Ordinance No. 2001m02
Effecting a change in the electric connection fee schedule
WHEREAS, a review if the electrical connection fees has revealed an increase in costs over the
past several years;
NOW, THEREFORE, BE IT ENACTED by the Board of Directors of the Truckee Donner Public
Utility District as follows:
• Effective 30 days from the date this ordinance is adopted, the electric connection fees, a
copy of which is attached hereto as Exhibit A, shall go into effect and prior electric
connection fee schedules shall be rescinded.
• The Clerk of the Board is hereby directed to post and publish this ordinance in accordance
with state law.
PASSED AND ADOPTED by the Board of directors of the Truckee Donner Public Utility District at a
regular meeting thereof duly called and held within said District on the 1 e day of April 2001,by the
following roll call vote:
AYES: Aguera, Hemig and Maass.
NOES: Sutton.
ABSENT: Van Gundy.
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
B (A 9LV,t���
Jame .7ass, President of the Board
ATTE
Peter L. Holzmeister, Clerk of the Board
smc
i
Exhibit A
ELECTRIC CONNECTION FEES
Size and Type of Service Connection Fee
A. Single phase, 120/240 service
Three-wire overhead
Actual cost
1) Temporary
$1,100
2) Permanent connection to structure
$1,350
3) Temporary connection to customer-owned
power pole and subsequent transfer to
structure
B. Single phase, 120/240 service
Three-wire underground (overhead transformer)
1) Permanent connection to structure $1,100
. $1,350
2) Temporary connection to customer-owned
.power pole; removal of same and installation
of underground permanent service to
structure
C. Single phase, 120/240 service
Three-wire underground (padmount transformer)
1) Permanent connection to structure $1,100
2) Temporary connection to customer-owned $1,350
power pole; removal of same and installation
of underground permanent service to
structure