Resolution No. 2009 - 41
AUTHORIZING THE ACCEPTANCE OF
DISTRICT PIPELINE REPLACEMENT — 2009 PROJECT — CONTRACT C
AND DIRECTING FILING OF THE NOTICE OF COMPLETION
WHEREAS, the Board of Directors of the Truckee Donner Public Utility District made the determination to
undertake the District Pipeline Replacement—2009 Project—Contract C; and
WHEREAS, Cruz Excavating Inc was selected by the District to perform the work; and
WHEREAS, Cruz Excavating Inc has completed all of the work included in the Project; and
WHEREAS,the District's Water System Engineer, Neil Kaufman, now certifies the completion of the project;and
WHEREAS,the District's Water Utility Manager, Ed Taylor,has recommended that the work be accepted by the
District;
NOW THEREFORE BE IT RESOLVED by the Board of Directors of the District as follows:
1. That the District hereby accepts the District Pipeline Replacement—2009 Project—Contract C as
complete.
2. That the Clerk of the District be directed to file with the County of Nevada the Notice of Completion, a
copy of which is attached hereto.
3. That 35 days following the filing of the Notice of Completion, the monies retained from the contractor
payments be released to the contractor if no claims have been made to the District by material suppliers,
laborers or sub-contractors.
PASSED AND ADOPTED by the Board of Directors at a meeting duly called and held within the District on the
sixteenth day of December 2009 by the following roll call vote:
AYES: Directors Aguera, Bender, Hemig and Hillstrom
NOES: None
ABSTAIN: None
ABSENT: Director Sutton
TRUC N R PU UTILITY DISTRICT
By
Jeff Be die esid mot- he Boa -
ATTEST:
Michael D. Holley, Clerk of the Board
RECORDING REQUESTED BY:
12-319-0 ��0 ::3 LVV
Truckee Donner Public Utility District Nevada County Recorder
Gregory J. Diaz
WHEN RECORDED, RETURN TO: Document#: 20090034321
Thursday December 24 2009,at 03:53:46 PM
TRUCKEE DONNER PUBLIC UTILITY DISTRICT
Post Office Box 309 Paid: CP
Truckee, CA 96160
THE UNDERSIGNED DECLARES
DOCUMENTARY TRANSFER TAX-NONE
LJ
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN:
1. That the name and address of the public entity for whom the improvement project was done, as owner
thereof, is the Truckee Donner Public Utility District, Post Office Box 309, Truckee, CA 96160.
2. Nature of interest or estate of owner: beneficial interest of a public utility easement for installation of water
facilities.
3. That on December 16t", 2009 the hereinafter described improvements were accepted as complete
pursuant to Resolution 2009-41 of the Truckee Donner Public Utility District, the awarding authority.
.., 4. That the subject improvements of the Notice are generally described and identified as follows: District
Pipeline Replacement— 2009 Project— Contract C — Chamonix Road, Donner View Tank site,
Innsbruck Tank site and Rhineland Ave, Truckee, California.
5. That the name and address of the contractor for such project was: Cruz Excavating Inc, P.O. Box
3269, Incline Village 89450
I certify under penalty of perjury under the laws of the State of
California that the foregoing is true and correct.
Dated.: TRUCKEE DONNER PUBLIC UTILITY DISTRICT
By - //",,.
Michael D. Holley, General Manager
MAIL TAX STATEMENTS TO:
SAME AS ABOVE
Legal References: CC-3093,CCP-2003(oath), 2015.5(unsworn statement)
Change Order
Contract Name: District Pipeline Replacement—2009—Contract C
Contract Change Order No: 4 Orig. Contract Amt. $ 656,993.00 Days NA
Date: December 16, 2009 Prev.Apprd Changes $ -203,004.25 Days NA
Contractor: Cruz Excavating, Inc. This Change$ 53,304.18 Days NA
Revised Contract Amt. $ 507,292.93 Days NA
This Change Order covers changes to the subject Contract as described herein. The Contractor shall construct,
furnish equipment and materials, and perform all work as necessary or required to complete the Change Order
Items for a lump sum price agreed upon between the Contractor and District.
Increase in (Decrease) Contract Time
Contract in Contract Extension
Description of Changes Amount $ Amount $ (days)
1 —Bid vs.Actual Quantities $1,645.97 NA
2—Leaking Water Mains $7,730.88 NA
3—Mismarked Utilities $922.50 NA
0-owl.. 4—Removing Brush from Project Site $1,020.00 NA
5—Laterals through Landscaping $1,310.82 NA
6—Additional Pavement Thickness on Rhineland and
Chamonix $25,716.80 NA
7—Adjustment for District Supplied Materials on Chamonix
(Change Order No. 3) $957.21 NA
8—Deletion of Credit for District Furnished Materials on
West Reed (Original Bid $14,000.00 NA
Totals $53,304.18 NA
Net change in contract amount(increase or decrease) $53,304.18 NA
The amount of the Contract will be increased by the sum of $53,304.18 and the Contract Time shall not be
extended. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the
contract price specified for each item including any and all supervision costs and other miscellaneous costs
relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on
account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other
necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete
the Change order items. This document will become a supplement of the contract and all provisions will apply
hereto. It is understood that the Change Order shall be effective when approved by the District.
Accepted: /Contractor Date: 1z i 10iJo
(Signature)
Approved: /District Date:
(Signature)
Page 1
Attachment 1
Analysis of Bid Quantities vs.Actual Quantities Constructed
District Pipeline Replacement-2009-Contract C
Contractor: Cruz Excavating
Bid Amounts Actual Amounts
Biq)b-►n Description Quantity Units I Unit Price Subtotal Quantity Units Unit Price Subtotal
Mobilization 1 LS $ 30,000.00 $ 30,000.00 1 LS $ 30,000,00 $ 30,000.00
1A 8"Water Main 843 FT $ 33.00 $ 27,819.00 850 FT $ 33.00 $ 28,050.00
1B 1.5'PE Water Service Lateral 240 FT $ 22.30 $ 5,352.00 274 FT $ 22.30 $ 6,110.20
1C Double Water Service 8 EA $ 1,700.00 $ 13,600.00 9 EA $ 1,700.00 $ 15,300.00
1 D Fire Hydrant Assembly 2 EA $ 4,800.00 $ 9,600.00 2 EA $ 4,800.00 $ 9,600.00
1 E Connection to Existing 6"Gate Valve at Station 0+00 1 LS $ 1,800.00 $ 1,800.00 1 LS $ 1,800.00 $ 1,800.00
1 F Connection to Existing 6"Piping at Station 8+43.13 1 LS $ 1,750.00 $ 1,750.00 1 LS $ 1,750.00 $ 1,750.00
1G Rock Excavation 5 HRS $ 550.00 $ 2,750.00 0 HRS $ 550.00 $ -
1 H A.C.Pavement and Base 5,200 SF $ 4.40 $ 22,880.00 5,166 SF $ 4.40 $ 22,728.77
11 All Other Work Required by the Contract Documents 1 LS $ 2,500.00 $ 2,500.00 1 LS $ 2,500.00 $ 2,500.00
2A 8"Water Main 2,402 FT $ 31.00 $ 74,462.00 2,400 FT $ 31.00 $ 74,400.00
2B 1.5"PE Water Service Lateral 780 FT $ 24.75 $ 19,305.00 873 FT $ 24.75 $ 21,606.75
2C Single Water Service 1 EA $ 1,200.00 $ 1,200.00 0 EA $ 1,200.00 $ -
2D Double Water Service 25 EA $ 1,500.00 $ 37,500.00 24 EA $ 1,500.00 $ 36,000.00
2E Fire Hydrant Assembly 4 EA $ 4,300.00 $ 17,200.00 5 EA $ 4,300.00 $ 21,500.00
2F 1"Air Valve Assembly 1 EA $ 2,900.00 $ 2,900.00 1 EA $ 2,900.00 $ 2,900.00
2G Connection to Existing 6"Piping at Station 0+00 1 LS $ 1,450.00 $ 1,450.00 1 LS $ 1,450.00 $ 1,450.00
?"- TeeNalve Assembly at Station 12+13 1 LS $ 1,900.00 $ 1,900.00 1 LS $ 1,900.00 $ 1,900.00
Tee/Valve Assembly at Station 23+67 1 LS $ 9,000.00 $ 9,000.00 1 LS $ 9,000.00 $ 9,000.00
2J Connection to Existing 8"Piping at Station 24+01.90 1 LS $ 1,300.00 $ 1,300.00 1 LS $ 1,300.00 $ 1,300.00
2K Rock Excavation 12 HRS $ 550.00 $ 6,600.00 0 HRS $ 550.00 $ -
2L A.C.Pavement and Base 15,350 SF $ 4.40 $ 67,540.00 17,100 SF $ 4.40 $ 75,240,00
2M All Other Work Required by the Contract Documents 1 LS $ 5,000.00 $ 5,000.00 1 LS $ 5,000.00 $ 5,000.00
Innsbruck
3 Skis►ope Work Deleted in Change Order No.3
4A Tank Site Utilities 1 LS $ 50,000.00 $ 50,000.00 1 LS $ 50,000.00 $ 50,000.00
46 Rock Excavation 2 HRS $ 500.00 $ 1,000.00 0 HRS $ 500.00 $ -
4C 3" Thick A.C.Pavement with Fibers and Base 460 SF $ 4.25 $ 1,955.00 404 SF $ 4.25 $ 1,717.00
4D All Other Work Required by the Contract Documents 1 LS $ 1,500.00 $ 1,500.00 1 LS $ 1,500.00 $ 1,500.00
Donner View
5A Tank Site Utilities 1 LS $ 35,000.00 $ 35,000.00 1 LS $ 35,000,00 $ 35,000.00
513 Rock Excavation 2 HRS $ 550.00 $ 1,100.00 0 HRS $ 550.00 $ -
5C 3"Thick A.C.Pavement with Fibers and Base 3,000 SF $ 4.25 $ 12,750.00 2,825 SF $ 4.25 $ 12,006.25
5D All Other Work Required by the Contract Documents 1 LS $ 1,000.00 $ 1,000.00 1 LS $ 1,000.00 $ 1,000.00
6 West Reed Work Deleted in Change Order No.3
$ 467,713.00 $ 4- 358.97