HomeMy WebLinkAboutRES 1995-21 - Board RESOLUTION NO. 9521
OF THE
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
ACCEPTING THE ROUTE 801891267 SEPARATION UTILITY CONSTRUCTION
PROJECT AS COMPLETE AND DIRECTING THE'FILING'OF THE NOTICE OF
COMPLETION
WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the
determination to construct access ways and block-outs for future pipelines through the
Route 80/89/267 separation structure; and
WHEREAS, the Contract was awarded to BENCO Contracting and Engineering, Inc.,
9886 Kent Street, Elk Grove, California 95624, and the contractor entered into an
agreement with the District to perform the work; and
WHEREAS, the District's Consulting engineer, Sauers Engineering, Inc., has inspected
the completed work and recommended that it be accepted by the District,
NOW, THEREFORE, BE IT RESOLVED by the Board of Directors of the Truckee Donner
Public Utility District as follows:
1. That the District hereby accepts the Route 801891267 Separation Utility Construction Project
as complete.
2. That the Clerk of the District be directed to file with the County of Nevada the Notice of
Completion, a copy of which is attached hereto.
3. That 35 days following the filing of the Notice of Completion, the 10% retained from the
contractor payments be released to the contractor if no claims have been made to the District
by material suppliers or laborers.
PASSED AND ADOPTED by the Board of Directors of the Truckee Donner Public Utility
District at a meeting duly called and held within said District on the seventh day of August
1995 by the following roll call vote:
AYES: Aguera, Hemig, Maass and Jones.
NOES: None.
ABSENT: Sutton.
TRUCKKEE DONNER PUBLIC UTILITY DISTRICT
By NL
Peter L. Holzmeist r, Cierk/Ex-officio Secretary
M A L
Z:
Susan M. Craig, Deputy District Jerk
smc
• RECORDING REQUESTED BY:
Truckee Donner Public Utility District
WHEN RECORDED, RETURN TO:
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
Post Office Box 309
Truckee, CA 96160
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN:
1. That the name and address of the public entity for whom the improvement project was
done, as owner thereof, is the TRUCKEE DONNER PUBLIC UTILITY DISTRICT, Post
Office Box 309, Truckee, CA 96160.
2. That on August 7, 1995 the hereinafter described improvements were accepted as
completed pursuant to a resolution of the Truckee Donner Public Utility District, the
awarding authority.
3. That the subject improvements of the Notice are generally described and identified as
follows: Route 80/89/267 Separation Utility Construction Project.
4. That the name of the contractor for such project was: BENCO Contracting and
Engineering, Inc., 9888 Kent Street, Elk Grove, California 95624.
Dated: e �� �99_s— TRUCKEE DONNER PUBLIC UTILITY DISTRICT
B I& 114)�Peter L. Ho z General Manager
STATE OF CALIFORNIA
COUNTY OF NEVADA
On before me, Susan M. Craig, personally appeared PETER L. HOLZMEISTER, personally
kno to a to be the person whose name is subscribed to the within instrument and acknowledged to me that
he executed the same in his authorized capacity, and that by his signature on the instrument the person or the
entity upon behalf of which the person acted, executed the instrument.
Capacity claimed by signer: Corporate officer- Clerk/Ex-officio Secretary of the Truckee Donner Public Utility
District.
Witness and aI
official al.
• L 808AN M.=Oaf
s Cot�s�t.� _
Susan M. Craig, Notary ! 4 Pkf N COUNTY
My Comm.Eq*es MAY 29.1997