three
arbitrators had been selected. The referee or arbitrators shall
decide which party shall pay the cost of referral or arbitration.
2
f
9) SERVICE OF NOTICES
All notices required to be given hereunder shall be mailed or
delivered to the addresses shown under the District's and
Contractor's signatures at the end of this contract.
10) EXTRA WORK
Any alteration or deviation from this contract involving extra
costs will be executed only upon written notice and will become an
extra charge over and above the bid amount.
By
Contractor
Address -
Phone
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
By
Peter L. Holzmeister, General Manager
P. 0. Box 309 - 11570 Donner Pass Road
Truckee, CA 95734
(916) 587-3896