HomeMy WebLinkAboutRES 1998-02 - Board RESOLUTION NCB. 9802
OF: THE , .
TRUCKEE DONNER PUBLIC:UTILITYDISTRICT
D/RECTINO VAT COMPETITIVE BIDD/NO BE DISf'El1[SED,WITH/N CONNECTION
WITH TNE DISTRICT'S;PURCNASE CIF A REBUILT TRANSFORMER
WHEREAS, within the past seven months, two transformers located in the Tahoe Donner substation
required emergency repairs to avoid future catastrophic failures, and
WHEREAS, one of the transformers is still being repaired and the District does not expect to receive
and place in service the transformer until approximately April 15, 1998, and
WHEREAS, the transformer enables the District to provide electricity to customers located in the
Tahoe Donner Subdivision; and
WHEREAS, without the transformer in the Tahoe Donner substation, the District could only serve
customers in the Tahoe Donner Subdivision by re-routing electrical load from other substations and
would result in severe stresses in other portions of the electrical system and significantly increase
the likelihood of additional failures and problems in the electrical system; and
WHEREAS, during the time that the transformers have been repaired, the District has been able to
... provide electrical service to its customers through a series of re-routing loads and the use of
temporary replacement transformers; and
WHEREAS, the District's temporary solution for the failed transformers is not a long term solution
because the load handled by the Tahoe Donner substation is causing the Tahoe Donner substation
to perform at near capacity, and
WHEREAS, it is possible to re-route some of the load necessary for Tahoe Donner customers
through the remaining substations, but it is not feasible to handle peak electric demand periods
without the Tahoe Donner substation in operation; and
WHEREAS, the District went to bid and has contracted to purchase rive additional single phase
transformers for a cost of approximately$600,000 with delivery of the transformers to the District
scheduled approximately for July 1998, and
WHEREAS, since two of three transformers in the Tahoe Donner substation have failed, it is more
likely that the remaining transformer has been damaged and likely has a greater chance of failure,
and
WHEREAS, the District plans to begin inspection of the third Tahoe Donner transformer for damage
upon receiving the second rebuilt unit during April 1998, with the entire process requiring
approximately eight weeks from the April 1998 date; and
WHEREAS, it has been determined that, should one of the transformers or temporary replacement
transformers in the Tahoe Donner substation fail before either the new transformers or the
transformer under repair are received and placed into service, the District will be placed in a severe
emergency situation and will likely be unable to provide electricity to meet its peak demand periods;
and
WHEREAS, the District has located a rebuilt transformer for sale by U. S. Transformer
West, which meets the specifications required by the District and which could be used by
the District in three of its substations, for a cost of approximately$153,000, which includes
tax, delivery and a multi year warranty, and
WHEREAS, the rebuilt transformer could be delivered to the District within approximately
four to six weeks from the date of its purchase, and
WHEREAS, rebuilt or used transformers meeting the District's specifications rarely or
sporadically become available for purchase in the marketplace, and
MHEREAS, the District is aware of several companies which are in the business of
buying and selling used transformers and none of the companies currently has a
transformer meeting the District's specifications available for sale and could not provide a
bid to the District should it solicit bids for one;and
WHEREAS, the cost to purchase a new transformer, similar to the rebuilt one currently for
sale by U. S. Transformer West is approximately$350,000 and could not be delivered for
approximately 26-52 weeks;and
WHEREAS, the competitive bid process would be unavailing or would not produce an
advantage, and the advertisement for competitive bids would thus be undesirable or
impractical, or impossible because the rebuilt transformers meeting District specifications
are not currently available and rarely become available; and
WHEREAS, the Public Contract Code Section 20201 generally requires that the District
engage in competitive bidding on any expenditure in excess of$10,000, and
WHEREAS, it has been determined by District staff that failure of another transformer will '
place the District in a disastrous situation and at risk for not being able to provide electricity
at peak demand periods; and
WHEREAS, Public Contract Code Section 22050 provides that in the case of an
emergency, a public agency, pursuant to a four-fifths vote of the goveming body, may
repair or replace a public facility, take any directly related and immediate action required
by that emergency, and procure the necessary equipment services, and supplies for those
purposes, without giving notice for bids to let contracts, and
WHEREAS, the failure of two of the three transformers in the Tahoe Donner substation and
current use of all available back-up transformers during the height of the winter season has
created a great emergency which, pursuant to Public Contract Code 22050, is justification
for the District to dispense with the competitive bidding procedures for the purchase of the
rebuilt transformer.
WHEREAS, various Califomia court decisions, including Graydon v. Pasadena
Development Agency, 104 Cal.App.3d 631 (1980), hold that if the subject of a contract is
such that competitive proposals would be unavailing or would not produce an advantage,
and the advertisement for competitive bids would thus be undesirable or impractical, or
impossible, a public agency may dispense with competitive bidding; and
WHEREAS, for all of the reasons set forth above, competitive proposals would be
unavailing and would not produce an advantage, and the advertisement for competitive
bids would thus be undesirable, impractical, and impossible and engaging in a competitive
bidding process would cause the District to continue to operate in a near crises mode.
NOW, THEREFORE, BE IT RESOLVED that the Board of Directors adopts the above
recitals as its findings; and
BE IT FURTHER RESOLVED by the Board of Directors that for the reasons set forth
above, the District finds that the recent failures of the transformers in the Tahoe Donner
substation and the temporary repair solutions have created an emergency and that the
emergency will not permit a delay resulting from a competitive solicitation for bids, and that
a repair of the faulty transformer is necessary to respond to the emergency.
BE IT FURTHER RESOLVED that for the reasons set forth above, competitive proposals
to purchase back-up transformer would be unavailing and would not produce an advantage,
and the advertisement for competitive bids would thus be undesirable, impractical and
impossible.
BE IT FURTHER RESOLVED that the District shall therefore dispense with competitive
bidding for the purchase of a rebuilt transformer which the District could use in the District's
substations.
BE IT FURTHER RESOLVED that the Board of Directors shall review the emergency action
at its next regularly scheduled meeting and, at every regularly scheduled meeting thereafter
until the action is terminated to determine whether there is a need to continue the action.
PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within
the District on the seventh day of January 1998 by the following roll call vote:
AYES: Aguera, Hemig, Jones, Sutton and Maass.
NOES: None.
4
ABSENT- None.
TRUCKEE DONNER PUB IC UTILITY DISTRICT a
By
Peter L H meiste , Clerk of the Board
ATT
Susan M. Craig, Deputy District gtiihk
smc