Ordinance No. 2003- 05
AMENDING THE ELECTRIC RETAIL RATES AND
AMENDING THE ELECTRIC CONNECTION CHARGES
WHEREAS District staff has prepared a budget for District operation for 2004; and
WHEREAS,on December 17,2003 a public hearing was held to receive comments from the public
concerning the 2004 budget; and
WHEREAS THE Board has adopted the budget for 2004; and
WHEREAS the budget for 2004 recommends that electric retail rates and electric connection
charges be increased to cover increases in costs of providing District services; and
WHEREAS on December 17, 2003 a public hearing was held to receive public commends on
proposed rate increases;
NOW, THEREFORE, BE IT ENACTED by the Board of Directors of the Truckee Donner Public
Utility District as follows:
Section 1. Effective 30 days from the date this ordinance is adopted the following monthly electric
rates shall be effective.
Domestic Electric Rates: Permanent Residents
Rate P 10
Customer Charge: per month $5.00
Energy Charge per kilowatt-hour $0.114
Domestic Electric Rates: Non-Permanent Residents
Rate S 10
Customer Charge: per month $5.00
Energy Charge per kilowatt-hour $0.130
Small Commercial Rates
Rate 15
Customer Charge: per month $9.70
Energy Charge per kilowatt-hour $0.137
Medium Commercial Rates
Rate 20
Customer Charge: per month $96.85
Energy Charge per kilowatt-hour $0.0811
Demand Charge per kilowatt of demand $11.11
1
Large Commercial Rates
Rate 25
Customer Charge: per month $425.00
Energy Charge per kilowatt-hour $0.0835
Demand Charge per kilowatt of demand $10.62
Section 2. Effective 30 days from the date this ordinance is adopted the following electric
connection charge schedule shall be effective.
ELECTRIC CONNECTION FEES
Size and Type of Service Connection Fee
A. Single phase, 120/240 service
Three-wire overhead
1) Temporary Actual cost
2) Permanent connection to structure $1,155
3) Temporary connection to customer-owned $1,418
power pole and subsequent transfer to
stru ctu re
B. Single phase, 120/240 service
Three-wire underground (overhead transformer)
1) Permanent connection to structure $1,155
2) Temporary connection to customer-owned $1,418
power pole; removal of same and installation
of underground permanent service to
structure
C. Single phase, 120/240 service
Three-wire underground (padmount transformer)
1) Permanent connection to structure $1,155
2) Temporary connection to customer-owned
power pole; removal of same and installation $1,418
of underground permanent service to
structure
2
Section 3. If no protest is made pursuant to Public Utilities Code Section 16078, then this
ordinance shall be effective thirty days after adoption by the board of directors of the District.
Section 4. The Clerk of the District shall immediately cause a copy of this ordinance to be
published in a newspaper of general circulation and posted in three places within the District.
Section 5. The provisions of other Ordinances shall remain if effect to the extent that they do not
conflict with this ordinance.
PASSED AND ADOPTED by the Board of Directors of the Truckee Donner Public Utility District at a
meeting duly called and held within the District on the seventeenth day of December 2003 by the
following roll call vote:
AYES: Directors Aguera, Hemig, Maass, Sutton and Van Gundy
NOES:None
ABSENT: None
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
By
S 5
Jame . Maass, President of the Board
ATTEST:
Peter L. Holzmeister, Clerk of the Board